Clause 11.5 “Removal of Defective Work” of FIDIC

image 68

1️⃣ Purpose of Clause 11.5

1999 Edition

The purpose of Clause 11.5 in the 1999 edition is to allow the Contractor to remove defective Plant from the Site for off-site repair—but only with the Employer’s consent. This creates flexibility while protecting the Employer’s interests through security requirements.

2017 Edition

In the 2017 edition, Clause 11.5 formalizes and significantly expands the process. It outlines a detailed notification procedure when off-site remedying is required, ensuring traceability, control, and accountability.

⚖️ Evolution in Contract Management:

2️⃣ Breakdown of Clause 11.5 – Let’s Dive Deep!

🧱 FIDIC 1999 – Clause 11.5: Removal of Defective Work

This version of the clause is short and sharp. Here’s what it says:

“If the defect or damage cannot be remedied expeditiously on the Site and the Employer gives consent, the Contractor may remove from the Site for the purposes of repair such items of Plant as are defective or damaged. This consent may require the Contractor to increase the amount of the Performance Security by the full replacement cost of these items, or to provide other appropriate security.”

So what’s going on here?

🔍 Let’s unpack it step by step:

  • “If the defect or damage cannot be remedied expeditiously on the Site” – this is the condition precedent. The clause applies only when it’s not practical or efficient to fix the issue on-site. Think of a broken-down transformer that needs to go back to the manufacturer’s workshop.
  • “and the Employer gives consent” – the Employer has the right to approve or reject the Contractor’s request to remove defective items. No unilateral action here! This is a key control mechanism for the Employer.
  • “the Contractor may remove… for the purposes of repair” – once approved, the Contractor is allowed to take the item off-site to fix it.
  • Security Requirements: The Employer may:
    • Ask for an increase in the Performance Security—covering the full replacement cost; or
    • Request some other form of appropriate security, like a bank guarantee or insurance.

💡 Practical Example:

Say a complex electrical panel has a manufacturing fault. The Contractor can’t repair it on site due to lack of specialized tools. They request to ship it back to the vendor’s factory abroad. The Employer can say “yes,” but might say, “You need to bump up the Performance Security first—just in case it gets lost or never comes back.”

🧾 FIDIC 2017 – Clause 11.5: Remedying of Defective Work off Site

Now, let’s look at the same clause from the 2017 edition. And buckle up—this one goes into a lot more detail.

Here’s the key part of the clause:

“If, during the DNP, the Contractor considers that any defect or damage in any Plant cannot be remedied expeditiously on the Site, the Contractor shall give a Notice, with reasons, to the Employer requesting consent to remove the defective or damaged Plant off the Site for the purposes of repair.”

So already, you see a shift. No more casual conversations—this is formal. The Contractor must issue a Notice and provide reasons.

But there’s more. The Notice must include:

  • Clear identification of each defective/damaged Plant item
  • Nature of the defect or damage
  • Destination of the Plant (where it’s going)
  • Transport and insurance details
  • Inspection and testing plans (off-site)
  • Timeline for:
    • Return to Site
    • Reinstallation and retesting (under Sub-Clause 7.4 or Clause 9 if applicable)

“The Contractor shall also provide any further details that the Employer may reasonably require.”

So the Employer has full oversight—not just whether it’s going, but where, how, when, and how it’ll be validated when it returns.

And then we have this clause mirror from 1999:

“When the Employer gives consent (which consent shall not relieve the Contractor from any obligation or responsibility under this Clause), the Contractor may remove from the Site such items of Plant as are defective or damaged.”

This is important: ✅ Consent doesn’t let the Contractor off the hook. Even after removal, all obligations remain.

And just like before:

“As a condition of this consent, the Employer may require the Contractor to increase the amount of the Performance Security by the full replacement cost of the defective or damaged Plant.”

So yes, we still have the security mechanism, but now it’s wrapped in formal procedure.

🔁 Key Comparisons

Element1999 Edition2017 Edition
Consent Required✅ Yes✅ Yes
Trigger ConditionCan’t remedy “expeditiously on Site”Same
Notice Requirement❌ Not mentioned✅ Mandatory, with detailed checklist
Info in Consent Request❌ Not specified✅ Must include item ID, transport, insurance, etc.
Further Employer Input❌ Minimal✅ Employer can ask for more info
Performance Security Increase✅ Optional✅ Optional but explicitly stated
Contractor’s Responsibility✅ Implied✅ Explicit – consent doesn’t waive liability

3️⃣ Key Interpretations and Implications

🚨 Risks and Responsibilities

  • Contractor remains fully responsible for the defective Plant even after off-site removal in both versions.
  • Employer’s consent does not transfer risk or waive liability.

