🧰 How to Draft an NEC3 Contract – A Practical Guide

NEC3 Contract

NEC3 Contract

🏗️ What Is the NEC3 Engineering and Construction Contract (ECC)?

The NEC3 ECC is the go-to contract when you’re hiring a contractor to carry out construction or engineering work. That could be:

  • Building roads, bridges, or buildings 🏢
  • Infrastructure upgrades 🛤️
  • Projects where the contractor has some design responsibility too ✏️

The ECC is ideal when you want to drive good management, collaboration, and timely delivery. It’s not just a legal document—it’s a project management tool in disguise.

And here’s the cool part: it’s drafted in plain English, which is rare for a contract. No “wherefores” or “heretofores” here. Just simple, direct language that everyone on the team can understand.

NEC3 Contract Explained: Step-by-Step Guide to Drafting Like a Pro (Part 1)

🧭 Step 1: Choose the Right NEC3 Contract – Set the Foundation Right!

Before you even think about payment options or legal clauses, you need to choose the right contract from the NEC3 family. This is the foundation of your entire project agreement. Get this right, and you’re off to a smooth start. 🚀

So, what is the NEC3 ECC all about?


💡 Why Is NEC3 ECC So Popular?

According to the document, the NEC3:

It’s even officially recommended by the UK government’s Office of Government Commerce (OGC) for public sector work.


🧩 Is ECC the Right NEC Contract for Your Project?

Here’s a quick test:

QuestionIf yes…
Are you hiring a contractor to build something?✔️ You need the ECC
Will the contractor have design responsibility for any part?✔️ ECC supports that too
Do you want a contract that’s clear, flexible, and management-friendly?✔️ ECC is built for that!

If your answers are mostly “yes,” then boom—you’re in the right place. ✅


🧱 What’s in the ECC Structure?

Now that you’ve picked the ECC, here’s what it includes:

ComponentWhat It Does
🔹 Core ClausesAlways included—covering general rules, payment, defects, time, termination, etc.
🔸 Main Option ClausesYou choose 1 (A–F) based on your pricing strategy
🔹 Secondary Options (X/Y/Z)Optional add-ons for things like delay damages, bonds, or special conditions
📊 Contract DataProject-specific info provided by Employer and Contractor
📘 Works Info & Site InfoTells the Contractor what to do, and what they’re working with
💰 Schedule of Cost ComponentsUsed to calculate costs for compensation events or cost-based contracts

Each piece plugs together like a contract Lego set 🧱—customizable but with structure.


🏁 Wrapping Up Step 1: Your Takeaway

So in plain terms:

If you’re hiring someone to construct or engineer something (with or without design responsibility), the NEC3 ECC is the contract you want.

It’s collaborative, clear, and flexible—and it forms the backbone of thousands of successful projects.

💸 Step 2: Pick a Main Option – How Will You Pay the Contractor?

Once you’ve chosen the NEC3 Engineering and Construction Contract (ECC), the next key decision is choosing your Main Option. This choice sets the foundation for how payments will be managed, how cost risk is shared, and how much flexibility you’ll have as the project evolves.

Let’s walk through this step-by-step—engaging, jargon-free, and crystal clear. ✅


🧩 What Is a “Main Option”?

The NEC3 ECC offers six Main Options, labeled A through F. Each one represents a different payment mechanism and risk allocation strategy.

But here’s a vital point:

💡 Your choice of Main Option has nothing to do with who does the design.
Design responsibility is handled separately in Clause 21 and your Works Information. So even if the Contractor is doing the detailed design, you can still use any Main Option—as long as the payment method suits your project.


🧾 Summary Table – All Six Options

OptionNameHow It WorksBest For
APriced contract with Activity Schedule 🧱Contractor is paid a lump sum per activity. Activities must be fully complete and defect-free.Projects with defined scope, including design-and-build
BPriced contract with Bill of Quantities 📏Payment based on actual quantities installed × fixed rates. Final cost may vary.Traditional BoQ-based contracts or civils works
CTarget contract with Activity Schedule 🎯Parties agree a target price and share cost savings or overruns based on actual cost.Collaborative projects aiming for shared risk/gain
DTarget contract with Bill of Quantities ⚖️Same as Option C, but based on measured quantities.Infrastructure jobs needing both remeasurement and cost-sharing
ECost reimbursable 💳Contractor is paid actual Defined Cost + fee—no fixed price upfront.Complex, uncertain, or fast-tracked projects
FManagement contract 🛠️Contractor manages the works (done by subcontractors), paid actual cost + fee.Employer-led, multi-package projects

🔍 Option A: Priced Contract with Activity Schedule

This is one of the most commonly used options—and yes, it works even when the contractor is doing the detailed design.

