Care and Supply of Documents with Practical Recommendations: Clause 1.8 of FIDIC Yellow Book 2017

Care and Supply of Documents[Sub-Clause 1.8] in the FIDIC Yellow Book 2017 (Conditions of Contract for Plant and Design-Build) outlines the responsibilities of the Contractor regarding the custody, care, and provision of documents required for the execution of the Works. This clause ensures that all relevant documents are properly managed, stored, and made accessible to the Employer’s Personnel, facilitating effective communication and project management.

Definition and Scope of Sub-Clause 1.8 [Care and Supply of Documents]

Clause 1.8 delineates the obligations of the Contractor concerning:

Key Aspects of Sub-Clause 1.8 [Care and Supply of Documents]

  1. Custody of Contractor’s Documents
    • Until submitted to the Engineer, all Contractor’s Documents remain under the Contractor’s care.
  2. Supply to the Engineer
    • The Contractor must supply:
      • One paper-original.
      • One electronic copy (format specified in the Employer’s Requirements or acceptable to the Engineer).
      • Additional paper copies as stated in the Contract Data.
  3. On-Site Documentation
    • The Contractor must keep the following on Site at all times:
      • The Contract.
      • Records under Sub-Clauses 6.10 and 20.2.3.
      • Publications named in the Employer’s Requirements.
      • Contractor’s Documents.
      • Variations, Notices, and other communications under the Contract.
  4. Access Rights
    • Employer’s Personnel have the right to access all aforementioned documents during normal working hours or as otherwise agreed.
  5. Error or Defect Notification
    • If any Party or the Engineer becomes aware of an error or defect in the Contractor’s Documents:
      • They must promptly notify the others.
      • The Contractor must rectify the error or defect promptly at their own risk and cost.

Key Considerations of Sub-Clause 1.8 [Care and Supply of Documents]

  1. Format and Delivery of Documents
    • Compliance with specified formats in the Employer’s Requirements or as acceptable to the Engineer.
    • Timely submission to avoid delays in approvals or execution.
  2. Accessibility
    • Keeping all required documents on Site ensures that the Employer’s Personnel can perform inspections, audits, or verifications effectively.
  3. Confidentiality and Security
    • While documents are accessible, sensitive information must be protected as per the Contract terms.
  4. Error Rectification Process
    • Understanding the obligation to rectify errors promptly and the implications on project costs and schedules.
  5. Integration with Other Clauses
    • Coordination with related clauses like 6.10 [Contractor’s Records], 4.20 [Progress Reports], and 20.2.3 [Contemporary Records].

Critical Terms and Concepts

Areas of Potential Ambiguity or Differing Interpretations

  1. Definition of “Contractor’s Documents”
    • Ambiguity: The term “Contractor’s Documents” may be interpreted differently by parties. Does it include only design documents, or does it extend to proprietary methods, calculations, and internal reports?
    • Perspective: Legally, undefined terms can lead to disputes over scope. Technically, including proprietary documents may raise confidentiality concerns.
  2. Format and Copies of Documents
    • Ambiguity: The clause specifies “one paper-original, one electronic copy… and additional paper copies (if any) as stated in the Contract Data.” If the Contract Data is silent, how many additional copies are required?
    • Perspective: Without clear specifications, the Contractor may under-prepare or over-prepare documents, affecting cost and efficiency.
  3. Form Acceptable to the Engineer
    • Ambiguity: If the electronic format is “not stated,” it should be acceptable to the Engineer. However, without predetermined acceptance criteria, disagreements may occur over acceptable formats (e.g., PDF vs. CAD files).
    • Perspective: Technically, incompatible formats can hinder the Engineer’s ability to review documents effectively.
  4. Access Rights of Employer’s Personnel
    • Ambiguity: The clause grants access “during all normal working hours, or as otherwise agreed with the Contractor.” What constitutes “normal working hours,” and can the Contractor reasonably restrict access?
    • Perspective: Construction schedules may vary, and differing expectations about access times can lead to conflicts.
  5. Notification and Rectification of Errors
    • Ambiguity: The clause states that if a Party becomes aware of an error, they shall “promptly” notify, and the Contractor shall “promptly” rectify it. The term “promptly” is subjective and may lead to differing expectations.
    • Perspective: Legally, lack of defined timeframes can cause disputes over delays. From a construction standpoint, delays in rectification can impact the project schedule.
  6. Scope of Errors or Defects
    • Ambiguity: The clause refers to errors “whether of a technical nature or otherwise.” It’s unclear if this includes minor typographical errors or is limited to significant issues affecting the Works.
    • Perspective: Contractors might be held responsible for rectifying inconsequential errors, leading to unnecessary effort and cost.

Practical Recommendations for Improved Clarity

  1. Define “Contractor’s Documents”
    • Recommendation: Include a clear definition in the Contract Data or Particular Conditions.
    • Example:
      • “Contractor’s Documents shall mean all documents, drawings, calculations, models, specifications, and other technical documentation prepared by or on behalf of the Contractor required for the execution of the Works, excluding proprietary internal reports and methods unless otherwise specified.”
  2. Specify Document Formats and Quantities
    • Recommendation: Clearly state the required formats and number of copies in the Employer’s Requirements or Contract Data.
    • Example:
      • “The Contractor shall supply to the Engineer one paper-original and one electronic copy in PDF and DWG formats, along with two additional paper copies of each of the Contractor’s Documents.”
  3. Establish Criteria for Electronic Formats
    • Recommendation: Agree on acceptable electronic formats prior to commencing work.
    • Example:
      • “Acceptable electronic formats include PDF for documents and drawings, DWG for CAD files, and XLSX for spreadsheets.”
  4. Define “Normal Working Hours”
    • Recommendation: Specify the standard working hours applicable to the Site.
    • Example:
      • “Normal working hours are defined as 8:00 AM to 6:00 PM, Monday to Friday, excluding public holidays.”
  5. Set Timeframes for Notifications and Rectifications
    • Recommendation: Replace “promptly” with specific time limits.
    • Example:
      • “Notification of any error or defect shall be given within 2 working days of discovery. The Contractor shall rectify the error or defect within 5 working days of receiving such Notice, or as otherwise agreed with the Engineer.”
  6. Clarify Scope of Errors or Defects
    • Recommendation: Differentiate between minor and major errors, and outline the rectification process accordingly.
    • Example:
      • “Errors or defects refer to any significant issues that may affect the safety, functionality, or compliance of the Works. Minor typographical errors that do not impact these aspects may be rectified during the next document revision cycle.”

Proposed Particular Condition

In accordance with the FIDIC Golden Principles—which emphasize clarity, balanced risk allocation, and maintaining the integrity of the standard contract—the following Particular Condition is proposed:

Particular Condition: Amendment to Clause 1.8 [Care and Supply of Documents]

  1. Definition of Contractor’s Documents
  2. Supply of Documents
    • The Contractor shall supply to the Engineer:
  3. On-Site Documentation
    • The Contractor shall maintain at the Site, and make available to the Employer’s Personnel, the following documents:
  4. Access Rights
  5. Notification and Rectification of Errors

Real-Life Examples and Perspectives

Legal Perspective

Technical Perspective

Construction Perspective

Risk Management

Conclusion

By addressing the potential ambiguities in Clause 1.8 through clear definitions, specified formats, and established timeframes, parties can improve contractual clarity and reduce the risk of disputes. The proposed Particular Condition aligns with the FIDIC Golden Principles by:

Implementing these recommendations fosters better communication, efficient project management, and a collaborative working relationship, ultimately contributing to the successful completion of the Works.