📌 1999 Simplicity vs 2017 Detail

  • 1999 wording allows for flexibility but may lead to disputes due to lack of clarity.
  • 2017 introduces documentation and procedural rigour—better risk mitigation but potentially more bureaucracy.

✅ Security Assurance

  • In both editions, Employer can demand financial security to mitigate the risk of non-return or total loss.

4️⃣ Cross-Referencing with Other Clauses – How Clause 11.5 Fits into the Bigger Picture

When you look at Clause 11.5, it may seem like a standalone permission clause—“Hey, can I take this broken thing off-site to fix it?” But once you start peeling back the layers, you’ll see that a whole web of other clauses come into play.

Let’s take a walk through the contractual neighborhood:


🔐 Clause 4.2 – Performance Security

Both 1999 and 2017 editions allow the Employer, as a condition of consent, to demand an increase in the Performance Security.

From 2017 Clause 11.5:
“The Employer may require the Contractor to increase the amount of the Performance Security by the full replacement cost…”

This connects directly with Sub-Clause 4.2, which defines the form, value, duration, and conditions for making claims under the security.

🔎 What to look out for:

👉 Contractors should ensure their security instruments are flexible enough to accommodate these scenarios—or they risk delays.


🧪 Clause 7.4 (2017): Testing by the Contractor

🧱 The Text (Key Highlights from Clause 7.4)

“The Contractor shall carry out the tests required by the Contract on Plant and Materials before their incorporation into the Works and on the executed Works to verify compliance with the Contract. The Contractor shall give a Notice to the Engineer of not less than 14 days of the date, time and place for the specified testing.”

It continues:

“If the Contractor is required, under the Contract, to carry out testing off the Site, the Contractor shall give a Notice of not less than 14 days to the Engineer of the date, time and place of the test(s), and the Engineer or his representative shall be entitled to attend.”

And then:

“After each test, the Contractor shall promptly submit to the Engineer a certified report of the test results.”


🔗 So how does this connect with Clause 11.5?

When defective Plant is removed off-site for repair under Clause 11.5, you don’t just fix it and bring it back. You have to prove it’s now compliant. That’s where Clause 7.4 steps in.

Under Clause 11.5, the Contractor must:

“…include in the Notice: the proposed inspections and testing off the Site… and the planned duration for reinstallation and retesting… under Sub-Clause 7.4 and/or Clause 9.”

Let’s break it down 👇


📌 Key Intersections with Clause 11.5

1. Off-site Repair = Off-site Testing

If you’re repairing Plant in a different country or location, you must notify the Engineer at least 14 days in advance about the time, location, and nature of the test.

✅ That means aligning your logistics and test lab schedules with the Engineer’s availability.

2. Engineer’s Right to Witness Tests

Even though it’s happening off-site, the Engineer or their representative has the right to attend. If you skip this step or test without notice, your test results could be invalidated. That could lead to delays—or worse, a rejection upon return.

3. Certified Test Reports Are Mandatory

Clause 7.4 obliges you to submit certified test reports. This acts as the formal documentation trail that proves the Plant is fixed and fit for reinstallation.


🧠 Why This Matters

Let’s say you’re the Contractor and you fix a high-voltage switchgear unit off-site. You complete the repairs and skip notifying the Engineer before testing. You bring it back, install it, and only then submit your results.

🚨 Problem: The Employer may refuse to accept it until testing is repeated in the presence of the Engineer—costing you time and money. Possibly even triggering delay damages under Clause 8.8.


🧰 Practical Tip:

Integrate Clause 7.4 planning into your Clause 11.5 Notice. You’re not just asking for permission to take the item off-site—you’re also laying out your testing and validation roadmap.

Include in your Notice:

This gives the Employer confidence, reduces objections, and keeps your timeline tight.

🧪 Clause 9 (Both Editions): Tests on Completion

Once the defective Plant is fixed off-site, it doesn’t magically qualify for reinstallation. It must be retested.

From 2017 Clause 11.5:
“…and retesting of the repaired Plant (under Sub-Clause 7.4 and/or Clause 9, if applicable).”

This means the full testing regime may kick back in. The repaired item may have to:

📌 This cross-link enforces quality assurance and functional validation before the item is accepted back into the Project.