💡 How It Works:

✅ When to Use It:

🧠 Just make sure your Works Information clearly states which parts of the design the contractor is responsible for (see Clause 21 in the ECC).


📏 Option B: Priced Contract with Bill of Quantities

Here, the pricing is still fixed, but payments are tied to measured quantities.

🧮 How It Works:

✅ When to Use It:


🎯 Option C: Target Contract with Activity Schedule

This brings in a shared risk/reward model.

💡 How It Works:

✅ When to Use It:

🧱 Option C is often used in design and build projects where cost certainty is helpful, but flexibility is still needed.


📐 Option D: Target Contract with Bill of Quantities

Basically Option C + BoQ.

This suits infrastructure projects with complex site conditions and potential quantity changes.


💳 Option E: Cost Reimbursable Contract

The most flexible—and riskiest—option.

🛠️ How It Works:

✅ When to Use It:


🧑‍🏭 Option F: Management Contract

Here, the contractor manages, but doesn’t carry out, the works.

🏗️ Best for large-scale, multi-package projects where you want oversight but not direct trade management.


✍️ A Word on Design Responsibility

In NEC3 ECC, design roles are defined by the Works Information and Clause 21, not by the Main Option.

So if your project is:

✅ Then any Main Option can be used, including Option A or C.

Just be sure your Works Information includes wording like:

“The Contractor shall complete the detailed design for the structural and MEP elements based on the Employer’s concept drawings provided in Appendix X.”


🎁 Final Tips

DoDon’t
Align payment method with project riskAssume design responsibility = a fixed option
Define Contractor design scope clearlyLeave Activity Schedules vague or incomplete
Use Activity Schedule or BoQ carefullyMix Main Options together

✅ In Summary:

Pick your Main Option based on how you want to manage payment and risk—not based on who does the design.

⚖️ Step 3: Choose a Dispute Resolution Option – Just in Case Things Get Bumpy

Alright, you’ve picked your NEC3 contract form, selected your Main Option for payment (nice work! 🧱), and now it’s time to think ahead… way ahead.

Let’s talk about disputes.

Not because we want them to happen—but because if they do, you’ll want a clear, agreed process for resolving them. That’s where NEC3’s dispute resolution options come in.


🧠 So What Are These Options?

In NEC3 ECC, you must choose one dispute resolution option from the W options:

OptionNameUse When…
W1Dispute resolution procedure (non-HGCRA projects)Use when the UK’s Housing Grants, Construction and Regeneration Act 1996 (HGCRA) does not apply
W2Dispute resolution procedure (HGCRA-compliant)Use for UK projects where HGCRA does apply (e.g., most UK construction jobs)

➡️ In short:

If your project is in the UK and HGCRA applies, choose W2.
If it’s international or HGCRA doesn’t apply, go with W1.


📜 What Is the HGCRA?

The Housing Grants, Construction and Regeneration Act 1996 (aka HGCRA) is UK legislation that gives parties in construction contracts the right to adjudication—a fast-track process for resolving disputes.

🛡️ NEC3 W2 is designed to comply with HGCRA. If your project falls under UK law and the Act applies, you legally need a compliant procedure like W2.


🔍 Let’s Look at Each Option

⚖️ Option W1 – Use Outside the UK (or Where HGCRA Doesn’t Apply)

🔹 Key Features:
🔹 Process (Simplified):
  1. A party notifies the other that a dispute has arisen.
  2. The dispute goes to the Adjudicator—who must decide within 28 days (can be extended by agreement).
  3. The Adjudicator’s decision is binding until overturned by the tribunal.

🧠 Good to know: You choose whether the tribunal is arbitration or litigation in the Contract Data.


⚖️ Option W2 – Use in the UK (HGCRA-Compliant)

This one follows the same structure as W1 but adds some HGCRA-specific rules, such as:

🔹 Process Highlights:

🛑 If you don’t choose W2 for a UK construction project, your contract could be non-compliant with UK law. Yikes!


🧑‍⚖️ Who Is the Adjudicator?

