FIDIC Clause 2.2: Permits, Licences & Approvals Explained

78 / 100 SEO Score

Views in the last 30 days: 78

Estimated read time: 12 minute(s)

🔎 Clause 2.2: Permits, Licences or Approvals

Purpose:
Clause 2.2 establishes the obligations regarding permits, licences, and approvals required for executing the Works.
It ensures both the Employer and Contractor know who is responsible for what in the often-complex web of regulatory compliance—whether that’s customs clearance, building permits, or export documentation.
Implications:
  • ✅ Clearly assigning responsibility prevents costly misunderstandings and project delays.
  • ✅ If either party fails in their obligations, the other is protected via entitlements to time/cost relief or indemnity.
  • ✅ Properly managing these regulatory hurdles is vital for project continuity and legal compliance.
Want to go deeper? Check out the in-depth article on Clause 2.2 here for real-world examples and actionable tips.
Quick Quiz 📝

📘 Clause 2.2: Permits, Licences or Approvals (1999 vs 2017)

What’s “Assistance”?
Letters, information, introductions, advocacy—but not “doing it for the Contractor.”
Who Gets Permits?
Almost always the Contractor—unless otherwise stated in the contract.
Mini Scenario: Who Does What?

🧠 Key Interpretations & Implications

  • Responsibility: The Contractor must obtain and pay for all necessary permits/licenses unless stated otherwise (see Clause 1.13). The Employer assists only when local knowledge, influence, or legal status is needed.
  • Assistance vs. Accountability: If the Employer fails to assist when properly requested, the Contractor may be entitled to Extension of Time (EOT) or cost recovery (see claim procedures).
  • 2017 Change: The word “promptly” now appears in FIDIC 2017, emphasizing that the Employer must help in a timely manner to avoid project delays.
  • Practical Risks: Delays in customs, local permissions, or export documentation can cause costly standstills. This clause gives the Contractor a clear escalation route if support is lacking.
Ask Yourself 🤔
Is your contract clear on who does what—and what happens if assistance is delayed?

🔗 Cross-Referencing with Other FIDIC Clauses

Clause 1.13
Compliance with Laws
Assigns main compliance & permit duties to Contractor, but exceptions exist for Employer-obtained permits.
Clause 20
Claims
If the Employer fails to assist, Contractor may claim EOT/cost (must follow notice requirements).
Clause 14
Payment
Approved claims for EOT/costs due to delays can be reflected in payment certificates.
📦 Customs & Export (Goods & Equipment)
Clause 4.16: Transport of Goods
Deals with the delivery of Goods, including customs processes and related permits.
Clause 4.17: Contractor’s Equipment
Covers removal/export of Equipment from site, often requiring specific export permits.
Want to explore more? See the full Clause 2.2 guide or jump to related clauses above.

⚡ What-If Scenarios? Clause 2.2 in Action

Scenario 1: Delayed Customs Clearance
Situation: Contractor needs customs clearance for imported turbines. Authorities require a support letter from the Employer, but it’s delayed.
Implication: Contractor notifies Employer (Clause 2.2), requests prompt help, and may claim EOT/costs if not their fault.
Scenario 2: Environmental Permit Blocked
Situation: Contractor can’t secure an environmental permit because Employer hasn’t provided required land documents.
Implication: Contractor issues notice under Clause 2.2 and Clause 1.13. EOT/costs may be claimed if delayed.
What’s the Right Move?