📆 Clause 11.1 – Completion of Outstanding Work and Remedying Defects

Clause 11.5 is essentially an extension of 11.1, which sets the core responsibility for the Contractor to remedy defects during the Defects Notification Period (DNP).

“During the DNP, the Contractor shall remedy any defects…” – Clause 11.1 (both editions)

So if a defect arises, 11.1 says, “Fix it.”
Clause 11.5 then adds, “Here’s how you can fix it if it requires off-site removal.”

🧩 These two are a package deal—Clause 11.5 should always be read as a method of compliance with Clause 11.1.


🚧 Clause 10 – Taking Over by Employer

In both editions, Taking Over Certificates (TOCs) mark the official handover of the Works or a Section. But Clause 11.5 plays into this timeline too.

🔁 If defective Plant is removed off-site during this period, delays in reinstallation may affect:


🧾 Clause 20.1 (1999) / Clause 20.2 (2017) – Claims

Here’s where it gets spicy 🌶️.

If the Employer unreasonably withholds consent to remove defective Plant—or if the Contractor suffers delay or cost due to procedural hurdles—this opens the door to claims.

So, if the Contractor:

👉 They may be able to trigger a contractual claim process for extension of time (EOT) or additional payment.


🔁 Cross-links in Action: A Realistic Chain of Events

  1. A turbine’s blade fractures—Contractor says it must be fixed in Germany.
  2. Submits Notice under 11.5 with detailed plan (as per 2017).
  3. Employer demands Performance Security update (Clause 4.2).
  4. Contractor sends turbine off-site.
  5. Repair complete—Contractor arranges retesting (Clause 7.4/9).
  6. Employer inspects and approves.
  7. Contractor seeks time extension for downtime (Clause 20.2).
  8. All of this happens during DNP (Clause 11.1) and ties into the timeline for the Performance Certificate (Clause 11.9).

You see? Clause 11.5 is just the tip of the procedural iceberg.

5️⃣ What If Scenarios?

🤔 What if the Contractor removes Plant without consent?

🤔 What if the Employer unreasonably delays consent?

🤔 What if the repaired Plant fails retesting?

6️⃣ Suggestions for Clarity and Improvement – Making Clause 11.5 Even Better

Even though Clause 11.5 works reasonably well in both editions, there are opportunities to refine the language and streamline the process to help both Employers and Contractors avoid misunderstandings, unnecessary delays, or disputes.

We’ll break this down by edition and focus on:

📘 FIDIC 1999 – Suggestions for Improvement

Let’s be honest—the 1999 version of Clause 11.5 is a bit bare bones. While its simplicity is attractive, it also leaves a lot unsaid.

🔧 Suggestion #1: Define “expeditiously”

“If the defect or damage cannot be remedied expeditiously on the Site…”

Issue: What does “expeditiously” mean? One day? One month?

🔍 Recommendation: Add a time threshold or objective standard. For example:

“…cannot be remedied within a period of 7 days on Site…”
Or: “…cannot be remedied on Site due to lack of appropriate facilities or specialized equipment…”

💬 Example:

A Contractor wants to send a control panel abroad for recalibration. The Employer argues it could be fixed on-site using a subcontractor within 10 days. Without clear criteria, it becomes a subjective argument.

🔧 Suggestion #2: Clarify the format of consent

“…and the Employer gives consent…”

Issue: Is this verbal consent? Written? Time-bound?

🔍 Recommendation: Specify that consent must be:

“…in writing, within 7 days of receiving the Contractor’s request.”

This avoids the “We talked about it on the phone!” scenario.


🔧 Suggestion #3: Detail what “other appropriate security” means

“…or to provide other appropriate security.”

Issue: Vague. What is “appropriate”? Who decides?

🔍 Recommendation: Provide examples or criteria:

“…including but not limited to a bank guarantee, insurance cover, or escrow account, acceptable to the Employer.”

📙 FIDIC 2017 – Suggestions for Improvement

The 2017 edition of Clause 11.5 is much more comprehensive—but that also makes it ripe for procedural fine-tuning.

📝 Suggestion #1: Add a response deadline for the Employer

“When the Employer gives consent…”

Issue: There’s no deadline for the Employer’s response, which could stall progress.

🔍 Recommendation: Add:

“The Employer shall respond to the Contractor’s Notice within 5 days of receipt. Failure to respond shall be deemed as refusal/approval [select as per risk preference].”

💬 Example:

The Contractor submits a detailed removal request on Monday. The Employer doesn’t respond for two weeks. The item sits on-site, delaying repairs and commissioning. A clear timeline avoids this.