The Adjudicator is a neutral person named in the Contract Data—or chosen via a process also stated there.

NEC3 emphasizes that the Adjudicator must:

👉 The Contract Data will usually include:

💡 Tip: If you don’t name an Adjudicator in advance, at least agree on a nominating body—this prevents disputes about how to resolve your disputes! 😅


🧾 What Goes in the Contract Data?

When filling out the Contract Data, you’ll need to include:

Example (W2 setup):

W Option Selected: W2
Adjudicator: Jane Doe, FCIArb
Nominating Body: Chartered Institute of Arbitrators
Tribunal: Court proceedings

✨ Real-World Example

Imagine your UK-based project hits a snag: the contractor believes they’re owed a compensation event payment. The Project Manager disagrees. A dispute arises. 🚧

Thanks to W2, either party can trigger adjudication. A neutral Adjudicator is brought in and gives a decision within 28 days—keeping the project on track while preserving the right to challenge the outcome later through court.

🎯 It’s fast, clear, and designed to avoid work grinding to a halt.


✅ Final Thoughts – Choosing Wisely

🔍 Question💡 Your Answer
Is your project in the UK and covered by HGCRA?Choose W2
Is your project international or non-HGCRA?Choose W1
Do you want to name an Adjudicator up front?You can (recommended!)
Prefer flexibility?At least name a nominating body instead
Litigation or arbitration?Pick one in the Contract Data for final tribunal

🧩 In Summary

Disputes might never happen—but if they do, NEC3 gives you a streamlined, fair, and legally sound path to resolution.

Choose W1 or W2 depending on the law that governs your project.
✍️ Then fill in the Contract Data to name your Adjudicator or at least the body who will appoint them.

🧩 Step 4: Choose Secondary Options – Plug and Play Your Contract 📦

You’ve nailed the big decisions so far: you’ve chosen your NEC3 contract form, picked a Main Option to handle payments, and selected how to manage disputes. Nice work! 👏

Now it’s time to customize your contract with Secondary Option Clauses—also known as the “X, Y, and Z” options.

Think of these as your plug-ins or add-ons. They’re optional, but they let you tweak the contract to reflect real-world risks, project-specific needs, and legal requirements.

Let’s walk through it together. 😊


🧠 What Are Secondary Options?

Secondary Options are modular clauses that you add only if you need them. They cover things like:

They’re grouped into:

You can include as many as you need—but don’t overload your contract. ⚠️


📦 X Options – The Most Common Add-Ons

Let’s break down the key X Options listed in your NEC3 document (Section: Secondary Option Clauses, starting page 57):

ClauseNameWhat It DoesWhen to Use It
X1Price Adjustment for InflationAdjusts prices if inflation rises during the projectLong-term projects, or high inflation risk
X2Changes in the LawAllows price/time adjustment if legal changes affect the worksFor public contracts or work in changing legal environments
X3Multiple CurrenciesAllows payment in more than one currency (Options A & B only)International contracts or cross-border suppliers
X4Parent Company GuaranteeRequires the contractor’s parent company to guarantee performanceContractor is a subsidiary, or financial assurance is needed
X5Sectional CompletionSplits Completion into sections with their own Key Dates and Completion DatesComplex phasing, partial handovers, or multi-stage projects
X6Bonus for Early CompletionPays the contractor a bonus for finishing before the Completion DateYou want to incentivize speed
X7Delay DamagesSets daily damages if the contractor is lateYou want protection against late delivery
X12PartneringEncourages collaborative behaviours and joint workingFrameworks, alliances, or high-trust projects
X13Performance BondRequires a financial bond to cover performance risksFinancial reassurance, especially on large-value contracts
X14Advanced Payment to the ContractorAllows for upfront payments, usually in return for a bondWhere early cashflow is essential
X15Limit on Liability for DesignLimits the contractor’s design liability to reasonable skill and careWhen contractor has design responsibility
X16RetentionApplies retention percentage to interim payments (not used with Option F)Standard practice in many UK construction projects
X17Low Performance DamagesDamages for when the works underperform (e.g., energy efficiency shortfall)Performance-critical projects (e.g., sustainability targets)
X18Limitation of LiabilityCaps the contractor’s overall liability under the contractHigh-risk contracts or to encourage tendering
X20Key Performance Indicators (KPIs)Tracks KPIs, which may be linked to incentives or bonusesYou want to measure and reward performance

👉 NEC3 gives you this flexibility without having to draft custom clauses—just tick the right boxes in the Contract Data, and the clause is activated.