💡 Suggestions for Clarity and Improvement: Clause 2.2

A. Why is Clarity Needed?
  • Ambiguity in permit obligations is a leading source of disputes, especially in complex regulatory environments.
  • “Assistance” is not defined—does it include payment, advocacy, only letters?
  • No timeframes for Employer action can stall projects.
  • Some permits can only be legally obtained by the Employer.
  • Stalled projects and disputes arise when roles aren’t explicit in the contract or Employer’s Requirements.
  • Golden Principles: GP1 (clear duties), GP2 (fair risk allocation) require unambiguous roles for permits.
B. Practical Suggestions and Examples
1. Define “Reasonable Assistance”
Suggested Wording + Examples
“Reasonable assistance” could include:
– Letters, meetings with authorities, legal docs, translations, direct interventions.
For Clause 2.2, ‘reasonable assistance’ shall include, but not be limited to:
(i) Letters of support,
(ii) Property/legal docs,
(iii) Representations to authorities,
(iv) Translations,
(v) Info/certifications unique to Employer,
(vi) Attending authority meetings.
2. Timeframes for Employer Action
Suggested Wording + Example
“Employer to act within 7 days of Contractor’s written request or as reasonably agreed—delays entitle Contractor to claim.”
Employer shall provide assistance/docs within 7 days of request or as reasonably agreed. Failure, after reminder, entitles Contractor to claim under Clause 20.
3. Permit Responsibility Matrix
See Example Table
Permit Type Primary Responsible Assistance by Deadline
Construction Permit Employer Contractor (tech data) 14 days from LoA
Import Customs Clearance Contractor Employer (letters) 7 days on request
Environmental Approval Employer Contractor (env. docs) 30 days from NTP
Utilities Connections Contractor Employer (local contacts) 14 days before need
A Permit Responsibility Matrix should be attached to Employer’s Requirements/Particular Conditions.
4. Explicit “Local Law Only” Clause
Suggested Wording
If only Employer can apply under law, Employer must obtain permit; Contractor provides info/support.
Where local law/practice requires Employer to hold/apply for permit, Employer is solely responsible for timely procurement; Contractor provides technical/support info.
5. Handling Governmental Delays
Suggested Wording
If delay is due solely to authority, Contractor gets time, but not cost (unless Employer’s fault).
Delays caused by authorities, after both Parties fulfill duties, entitle Contractor to EOT (not cost), unless delay is Employer’s fault/omission.
6. Clear Notice & Record-Keeping
Suggested Wording + Example
All requests and responses must be in writing and logged; register accessible for inspection.
All assistance requests/responses under Clause 2.2 shall be in writing and copied to Engineer. Parties maintain a correspondence register, open to inspection.
❓ FAQ: Why Are These Improvements Needed?
Unclear obligations cause project delays, disputes, and unexpected risks.
Defining responsibilities, timelines, and documentation helps prevent ambiguity and protects both parties.
Want more practical templates? See the full Clause 2.2 improvement guide

Permit Responsibility Matrix Generator

List all the permits, licences, or approvals required for your project (one per line). Click “Generate Matrix” for a clear Employer/Contractor allocation table and a template request letter for Employer assistance.

Permit Responsibility Matrix

Permit / Approval Responsible Party Assisting Party & Action Key Deadline / Milestone
Construction Permit Employer Contractor submits technical/design info 14 days from Letter of Acceptance
Import Customs Clearance Contractor Employer provides letters/support as needed 7 days after request
Environmental Impact Approval Employer Contractor supplies studies/reports 30 days from Notice to Proceed
Utility Connections (Water/Electricity) Contractor Employer provides utility contact info/intro letters 14 days before required connection
Export Permit for Contractor’s Equipment Contractor Employer assists with customs clearance if needed 21 days before demobilization
Land Use or Occupancy Permit Employer Contractor provides site layout and access plan Prior to commencement on affected land
Road Closure Permission Joint Contractor prepares application; Employer submits to authorities 14 days before planned closure
Scaffolding / Temporary Works Permit Contractor Employer provides site safety guidelines if required Before erection of temporary works
Discharge/Water Pollution Permit Employer Contractor provides technical specs, method statements Prior to any water discharge activity
Tip: For every permit, keep a record of requests and responses. Update this matrix as project details evolve!

📋 FIDIC Clause 2.2 Permit, Licence or Approval Checklist

How to use: Review at project start and during key phases (design, procurement, execution, commissioning).
Tick the “Done?” box (☐ → ☑) as each action is completed and keep for your records. This checklist can also be copied into Word, Excel, or project tools.
# Task Description Party Responsible Relevant Clause Done?
1 Identify all permits, licences, and approvals required for the Works (local, national, export, import, etc.) Contractor 1.13, 2.2
2 Review Employer’s Requirements for permits/approvals to be obtained by Employer Contractor/Employer 1.13, 2.2
3 Prepare permit responsibility matrix (who does what, by when) Contractor/Employer 2.2, Particular Conditions
4 Request in writing any “reasonable assistance” needed from Employer Contractor 2.2
5 Provide prompt and reasonable assistance to Contractor upon request Employer 2.2
6 Obtain copies of applicable Laws and regulations if not readily available Employer 2.2(a)
7 Prepare and submit all applications for permits, licences, and approvals as required by Law Contractor 1.13, 2.2(b)
8 Provide all necessary supporting documents and information for Employer’s or authorities’ use Contractor 2.2(b)
9 Follow up regularly on pending applications with authorities Contractor Good practice
10 Communicate immediately any delays or problems with permit/approval process to Employer & Engineer Contractor 2.2, 20
11 Document all communications, submissions, and responses about permits/approvals Contractor/Employer Good practice
12 Escalate to claims procedure if delay/costs arise due to Employer’s failure to assist Contractor 20, 2.2
13 Review and update checklist at regular intervals and major project milestones Contractor/Employer Good practice

📬 FIDIC Clause 2.2 Communication Templates

How to use: Replace all [bracketed fields] with your project details. Attach documents as needed, and always keep records for claims or audits.

Leave a Comment

Scroll to Top