[Performance Security]
This clause requires the Contractor to:
- Provide a Performance Security in a specified form, amount, and currency.
- Deliver it within 28 days after receiving the Letter of Acceptance.
- Ensure it is valid and enforceable until the Contractor has:
- Executed and completed the Works, and
- Remedied any defects.
- Extend its validity if it is set to expire before these obligations are completed.
- The Employer may make a claim only for amounts due under the Contract.
- The security is to be returned within 21 days of the Performance Certificate.
- No provision for adjustment based on variation in Contract Price.

[Performance Security]
This version includes all of the above provisions and adds the following MDB-specific enhancements:
- Clause still applies only if a value is stated in the Contract Data.
- Employer may not claim under the Performance Security except for amounts entitled under the Contract.
- Employer indemnifies the Contractor for improper claims under the security.
- 🔁 Dynamic Adjustment Clause:
- If the Engineer determines that variations or legislative/cost changes cause a >25% increase/decrease in the Contract Price in any currency,
- Then the Contractor must adjust the value of the Performance Security up or down accordingly, upon the Engineer’s request.
Feature | Red Book 1999 | Pink Book 2010 | Rationale for Change |
---|---|---|---|
Adjustment of Performance Security Value | ✘ Not provided | ✔ Required if Contract Price changes ±25% | MDBs needed a mechanism to align the value of security with actual exposure—especially in high-inflation, currency-volatile, or variation-heavy environments. |
Indemnification for Improper Employer Claims | ✘ No protection | ✔ Employer must indemnify Contractor for wrongful call | Protects Contractors from arbitrary or politically motivated use of security—important in public infrastructure projects. Promotes good faith conduct. |
Explicit Tie to Entitlements Under the Contract | ✔ Vaguely implied | ✔ Explicit: Security claim only allowed for sums due under the Contract | Clarifies that Performance Security isn’t a blank cheque. Prevents abuse and supports equitable contract administration. |
Engineer-Triggered Adjustment Mechanism | ✘ No role | ✔ Engineer may instruct security adjustment | Empowers the Engineer to safeguard financial fairness without unilateral employer action—aligns with the MDB emphasis on Engineer neutrality. |
Mandatory Only If Amount Stated | ✔ Implied | ✔ Explicit | Makes the clause conditional, allowing flexibility for smaller or low-risk contracts under MDB frameworks. |
🧠 Why These Changes Were Introduced
Multilateral Development Banks (like the World Bank, ADB, AfDB) fund massive infrastructure projects in volatile economies. When inflation spikes or scope expands, a static Performance Security becomes inadequate—or excessive.
The 2010 update lets the Engineer scale the security proportionally, maintaining fairness.
MDBs encountered cases of unjustified calling of security instruments, especially in contentious or politically pressured projects. This led to delays, arbitrations, and loss of trust in the procurement process.
The indemnity clause discourages misuse by shifting risk for wrongful calls back to the Employer.
The Pink Book reflects the MDB Harmonised Edition, created to unify contracting standards across borders.
Uniformity in security terms ensures bankability, contractor confidence, and smoother dispute resolution—critical in multinational project portfolios.
By authorizing the Engineer—not just the Employer—to request security adjustments, the update supports FIDIC’s goal of a balanced and impartial contract administrator—something MDBs prioritize for due process.
🏗️ Real-World Implication Example
Imagine a hydro project in Ethiopia funded by the World Bank. Originally budgeted at $80M, scope changes and inflation push it to $105M.
Under the Red Book, the original $8M Performance Bond (10%) stays fixed.
But under the Pink Book, the Engineer can instruct an increase to maintain the same 10% coverage—protecting the Employer while keeping the Contractor accountable.
🔸 Verbatim Highlights with MDB Additions:
- If the Contract Data specifies, the Contractor shall obtain and deliver a Performance Security within 28 days after the receipt of the Letter of Acceptance.
- The Performance Security shall:
- Be in the amount(s) and currency(ies) stated in the Contract Data,
- Be issued by an entity approved by the Employer, and
- Be in the form annexed or another form approved by the Employer.
- The Contractor shall ensure the Performance Security remains valid and shall extend its validity as required.
- The Employer shall not make a claim under the Performance Security, except for amounts to which the Employer is entitled under the Contract.
- If the Employer makes a false or improper claim, they shall indemnify the Contractor against the consequences.
- If the Engineer determines that variations or legislation changes result in a >25% increase or decrease in the Contract Price (in any currency), the Contractor shall increase or decrease the value of the Performance Security accordingly.
🔍 Breakdown: Rights & Responsibilities (Pink Book Enhancements in 🟣)
- 🟣 Only required to provide security if Contract Data specifies.
- Must comply with all terms related to amount, timing, form, and issuer.
