Here’s a detailed explanation of the revised flowchart, which combines Clauses 10.1, 10.2, and 10.3 and includes durations:
- Start: Contractor Completes Work: This is the initial stage where the Contractor has completed the work as per the contract requirements.
- Contractor Requests Taking-Over Certificate: After completing the work, the Contractor formally requests the Engineer to issue a Taking-Over Certificate.
- Engineer Reviews Request (Within 14 days): The Engineer reviews the request and the state of the completed work to decide whether to issue the Taking-Over Certificate.
- Approves: If the Engineer approves, they proceed to issue the Taking-Over Certificate.
- Issue Taking-Over Certificate: The Engineer issues the Taking-Over Certificate, indicating that the works are accepted and responsibilities are transferred to the Employer.
- Works Handed Over to Employer: The responsibility for the works is officially transferred to the Employer.
- Defects Liability Period Begins: After the Taking-Over Certificate is issued, the Defects Liability Period commences.
- End of Contract: The contract reaches its conclusion, typically after the Defects Liability Period ends.
- Denies: If the Engineer denies the request, they must specify the reasons for the denial.
- Specify Reasons for Denial: The Engineer must specify the reasons for denying the Taking-Over Certificate.
- Contractor Rectifies Issues: The Contractor rectifies any issues or completes any pending work based on the Engineer’s feedback.
- Interference with Tests on Completion?: This decision point checks if there’s any interference with the Tests on Completion.
- Yes: The Works are deemed to have been taken over by the Employer.
- Engineer Issues Taking-Over Certificate: The Engineer issues the Taking-Over Certificate accordingly.
- Contractor Carries Out Tests ASAP: The Contractor carries out these Tests on Completion as soon as practicable.
- Engineer Requires Tests with 14 Days’ Notice: The Engineer requires the Tests on Completion to be carried out by giving 14 days’ notice.
- Contractor Gives Notice for Delay/Cost: If the Contractor suffers delay and/or incurs Cost, they give notice to the Engineer.
- Engineer Proceeds to Determine Matters: The Engineer proceeds to determine these matters, leading to the end of the contract.
- No: The standard process is followed, leading to the end of the contract.
- Yes: The Works are deemed to have been taken over by the Employer.