⚖️ Y Options – Legal Requirements (Jurisdiction-Specific)

These clauses handle compliance with national law. From your document:

ClauseNameWhat It Covers
Y(UK)2The Housing Grants, Construction and Regeneration Act 1996Ensures compliance with UK construction law (adjudication, payment rules)
Y(UK)3The Contracts (Rights of Third Parties) Act 1999Clarifies whether third parties have contract rights

🧠 Use Y(UK)2 if you’re using W1 on a UK construction project (though most will use W2).
Use Y(UK)3 if you want to exclude or include third-party rights explicitly.


🛠️ Z Option – Custom Amendments (Handle with Care!)

This is your “wild card” option—used when the Employer wants to add or tweak something not covered in the standard contract.

For example:

🛑 But be careful! Once you start editing NEC3 with Z clauses:

✅ Best practice? Keep Z clauses minimal and have them reviewed by a legal advisor.


🎯 How to Choose the Right Secondary Options

Here’s a practical checklist:

✅ Question🔍 Suggestion
Do you want to protect against delays?Use X7 (Delay Damages)
Want to reward early delivery?Add X6 (Bonus for Early Completion)
Need part-handover or phased completion?Use X5 (Sectional Completion)
Concerned about inflation?Include X1 (Price Adjustment)
Sharing design responsibility with the Contractor?Add X15 (Reasonable skill & care limit)
Need extra financial protection?Use X13 (Performance Bond) or X4 (PCG)
Project must comply with UK laws?Include Y(UK)2 and/or Y(UK)3

✍️ Filling Out the Contract Data

Each Secondary Option has associated blanks in the Contract Data, where you’ll fill in:

📌 Tip: Don’t activate an X Option unless you complete its info in the Contract Data. A clause without data is just confusion waiting to happen.


✅ Final Thoughts – Customize With Care

Secondary Options are your contract’s tuning tools. They let you:

But more isn’t always better.

🧠 Choose only what you need. Use the core clauses by default, and layer in extras when the project demands it.

🧾 Step 5: Fill in the Contract Data – Make It Your Own

The Contract Data is a critical section of the NEC3 ECC. It sits right after the core clauses and options you’ve chosen, and it’s where the abstract contract becomes a real, working agreement tailored to your project.

You don’t need to be a lawyer to complete it—but you do need to be precise.


🧩 The Contract Data Is Split Into Two Parts:

PartWho Fills It OutWhat’s Included
Part OneThe EmployerProject details, dates, options selected, delay damages, insurance, etc.
Part TwoThe ContractorContractor’s people, design responsibilities, working areas, and other commitments

📘 Part One – What the Employer Must Complete

Here’s what you’ll need to fill in as the Employer:

1. 📛 General Details

2. 🗓️ Key Dates

🔔 These are the dates against which progress, delay damages, and bonuses are measured. Be accurate!

3. 📜 Names and Roles

💡 These roles are fundamental under NEC3—they drive communication, assessment of compensation events, and quality checks.

4. 📊 Payments and Damages

5. 🛡️ Insurance Requirements

📌 These must align with the project’s risk profile. High-value projects often demand higher coverage.


🧑‍🔧 Part Two – What the Contractor Must Complete

Here’s what the Contractor fills in:

1. 🧑‍💼 Key Personnel

🧠 These people are often part of contract performance—replacing them may need Project Manager approval.

2. ✍️ Design Responsibilities

💡 If this is a design-and-build job, this section confirms who’s doing what (and when).

3. 🚧 Working Areas

This affects:

4. 🧾 Subcontracting

5. 📅 Proposed Programme Info


🧠 Tips for Filling in the Contract Data

✅ Do…❌ Don’t…
Be precise and specificLeave sections blank
Ensure Contract Data matches Works InfoLet Contract Data contradict other documents
Define realistic dates and durationsUse rough estimates or vague phrases
Align insurances with real-world project riskForget to verify actual policies with brokers
List key people with correct rolesLeave out CVs or approval requirements

📝 Example Snippets

Delay Damages:

Delay damages: £3,000 per day
Completion Date: 1 October 2025

Design Responsibility:

The Contractor is responsible for all detailed design for the structural, MEP, and architectural packages, based on the Employer’s concept design provided in Appendix A.