- 🟣 Adjust Performance Security value up/down if the Contract Price changes by more than 25%.
- 🟣 Must maintain validity and extend the security if Performance Certificate is delayed.
- May approve or reject issuer and form of the security.
- 🟣 Can only claim amounts they are entitled to under the Contract.
- 🟣 Must indemnify the Contractor for false or improper claims.
- Return Performance Security within 21 days after Performance Certificate is issued.
- 🟣 May determine and instruct the adjustment of the Performance Security when the Contract Price varies significantly.
🧠 Interpretation of Key Updates
Clause Element | 1999 Red Book | 2010 Pink Book | Interpretation |
---|---|---|---|
Trigger for Security | Mandatory | Optional (only if Contract Data states amount) | Adds flexibility for MDB-funded contracts where security may not always be required. |
Security Adjustment Mechanism | ✘ | ✔ Based on ±25% variation | Ensures that security reflects the Employer’s real exposure—especially in inflationary or variation-heavy environments. |
Employer’s Right to Claim | Vague limit to “amounts due” | ✔ Must be entitled under the contract | Tightens scope of allowable claims—protects Contractor against abusive practices. |
Indemnification of Contractor | ✘ | ✔ Required for improper claim | New safeguard to deter Employers from drawing on bonds unfairly or politically. |
Engineer’s Role | Not involved | ✔ Can instruct adjustments | Elevates Engineer’s role to maintain fairness in financial securities. |
🔁 Key Cross-Referenced Clauses in Both Editions
The Works shall be taken over by the Employer when they have been completed in accordance with the Contract... The Defects Notification Period shall be as stated in the Contract.
If the Contractor fails to remedy any defect within a reasonable time, the Employer may carry out the work at the Contractor’s cost.
The Contractor may apply for a Taking-Over Certificate... If the Works are substantially complete, the Engineer shall issue it.
Applies if the Works are taken over in sections.
Substantial Completion → Taking-Over Certificate → Performance Certificate → Return of Security.
Both return of Performance Security and release of Retention Money are tied to the Performance Certificate—suggesting that the Employer’s financial security peaks during the defects notification phase, after which both security mechanisms conclude.
Even when calling the Performance Security, the Employer’s right is not automatic—it is still subject to proper notice under Sub-Clause 2.5. If the Employer fails to follow the procedure, especially in the Pink Book, they risk contractual breach and indemnity exposure under 4.2.
🔹 5. Pink Book Only – Engineer’s Role in Adjusting Security
📘 Sub-Clause 4.2 (Pink Book Addition):
“If the Engineer determines that the Contractor’s entitlement under Sub-Clause 13.7 [Adjustments for Changes in Legislation] or the cumulative effect of variations results in a change >25%... the Contractor shall increase/decrease the Performance Security.”
This ties directly to:
- 📘 Sub-Clause 13.1 [Right to Vary]
- 📘 Sub-Clause 13.7 [Adjustments for Changes in Legislation]
- Scope changes (13.1), and/or
- Legislative financial impact (13.7)

Interaction | Resulting Effect |
---|---|
Clause 11 + 4.2 | Security must remain valid during Defects Notification Period (DNP). |
Clause 10 + 4.2 | Return of Security hinges on Performance Certificate, which depends on Taking-Over. |
Clause 14.9 + 4.2 | Aligns financial closure of project (Retention + Security) post-defects resolution. |
Clause 2.5 + 4.2 | Claims on security must follow proper notice and substantiation. |
Clauses 13.1, 13.7 + 4.2 (Pink) | Allows dynamic recalibration of security based on contract variations or law changes. |
✅ Conclusion
Sub-Clause 4.2 isn’t isolated—it’s tightly woven into project milestones (Taking Over, Defects Notification, Final Payment) and dispute processes (claims, entitlements). The Pink Book strengthens this network by:
- Introducing dynamic adjustment (via the Engineer),
- Requiring indemnity for wrongful claims,
- And clarifying the sequencing with other contract entitlements.
🔍 What-If Scenarios for Sub-Clause 4.2 [Performance Security]
🟠 Scenario 1: Late Submission of Performance Security
What if: the Contractor fails to submit the Performance Security within 28 days of receiving the Letter of Acceptance?
📕 Red Book 1999 & 📘 Pink Book 2010:
- Neither version explicitly outlines consequences beyond this timeline.
- However, Sub-Clause 15.2 allows termination for failure to submit required security.
Practical Effect:
- Employer could terminate with 14 days' notice.
- Risk: Delays mobilization and could trigger disputes.
“If the Contractor fails to submit the Performance Security within 28 days, and such failure continues for a further 7 days after receiving notice from the Employer, the Employer may terminate the Contract under Sub-Clause 15.2, and the Employer shall be entitled to forfeit the Tender Security, if applicable.”