📝 Suggestion #2: Define the process for requesting additional info

“…Contractor shall also provide any further details that the Employer may reasonably require.”

Issue: What’s “reasonable”? Can the Employer keep asking for more and more?

🔍 Recommendation:

  • Limit to one round of clarifications, or
  • Add wording:

“…such further details shall be requested within 3 days, and shall be relevant to the decision on removal.”

📝 Suggestion #3: Standardize the required Notice content

The 2017 clause demands a long list of information in the Notice—but it’s not formatted clearly.

🔍 Recommendation: Use a standard template or reference a Schedule:

“The Contractor shall complete Form X (Appendix B), which includes all required details under this Clause.”

This helps contractors provide consistent submissions and helps Employers review quickly.


🧠 BONUS – Suggestions for Both Editions

📌 Define “Plant” precisely in this context

Not all equipment or materials are Plant. Should Clause 11.5 apply only to permanent Plant forming part of the Works?

🔍 Recommendation: Clarify applicability:

“…items of Plant forming part of the Permanent Works and subject to the Employer’s Taking Over obligations.”

This excludes temporary tools or consumables that shouldn’t trigger this level of scrutiny.

🧰 Final Enhancement Tip: Link Clause 11.5 to Schedule Risk Register

Many projects today use a live Risk Register. It might be helpful to require potential off-site removals to be logged proactively, especially if high-value Plant is involved.

“Any anticipated off-site repair scenarios shall be identified during the design stage and included in the Project Risk Register.”

This gets everyone thinking ahead, not reacting later.

7️⃣ Final Takeaways

AspectFIDIC 1999FIDIC 2017
🔄 Consent ProcessBrief, open-endedDetailed with mandatory Notice and checklist
🛡️ Security ProvisionsOptional, at Employer’s discretionExplicit, can require full replacement value
🧾 Documentation RequirementNoneExtensive pre-approval information
🧠 Practical ImplicationSimpler but riskierSafer and more transparent, but more paperwork

✅ The 2017 version of Clause 11.5 reflects a modern approach to contract administration—emphasizing clarity, accountability, and risk control.

✅ Checklist for the Contractor – Requesting Off-Site Removal (FIDIC 2017 – Clause 11.5)

StepDescriptionCompleted ✅
1Identify item of defective or damaged Plant needing off-site repair
2Determine that the defect cannot be remedied expeditiously on Site
3Prepare written Notice to Employer, requesting consent for removal
4Include clear identification of each defective/damaged item
5Describe the nature of the defect or damage
6Provide the repair location/address
7Specify transport method and insurance arrangements
8Detail proposed inspections/testing to be carried out off-site
9State expected duration off-site (repair + return)
10State timeline for reinstallation and retesting on Site
11Submit any additional info requested by the Employer
12Obtain written consent from Employer before removal
13Joint inspection and documentation of condition before dispatch
14Update or provide Performance Security if required
15Ensure tracking and control of item while off-site
16Reinstall, retest and notify Employer upon return

✅ Checklist for Employer/Engineer – Reviewing Contractor’s Clause 11.5 Notice

StepDescriptionCompleted ✅
1Confirm receipt of formal written Notice under Clause 11.5
2Review justification for off-site removal (expediency criteria)
3Check item identification and verify it’s part of the Works
4Validate defect description and need for external repair
5Assess adequacy of repair location and method
6Review transportation and insurance provisions
7Confirm plan for off-site inspections and testing
8Review proposed reinstallation and retesting schedule
9Request and review additional info, if necessary
10Evaluate risk exposure—consider Performance Security adjustment
11Conduct joint inspection and record condition prior to removal
12Provide written consent or justified refusal within time frame
13Ensure monitoring system for tracking item status and return
14Supervise retesting upon return to Site (Clause 7.4 / Clause 9)
15Confirm compliance and close out defect item upon success

✉️ Sample Letter 1 – Contractor’s Request for Off-Site Removal of Defective Plant

Subject: Request for Consent to Remove Defective Plant for Off-Site Repair under Clause 11.5

[Contractor’s Letterhead]

[Date]

To: [The Engineer/Employer’s Representative]
[Employer’s Name]
[Project Name and Contract Number]

Dear [Engineer’s Name],

**RE: Request for Consent to Remove Defective Plant Item for Off-Site Repair – Clause 11.5**

We hereby submit a formal request for consent under **Clause 11.5 [Remedying of Defective Work off Site]** of the Contract to remove the following defective item of Plant for off-site repair:

- **Item Description**: [e.g., Main Control Panel, Serial No. X123]
- **Nature of Defect**: [e.g., Intermittent power failures traced to internal wiring faults]
- **Repair Location**: [e.g., Manufacturer's Service Center, Munich, Germany]
- **Transportation Method**: [e.g., Sealed container via DHL Air Freight]
- **Insurance**: [e.g., Insured with AXA under Policy No. 56789XYZ]
- **Off-Site Inspections/Testing**: [e.g., Factory Acceptance Test (FAT) per IEC 60204]
- **Estimated Time Off-Site**: [e.g., 3 weeks]
- **Return/Reinstallation Plan**: [e.g., Delivery by 10 April, retesting by 14 April under Clause 7.4]

Please find attached technical documentation, photos, insurance certificate, and the proposed testing protocol for your review.

We remain fully responsible for the item and are ready to provide any additional security the Employer may reasonably require, including adjustment of the Performance Security.

Your written consent is kindly requested by **[insert date]** to avoid delays in remedying the defect.

Yours sincerely,
[Name]
[Title]
[Contractor’s Company Name]

✉️ Sample Letter 2 – Employer’s Conditional Consent for Removal

Subject: Conditional Consent for Off-Site Repair of Defective Plant – Clause 11.5

[Employer’s Letterhead or Engineer’s Letterhead]

[Date]

To: [Contractor’s Name]
[Contractor’s Company Name]
[Project Name and Contract Number]

Dear [Contractor’s Representative],

**RE: Consent for Removal of Defective Plant Off-Site – Clause 11.5**

We refer to your letter dated [insert date], requesting to remove [Plant item] for repair off-site in accordance with **Clause 11.5** of the Contract.

The Employer hereby provides **conditional consent** to proceed with the removal, subject to the following:

1. **Increase of Performance Security**: Please provide a revised Performance Security covering the full replacement cost of the item, valued at [amount].
2. **Notification of Shipping and Receipt Dates**: Provide evidence of dispatch and receipt at the repair facility.
3. **Return and Testing Schedule**: Strict adherence to the reinstallation and testing plan as proposed. Any changes must be notified in advance.

This consent does **not relieve** the Contractor of its obligations under the Contract. The Employer reserves the right to verify repair progress and participate in off-site inspections.

Please acknowledge your agreement to the above conditions in writing before removal.

Yours faithfully,
[Name]
[Title – Engineer or Employer’s Representative]
[Employer’s Name]

✉️ Sample Letter 3 – Engineer’s Rejection of Off-Site Removal Request

Subject: Rejection of Request for Off-Site Repair – Clause 11.5

[Engineer’s Letterhead]

[Date]

To: [Contractor’s Name]
[Contractor’s Company Name]
[Project Name and Contract Number]

Dear [Contractor’s Representative],

**RE: Rejection of Request for Off-Site Repair of Plant – Clause 11.5**

We acknowledge receipt of your Notice dated [insert date] requesting consent to remove the [item description] from Site for off-site repair under **Clause 11.5**.

After due consideration, the Employer has decided **not to grant consent** for the following reasons:

- Adequate repair resources are available on Site or locally.
- The proposed repair timeline is incompatible with the Project schedule.
- Inadequate details were provided regarding transport security and insurance.

You are therefore instructed to proceed with an **on-site remedy** of the defect, or submit a revised request with sufficient justification and detail.

Yours sincerely,
[Name]
[Title – Engineer]
[Employer’s Name]

✉️ Sample Letter 4 – Contractor’s Confirmation of Return and Reinstallation

Subject: Notification of Return, Reinstallation, and Retesting – Clause 11.5

[Contractor’s Letterhead]

[Date]

To: [The Engineer/Employer’s Representative]
[Employer’s Name]
[Project Name and Contract Number]

Dear [Engineer’s Name],

**RE: Return and Reinstallation of Plant Item Repaired Off-Site – Clause 11.5**

We write to inform you that the [Plant item] previously removed for repair under **Clause 11.5** has been returned to Site on [date].

Reinstallation will commence on [date] and retesting will be conducted on [date] in accordance with:
- Sub-Clause **7.4 [Testing by Contractor]**
- Clause **9 [Tests on Completion]**, where applicable

Please confirm the Engineer’s availability to witness the test, or nominate a representative.

Attached are:
- Delivery receipt
- Repair certificate
- Test reports from the off-site facility

Yours faithfully,
[Name]
[Contractor’s Representative]
[Company Name]