Insurance:

Contractor must carry:
- Works Insurance: £10 million
- Third Party Liability: £5 million
- Professional Indemnity: £2 million (if applicable)

🧩 Final Thoughts – Don’t Skip the Details

The Contract Data is where your project’s rules get real.

It connects the dots between:

Fill it out carefully, cross-check it with your Works Information, and make sure everything lines up—this is what keeps NEC3 working like the well-oiled machine it’s meant to be. ⚙️

📘 Step 6: Create the Works Information – Tell the Contractor What’s What

In NEC3, the Works Information is like your project’s instruction manual. It’s not legal fluff—it’s a practical, working guide that tells the contractor:

This section replaces the old-fashioned “employer’s requirements” or “specification” from traditional contracts—and it’s way more powerful when done right.


🧩 Where Does It Fit in the Contract?

The Works Information is one of the NEC3 Contract Documents, alongside:

It’s referenced by multiple NEC3 clauses, especially:


✍️ What Should the Works Information Include?

There’s no fixed format—but NEC3 suggests it should include everything the contractor needs to know to:

Here’s a helpful checklist:

✅ 1. Scope of Works

✅ 2. Design Requirements

If the Contractor is doing the design (Clause 21 applies), you must:

🧠 Tip: Be clear whether the Contractor must use reasonable skill and care or fitness for purpose—this is often supported by X15 or Z clauses.

✅ 3. Technical Specifications & Standards

📌 Be specific. Vague phrases like “good quality” or “industry standard” often lead to disputes.

✅ 4. Method or Process Constraints

✅ 5. Access & Interface Information

✅ 6. Health, Safety & Environmental Requirements

✅ 7. Testing, Inspection, and Handover

✅ 8. Workmanship, Materials, and Products


🧠 Real-World Example: Design and Build School

Let’s say the Employer provides a concept design for a new school. In the Works Information, you might write:

“The Contractor shall develop and complete the detailed design and construction of the building, based on the Employer’s concept layout and functional requirements. The building must comply with BB103 and BB93 standards, achieve a BREEAM ‘Very Good’ rating, and provide full MEP coordination.”

🧰 You’d attach:


⚠️ Common Mistakes to Avoid

❌ Mistake✅ Better Practice
Vague scope or missing detailsUse clear, detailed specs and drawings
Conflicting documents (e.g., old specs)Cross-check everything before issue
Forgetting contractor design dutiesState them clearly under Clause 21
Using generic terms like “best practice”Reference actual standards and outcomes

📋 Pro Tip: Align With the Contract Data

Your Works Information must align with what’s in:

🎯 Consistency avoids conflict.


✅ Final Thoughts – Clarity = Control

The Works Information is your best tool to set expectations and control quality, time, and cost.

Get it right, and the Contractor knows exactly what’s expected.
Get it wrong—or leave it vague—and you open the door to misunderstandings, arguments, and compensation events galore. 😬

🗺️ Step 7: Prepare the Site Information – Help the Contractor Know the Terrain

Think of Site Information as the contractor’s reality check. While the Works Information tells them what to build, the Site Information tells them what they’re walking into.

It’s essentially:

“Here’s what we (the Employer) know about the site. Use this to price and plan your work.”

Providing this information is a requirement under NEC3. It’s referred to directly in:


📘 What Exactly Is Site Information?

According to NEC3, Site Information is:

“Information which describes the site and its surroundings and is in the documents which the Employer has stated in the Contract Data to be Site Information.”

In simpler terms:

It’s everything the Employer knows about the physical site conditions, boundaries, risks, utilities, and legal/environmental constraints.

The idea is transparency. You give the contractor a factual baseline so they can plan, price, and deliver the works safely and efficiently.


🧩 What Should Be Included in Site Information?

There’s no strict format, but here’s a checklist of what’s typically included:

✅ 1. 📍 Site Location and Access

🧠 Especially useful if the site is shared with the public, existing tenants, or other contractors.


✅ 2. 🌍 Ground Conditions

This is crucial. If ground conditions are materially different from what’s in Site Information, it could be a compensation event under Clause 60.1(12).


✅ 3. 🛠️ Existing Structures or Services

📌 Attach utility search records and drawings from previous investigations.


✅ 4. 🧱 Existing Surveys or As-Built Info

Even if reports are several years old, include them—just mark their date and status clearly.


