Site icon Navigating Knowledge Across Domains

Clearance of Site FIDIC Clause 11.11 Explained

Clearance of Site

Clearance of Site

Clause 11.11 — Clearance of Site (FIDIC Yellow Book 1999 📘 & 2017 📒)

Quick visual 📊
Trigger ➜ Action ➜ Deadline ➜ Employer’s Remedies
Performance Certificate issued ➜ Contractor removes equipment, materials, rubbish; reinstates affected areas; leaves Site clean/safe ➜ within 28 days ➜ Employer may sell/dispose/clean/reinstate and recover costs.


1️⃣ Purpose of Clause 11.11

Why it exists: To ensure the Works and Site are handed back properly after completion—free of the Contractor’s temporary footprint and safe for operation or subsequent use. Under both editions, the obligation is tied to the Performance Certificate (PC): only on PC is acceptance deemed to occur, and post-PC “clearance” finishes the housekeeping.

Who it protects:

Risk if ignored: Safety hazards, environmental non-compliance, obstruction of Employer’s operations, and chargebacks for Employer’s remedial actions.


2️⃣ Breakdown of Clause 11.11

📘 1999 — Clause 11.11 (core points)

📒 2017 — Clause 11.11 (what’s new/clearer)


3️⃣ Key Interpretations & Implications

Interpretative question: Can it be read that in 1999, reinstatement is optional after PC since 11.11 doesn’t say it?
Answer: No—the duty to leave the Site clean and safe applies upon Taking-Over under 4.23, and that part-by-part clearance standard carries forward; 11.11 adds the end-of-contract removal obligation and employer remedies post-PC.


4️⃣ Cross-Referencing (how clauses interact)


5️⃣ What-If Scenarios (practical)

  1. Contractor leaves containers & scrap post-PC
    • After 28 days, Employer may sell or dispose of the items; may also restore/clean and recover reasonable costs (2017 expressly routes via claims clause). Net proceeds go to Contractor; shortfall is recoverable from Contractor.
  2. Hazardous waste left on Site
    • 2017’s operational duties (4.22) encompass hazardous waste—failure to remove could justify Employer’s remediation and cost recovery; potential environmental law exposure too.
  3. Partial Taking-Over (Sections)
    • On each TOC, the Contractor must clear and leave that part clean and safe; can retain necessary goods during DNP in agreed areas. Final 11.11 “sweep” happens after the overall PC.
  4. Termination for convenience
    • Demobilise and remove goods under 16.3; valuation/payment handled under termination provisions—clearance obligations still apply as part of leaving the Site.

6️⃣ Suggestions for Clarity & Improvement (Particular Conditions ✍️)


7️⃣ Final Takeaways


Bonus: Mini-checklist you can paste into a PC handover meeting ✅


FIDIC **11.11 — Clearance of Site** Letters

Generate, review, and copy letters for post-PC clearance. Choose the edition, fill basics, then click Generate Letter. Nothing renders until you click.

Edition:
⏱️ Deadline: PC + 28 days
🧩 Cross-refs: 4.22/4.23, 10.2, 11.10, 13, 16.3, 18/19, 20.1/20.2
Project & Dates (click to open)

🛈 The widget will auto-calculate PC + 28 days where needed.

Tip: You can generate multiple letters with the same inputs. Edit inside the textarea before copying.

1) Contractor → Engineer/Employer — Clearance Plan & Demobilisation 11.11

Submission of plan, scope, HSE, and PC + 28 days completion.

2) Contractor → Engineer — Access/Permits for Clearance 11.11

Requests for access windows, isolations, and approvals to meet the deadline.

3) Contractor → Engineer — Exceptional Event / Force Majeure Notice 18/19, 20.x

Edition-aware relief notice (📒 18 + 20.2 / 📘 19 + 20.1).

4) Contractor → Engineer/Employer — Completion of Clearance 11.11

Confirms completion within 28 days; attaches evidence pack.

5) Contractor → Engineer — Retain Items Post-PC (Variation/Valuation) 13, 11.11

Engineer’s instruction to retain temporary facilities beyond the window.

6) Contractor → Engineer/Employer — Controlled Disposal & Title 11.11

Confirms licensed facility route and seeks salvage/title instructions.

7) Engineer/Employer → Contractor — Reminder of 28-Day Deadline 11.11

Gentle nudge with plan request and date reference.

8) Engineer/Employer → Contractor — Non-Compliance & Intention to Dispose 11.11, 11.10

Missed deadline → notice of disposal/reinstatement and cost recovery.

9) Employer → Contractor — Accounting of Sale/Disposal & Set-Off 11.11

Shares proceeds vs costs and shortfall or net due.

10) Engineer → Contractor — Hazardous-Waste & Environmental Docs 4.22/4.23, 11.11

Requests manifests, licenses, and prevention/clean-up methods.

11) Engineer → Contractor — Sectional (Part) Taking-Over Clearance 10.2, 4.22/4.23, 11.11

Clean & safe per section; retain only what’s agreed for DNP.

12) Employer → Contractor — Termination Demobilisation & Clearance 16.3 (+ 4.22/4.23)

Post-termination removal and safe condition notice.

Disclaimer: Templates are editorial aids for FIDIC **11.11** workflows. Adapt to your contract, law, and facts. Not legal advice.
Copied to clipboard ✅
Your browser has JavaScript disabled. Enable it to use the generator.
Exit mobile version