🎯 Why? Adds a grace period and due process — aligning with Golden Principle GP1 (clear and enforceable) and GP3 (balanced risk).
🟢 Scenario 2: Major Variation Increases Contract Price by 40%
What if: the Engineer issues multiple variations increasing the Contract Price by 40%?
📘 Pink Book 2010:
- Engineer may instruct a proportional increase if variations exceed ±25%.
📕 Red Book 1999:
- Lacks any mechanism for adjustment based on Contract Price variation.
“If the total value of approved Variations increases or decreases the Contract Price by more than 25%, the Engineer shall instruct the Contractor to adjust the value of the Performance Security accordingly.”
🎯 Why? Ensures risk remains proportionate — consistent with GP2 (defined roles) and GP4 (financial balance).
🔴 Scenario 3: Employer Calls the Security Without Notice
What if: the Employer lodges a claim under the Performance Security without issuing a prior notice under Sub-Clause 2.5?
📕 Red Book 1999:
- Restricts claims to “amounts due” but lacks procedural safeguards.
📘 Pink Book 2010:
- Prohibits improper claims and requires Employer indemnity.
“The Employer shall not make a claim under the Performance Security unless the amount has first been determined in accordance with Sub-Clause 3.5 or agreed with the Contractor. Any claim made without such determination shall render the Employer liable to indemnify the Contractor for direct loss.”
🎯 Why? Promotes proper contract administration and deters aggressive claims—aligns with GP5 (good faith and fair dealing).
🔵 Scenario 4: Security Expiry During Defects Notification Period
What if: the Contractor fails to extend the Performance Security validity during the DNP?
📕 & 📘 Both Editions:
- Require extension of validity.
- Enforcement depends on Employer’s proactive measures.
“If the Contractor fails to extend the validity of the Performance Security 14 days before expiry, the Employer shall be entitled to suspend interim payments under Sub-Clause 14.6 until the extension is provided.”
🎯 Why? Provides a financial nudge for compliance—fairer than termination. Aligns with GP1 (clarity) and GP4 (balanced financial protection).
✍️ Final Word on Particular Conditions
Here are golden rule–compliant principles to guide your Particular Conditions under Sub-Clause 4.2:
FIDIC Golden Principle | Application to Sub-Clause 4.2 |
---|---|
GP1: Clarity & Enforceability | Define timelines and remedies for delays or omissions. |
GP2: Defined Roles & Responsibilities | Clarify when and how the Engineer may instruct adjustments. |
GP3: Risk Balance | Avoid Employer overreach; embed indemnity provisions. |
GP4: Financial Equilibrium | Allow for dynamic security adjustment with contract price. |
GP5: Good Faith Dealings | Restrict unfair calling of securities; mandate procedural fairness. |
🧩 Final Takeaways: Sub-Clause 4.2 [Performance Security] – Red Book 1999 vs Pink Book 2010

The Performance Security acts as a financial safety net, giving the Employer assurance that the Contractor will:
- Complete the Works as agreed, and
- Remedy any post-completion defects.
It’s not just a formality—it’s a tool for balancing trust and enforceability. 🔐

Area of Change | 1999 Red Book | 2010 Pink Book (MDB) | Practical Impact |
---|---|---|---|
Adjustment Clause | ✘ | ✔ Security increases/decreases with ±25% Contract Price change | Keeps security aligned with actual project risk |
Employer Claims | Limited wording | ✔ Only for Contract entitlements | Prevents misuse or abusive claims |
Indemnity for Improper Claims | ✘ | ✔ Employer must indemnify Contractor | Adds accountability and fairness |
Engineer’s Role | ✘ | ✔ Can trigger security adjustments | Introduces third-party neutrality |
Applicability | Implied | ✔ Only applies if Contract Data specifies | Greater flexibility for MDB procurement |
⚖️ 3. Cross-Clause Interactions You Must Track
📌 Clause 10 & 11: Return of Performance Security is linked to the Performance Certificate, which depends on Taking Over and the Defects Notification Period.
📌 Clause 14.9: Aligns timing of security return with release of Retention Money—a key milestone in closing out obligations.
📌 Clause 2.5: Employer must properly notify claims before drawing on security—especially critical in the Pink Book.
🏗️ 4. Practical Applications: What This Means On Site
- ✅ Ensure the security covers Defects Correction by monitoring expiration dates.
- ✅ Track cumulative variations and legislation changes—your Performance Security may need to scale.
- ✅ As an Employer, avoid surprise calls on the bond—follow notice procedures to maintain trust and avoid indemnity liabilities.
- ✅ As a Contractor, resist providing security without proper form/terms—use the approved format and confirm the right conditions are in place.