✅ 5. ⚠️ Known Site Hazards or Restrictions

If you already know there’s a bat roost, don’t wait for the contractor to find out mid-roofing. 🦇


✅ 6. 📜 Legal and Statutory Constraints

These impact what the contractor can or can’t do on site, and when.


📄 Example Excerpt – Site Information Schedule

Document Title                          | Description                                     | Status
-------------------------------------- | ----------------------------------------------- | ------------------------
Topographical Survey – Ref TS/014 | Site levels and boundary positions | Verified, March 2023
Utilities Search – Linesearch Report | Locations of gas/electric/telecoms | Supplied by utility providers
Ground Investigation – GI Report 2022 | Soil type, rock, water table data | Summary only; full logs in Appendix B
Tree Protection Plan – TP/19 | Locations of protected trees | Mandatory buffer zones identified
CCTV Drainage Survey – DR/05 | Layout and condition of existing drainage | For information only; no guarantee

⚠️ Risks of Poor Site Information

If you leave this vague or incomplete, you risk:

🎯 Good Site Information = better pricing, fewer surprises.


✅ Tips for Creating Great Site Information

✅ Do…❌ Don’t…
Include all surveys, even if oldAssume “the contractor will find out later”
Clearly mark documents as “for info” or “verified”Leave status or assumptions ambiguous
Reference Site Information in the Contract DataForget to list documents officially
Provide digital formats for drawings/dataRely on hard copies alone

📌 Where Does Site Information Sit in the Contract?

It’s formally listed in the Contract Data Part One under:

“The documents which the Employer has stated to be Site Information are…”

That list becomes legally binding—so if it’s not listed there, it doesn’t count as Site Information.


✍️ Final Thoughts – The Site Tells a Story

Site Information tells the contractor everything they should reasonably know before starting work.

It’s not about protecting the employer from risk—it’s about giving the contractor a fair shot at planning and pricing the job properly.

The more transparent and accurate your Site Information is, the smoother your project will run.

💵 Step 8: Prepare the Pricing Document – Show Me the Money!

The NEC3 ECC doesn’t use a one-size-fits-all approach when it comes to pricing. Instead, the type of pricing document depends entirely on the Main Option you selected in Step 2.

So before we dive in, let’s quickly recap what you picked:

Main OptionType of Pricing Document You Need
Option AActivity Schedule 🧾
Option BBill of Quantities (BoQ) 📏
Option C/DTarget price with Activity Schedule or BoQ
Option E/FSchedule of Cost Components (plus Fee %) 💰

Once you’ve confirmed your option, here’s how to build the right pricing doc.


📋 Option A: Activity Schedule (Used in A & C)

An Activity Schedule is a list of all the contractor’s activities, each with a lump sum price attached.

✅ Key Features:

🧱 Example Format:

Activity No.DescriptionPrice (£)
1Mobilisation5,000
2Site setup and access roads10,000
3Foundation works25,000
4Structural steel erection40,000
5MEP first fix15,000

🧠 Keep the descriptions aligned with what’s in your Works Information.

💡 Pro Tip:

The more detailed your activity descriptions are, the easier it is to track progress and approve payments.


📏 Option B: Bill of Quantities (Used in B & D)

This is the more traditional pricing document, especially for civil and infrastructure jobs.

✅ Key Features:

📐 Example Format:

Item No.DescriptionUnitQtyRate (£)Total (£)
1Excavation to formation50015.007,500
2Reinforced concrete base20090.0018,000
3Brickwork to plinth walls12045.005,400

📌 Remeasurement applies here—final payment depends on what’s actually done on site.


💰 Option E & F: Schedule of Cost Components (SCC) + Fee %

In these options, the Contractor is reimbursed actual costs plus a pre-agreed fee.

You’ll need:

SCC Covers:

🧮 Payment is based on:

Defined Cost + Fee
Where “Defined Cost” is carefully calculated using time sheets, invoices, etc.

📊 Example Entry:

Project Manager reviews Contractor’s records weekly. Defined Cost includes site workers’ wages, plant hire, subcontractor invoices, and site accommodation hire.
Fee: 10%

📌 This is an open-book model—great for transparency, but requires tight cost control.


📉 Risk of Poor Pricing Docs

If your Pricing Document isn’t well-structured:


✅ Best Practices for Pricing Documents

✅ Do…❌ Don’t…
Align pricing document with Works InformationCreate pricing items that don’t match the scope
Be specific in descriptions and unitsUse “catch-all” terms like “general works”
Cross-check totals with Contract DataAssume accuracy—double check every figure
Get contractor input for Activity ScheduleDictate items without coordination
Link to programme (especially under Option A)Forget to update if programme changes

✍️ Final Thoughts – Price with Purpose

Your Pricing Document is more than a spreadsheet—it’s your financial playbook.

Whether you’re working with fixed sums or reimbursable costs, it needs to be:

The clearer your pricing document is, the fewer payment disputes you’ll face, and the smoother your monthly assessments will be.

🔍 Step 9: Final Review and Consistency Check – Tie It All Together

By now, you’ve drafted:

But here’s the thing…

Even one small inconsistency—like a date mismatch or conflicting scope—can lead to delays, confusion, or disputes down the road. 😬

That’s why this consistency check is so important. It’s your contract quality control pass. Let’s walk through exactly what to review.


✅ What Should You Check?

Here’s your NEC3 contract review checklist. Think of it like doing a “snag list” for your paperwork before letting work start on site.


1. 📅 Are All the Key Dates Aligned?

⚠️ If Works Info says work starts 1 May, but Contract Data says 15 May—you’ve got a problem.


2. 🔢 Do the Payment Mechanisms Match?

✅ Double-check that:


3. 📘 Is the Scope Clear and Consistent?

💡 Ambiguity = claims. Clarity = control.


4. 🗺️ Is the Site Information Correct and Complete?

🎯 If you want to avoid Clause 60.1(12) compensation events, be clear about what’s assumed and what’s guaranteed.


5. 🧩 Are Your Secondary Options Activated Properly?

📌 Example: If you use X5 (Sectional Completion), your Works Information must define each section and its Key Dates clearly.


6. 🛡️ Are Insurances and Bonds Fully Defined?


7. 📊 Is the Contract Data Fully Complete?

✅ Remember: anything left blank in the Contract Data is a potential ambiguity—and in NEC, clarity is king. 👑


8. 📚 Have You Included All Referenced Documents?

Check that:

📎 Missing attachments are a major source of delay post-award.


✅ Final Thoughts – Check Twice, Sign Once

This is your “golden hour” before the contract is signed.
A few hours of careful checking now can save weeks (or months) of delay and disagreement later.

Use this moment to:

Then—and only then—move on to Step 10: Sign the Contract and Issue Copies.

✍️ Step 10: Sign the Contract and Issue Copies – Make It Official

You’ve done the heavy lifting: you’ve chosen the contract type, set the rules, defined the scope, priced the works, and checked everything twice. Now it’s time to sign the deal and get ready for site mobilization. 🖊️📁

But don’t rush—signing an NEC3 contract isn’t just about putting pen to paper. It’s also about ensuring that everyone has the same version of the documents and that all parties are clear on their commitments from Day 1.

Let’s walk through the final step the right way.


✅ What Needs to Be Signed?

You’ll be signing the entire contract suite, including:

DocumentWho Signs It?
NEC3 Engineering and Construction Contract (ECC)Employer and Contractor
Contract Data Part OneEmployer
Contract Data Part TwoContractor
Pricing Document (Activity Schedule / BoQ / SCC)Usually initialled by both
Works InformationEmployer and acknowledged by Contractor
Site InformationEmployer
Secondary Options (if bespoke, e.g. Z clauses)Employer and Contractor

💡 If you’ve included any Z clauses, they should be reviewed by legal advisors and signed too.


🧾 Before You Sign: Last-Minute Checks

✔️ Ensure the final version includes:


📤 Distribute the Final Signed Contract

Once signed, issue certified copies to all key stakeholders. This often includes:

👉 Best practice: Digital PDF copies, plus one signed hard copy for file retention.

🎯 Store it in a shared project folder or contract management system so it’s easy to access.


🔔 After Signing: What Happens Next?

  1. Project Manager takes the lead – administering early warnings, reviewing the first programme, and issuing the first Payment Certificate.
  2. Contractor mobilises – sets up the site, confirms insurances, and begins work as per the Starting and Access Dates.
  3. Everyone works “in a spirit of mutual trust and co-operation” (Clause 10.1) – the golden rule of NEC3. 🤝

✅ Final Thoughts – Sealing the Deal

Signing the NEC3 contract is more than a formality—it’s the moment the project officially begins.

You’ve now created a contract that: