Purpose of Clause 12 — Tests after Completion
A fast, field-ready explainer of why Clause 12 exists, who it protects, and how it balances risk for both parties (📘1999 & 📒2017).
Verify real-world performance after Taking-Over
Clause 12 makes sure the Works (or a Section) are tested in genuine operating conditions after Taking-Over to confirm they meet the Employer’s specified performance criteria. The Employer runs these tests (with the Contractor’s guidance/attendance), the parties jointly evaluate the results, and any prior use by the Employer is taken into account. If the tests are delayed or can’t be completed for reasons not attributable to the Contractor, the Contract provides compensation mechanisms and—with defined triggers—deemed pass safeguards to prevent open-ended exposure.
Tip: Pair this purpose section with clearly defined KPIs, instrumentation accuracy, and pass/fail logic in your Employer’s Requirements.
Clause reference: **Clause 12 — Tests after Completion** (applies after Taking-Over; Employer runs tests; results jointly evaluated; fairness mechanisms for delay and “deemed pass” are provided in the Contract).
Breakdown of Clause 12 — Tests after Completion (📘1999 vs 📒2017)
Side-by-side essentials for **12.1–12.4** with timelines, roles, and “what happens if…” outcomes. Click to reveal.
Who provides what & how the day runs
- Employer provides electricity, equipment, fuel, instruments, labour, materials, and qualified staff.
- Tests follow O&M guidance provided by the Contractor; Contractor’s Personnel attend.
- Notice: Employer gives 21 days notice of the date after which tests will be carried out; tests occur within 14 days after that date, on days the Employer decides.
- If the Contractor doesn’t attend, Employer may proceed; tests are deemed in Contractor’s presence and readings stand.
- Results are jointly evaluated and prior Employer use is taken into account.
Sharper anchors: Requirements + Programme
- Employer provides utilities (incl. water/sewage if relevant), equipment, fuel/consumables, instruments, labour, materials, and competent staff.
- Tests follow the Employer’s Requirements and O&M Manuals issued with No-objection; Contractor attends/guides.
- Notice: the Engineer gives at least 21 days notice of the date and place and includes a test programme; unless agreed otherwise, tests occur on that date.
- If the Contractor doesn’t attend, Employer may proceed; readings stand.
- Results are jointly evaluated; prior Employer use is considered.
Delayed Tests
- If the Employer unreasonably delays, the Contractor (by notice under 20.1) is entitled to Cost + reasonable profit.
- If a Test can’t be completed within the Defects Notification Period (DNP) for reasons not attributable to the Contractor, the Works/Section are deemed to have passed that Test.
Delayed Tests (updated claims route)
- Same protective logic; entitlements channel through Clause 20 (Claims), commonly referenced as 20.2 procedure.
- “Deemed pass” if not attributable to Contractor within the DNP (or other agreed period) still applies.
Retesting after failure
- On failure, 11.1(b) applies; either Party may require failed tests (and related tests) to be repeated after remedy.
- If failure/retesting arises from matters in 11.2(a)–(d), and causes Employer extra cost, Contractor pays (via 2.5 Employer’s Claims).
Retesting via Defects clause
- On failure, 11.1(b) applies; after remedying, 11.6 (Further Tests after Remedying Defects) governs retesting.
- Employer recovers attributable extra costs (matters under 11.2(a)–(d)) through the unified Clause 20 claims route.
Failure to pass & non-performance damages
- If Tests fail and a non-performance damages sum/method is stated, Contractor pays during DNP ➜ Works/Section are deemed to have passed.
- If Contractor proposes modifications, Employer may delay access; Contractor remains liable to adjust and satisfy the Test within a reasonable period after access is given.
Performance Damages & access safeguards
- Failure triggers Performance Damages (per Schedule of Performance Guarantees) — typically in full satisfaction of the failure. Payment within DNP ➜ deemed pass.
- If Contractor proposes modifications and Employer withholds access until a “convenient time”, Contractor must adjust; but if no access within the relevant DNP, Contractor is relieved and the Works/Section are deemed to have passed.
- Unreasonable delay in access entitles Contractor to Cost + Profit via the claims procedure under Clause 20.
Clause references: **12.1–12.4** with cross-links to **11.1(b)**, **11.2(a)–(d)**, **11.6**, **20** (2017 unified claims), **20.1/2.5** (1999 split). Durations like **21 days** and **14 days** are shown where applicable. This is an editorial aid—always verify against your executed Contract.
Key Interpretations & Implications — Clause 12 (📘1999 vs 📒2017)
Practical meanings behind the wording: who runs the tests, timing signals, “deemed pass” safety valves, money routes, and the rationale for the 📒2017 edits.
Who runs the tests & how guidance works
- Employer conducts Tests after Completion; Contractor attends, guides, and interprets O&M/testing guidance.
- 📒2017 anchors procedures to the Employer’s Requirements and O&M Manuals issued with No-objection.
Interpretative question: does 📒2017 expect higher Employer preparedness?
Notices & execution anchors
- 📘1999: Employer gives 21 days notice of the date after which tests will be carried out; tests occur within 14 days after that date.
- 📒2017: Engineer gives ≥ 21 days notice of the date & place and includes a test programme; tests are held on that date unless otherwise agreed.
Can the Employer control slippage better in 📒2017?
When “deemed pass” can apply
- Both editions: if tests can’t be completed within the DNP for reasons not attributable to the Contractor → deemed pass.
- 📒2017 enhancement: if the Contractor proposes modifications but no access is given within the relevant DNP, the Contractor is relieved and the Works/Section are deemed to have passed; unreasonable access delay → Cost + Profit (claims route).
Is this fair to the Employer?
How entitlements are routed
- 📘1999: Contractor uses 20.1 (Contractor’s Claims); Employer recovers via 2.5 (Employer’s Claims).
- 📒2017: unified process under 20.2 (Claims) for both Parties → cleaner references in 12.2/12.4 and 11.6 retesting.
Practical tip: how to avoid “wrong clause” arguments?
Why the 2017 edits matter
- Clarity on responsibilities, scheduling, and consequences.
- Stronger tie-in to Schedule of Performance Guarantees for Performance Damages.
- Emphasis on specifying KPIs, baseline conditions, and instrumentation so tests are objectively verifiable.
What should go into Employer’s Requirements?
Clause references: 12.1–12.4, cross-ref. 11.6 and Clause 20 (📒2017 unified 20.2 vs 📘1999 20.1/2.5). Durations like 21 days and 14 days shown where applicable. Always verify against your executed Contract.
Cross-Referencing with Other Clauses — Clause 12 (Tests after Completion)
How Clause 12 plugs into 9, 10, 11, 13, 14, 17/18, 20, and the Schedule of Performance Guarantees—with pitfalls, tips, and copy-ready PCs. Click to reveal.
Before & After: commissioning ➜ Taking-Over ➜ 12 tests
- Clause 9 gets you ready (pre-TOC checks); Clause 12 proves performance after Taking-Over.
- Clause 10 starts the DNP and flips risk/operation to Employer—yet the Contractor still attends/guides 12 tests.
- Timing signal: 📘1999 uses 21 days notice + tests within 14 days after; 📒2017 uses ≥ 21 days notice of the date & place + a test programme.
Tip — map the sequence in PCs
When 12 finds a shortfall, 11 drives the remedy
- 11.1(b): Contractor remedies defects/damage revealed by 12 tests.
- 📒2017: retesting is under 11.6 (Further Tests after Remedying Defects) rather than “either Party may require” (1999).
- 11.2(a)–(d): who pays for retest costs where cause is Contractor-side.
- 11.3: DNP can extend for substantially remedied parts—synchronise your 12 retest timing.
Who breaks ties on procedures, instruments, borderline results?
- 📘1999 3.5 vs 📒2017 3.7: use determinations for script disputes, data quality, and “pass vs marginal” calls.
- PC idea: if data quality is disputed, Engineer must set a validation plan (spot checks / second instrument / sub-run) within 7 days.
How delay/access costs flow under 12.2 & 12.4
- 📘1999: Contractor uses 20.1 (≤ 28 days notice); Employer uses 2.5.
- 📒2017: unified 20.2 for both Parties—clean references for Cost / Cost + Profit.
- “Deemed pass” applies if tests can’t complete within the DNP for reasons not attributable to the Contractor.
Scenario — grid curtailment for 45 days
Variations can change the target you test against
- Variation after TOC? Align performance KPIs, procedures, and 12.4 damages; don’t test outdated targets.
- PC: “If a Variation materially affects the Schedule of Performance Guarantees, adjust KPIs, tolerances, test duration, and damages neutrally.”
Paying Performance/Non-performance Damages; set-off order
- 14 governs payment and set-off; ensure damages under 12.4 can be set-off cleanly without choking unrelated cash flow.
- 4.2: PCs can define the order—(i) invoice & pay, (ii) set-off, (iii) call security if needed.
Who carries what risk during post-TOC test runs?
- After TOC, Employer’s care resumes, but Contractor’s testing operations can still create Contractor liabilities.
- Ensure insurance explicitly covers operation for testing after Taking-Over (hot runs included).
Where 12.4 points for damages & deemed pass
- 📒2017: Performance Damages listed here are usually in full satisfaction of that failure; if paid within DNP → deemed pass.
- Define KPIs, tolerances, ambient/utilities bands, averaging windows, and instrument accuracy—vagueness breeds disputes.
Why O&M and ER detail makes 12.1 “test-day ready”
- 📒2017: 12.1 anchors to Employer’s Requirements & O&M Manuals with No-objection—thin manuals lead to chaotic test days.
- Add a “Test Data Pack”: calibrated instrument list, trending points, logging interval, and acceptance logic.
Clause interplay in action
- 35 days access delay post-TOC → 12.2 claim via 20.2; if still blocked within DNP (not Contractor’s fault) → deemed pass.
- Heat-rate fail; Contractor remedies; Employer won’t schedule retest → 11.6 governs; if no access within DNP (📒2017) → relief + deemed pass; plus Cost + Profit for unreasonable delay.
- Variation swaps cooling tower type; KPIs unchanged → adjust via 13 or you’ll test the wrong target under 12.4.
Particular Conditions (paste-in snippets)
- Test Programme (12.1): “Engineer’s ≥ 21 days notice shall attach a day-by-day programme, instrument accuracy classes, calibration dates, sampling frequency, and pass/fail logic. Contractor comments within 7 days; silence = no-objection.”
- Deemed Pass (12.2/12.4): “If tests cannot be completed within the DNP for reasons not attributable to the Contractor, the test is deemed passed. If Contractor proposes modifications but access is not granted within the DNP, the Contractor is relieved and the test is deemed passed; any unreasonable delay entitles the Contractor to Cost + Profit under Clause 20.”
- Variation Alignment (13): “Variations materially affecting performance shall trigger neutral adjustment of KPIs, procedures, tolerances, and Performance Damages in the Schedule of Performance Guarantees.”
- Insurance (17/18): “Insurance shall expressly cover operation for testing after Taking-Over, including hot runs under Clause 12, with limits/deductibles stated.”
- Set-off Ladder (14/4.2): “Damages due under 12.4 are settled by (i) invoice & pay, (ii) set-off under 14, (iii) 4.2 security only if (i)–(ii) fail.”
Clause references: 9, 10, 11.1(b), 11.2(a)–(d), 11.6, 12.1–12.4, 13, 14, 4.2, 17/18, 20. Durations like 21 days, 14 days, 28 days highlighted for clarity. Always verify against your executed Contract.
Suggestions for Clarity & Improvement — Clause 12 (Tests after Completion)
Turn Clause 12 into a site-ready test playbook: crisp KPIs, dependable test-day governance, clean claims plumbing, and fair “deemed pass” safety valves. Click to reveal.
Define what, how, and under which conditions you measure
Most disputes start with fuzzy “meets Employer’s Requirements.” Lock the variables, reference conditions, sampling, averaging, and acceptance math.
📄 Model PC wording
Use the ≥ 21 days notice to attach a real programme
📒2017 expects a programme; make it a checklist so test day isn’t guesswork.
📄 Model PC wording
Accuracy, traceability, and dispute short-circuits
Arguments often hinge on calibration/accuracy. Pre-agree a validation path.
📄 Model PC wording
Write the safety valves clearly
Both editions support “deemed pass”; 📒2017 also relieves the Contractor if no access within DNP after proposing modifications.
📄 Model PC wording
Stop the “we’ll find a date later” spiral
Without a timebox, access drifts and risk never closes.
📄 Model PC wording
Route retests via 11.6 (📒2017)
Avoid “either Party may require” ambiguity from 📘1999.
📄 Model PC wording
Prevent double-counting; cap exposure
📄 Model PC wording
Rate × ΔQ × hours
, capped at 2% of the Section price.When scope changes, move the target too
📄 Model PC wording
Plan for weather/utility bands
📄 Model PC wording
Independent validation + same-day paperwork
📄 Model PC wording
Don’t lose the evidence
📄 Model PC wording
Make settlement mechanical, not emotional
📄 Model PC wording
Stop infinite “almost there” testing
📄 Model PC wording
Bundle the essentials into one addendum
📄 Combined wording
Generate a ready-to-paste KPI clause snippet
Durations like 21 days, 14 days, 28 days are highlighted to match contract timing signals. Always verify against your executed Contract and the edition in use (📘1999 / 📒2017).
Tests after Completion by Contractor as Testing Agent — Particular Conditions (PCs)
When the Employer isn’t equipped to run the tests, delegate execution to the Contractor as agent while preserving FIDIC’s Golden Principles: clear roles, balanced risk, Engineer’s control, and intact claims/damages logic. Click to reveal.
Definition — “Testing Agent”
Purpose: delegate the doing of the tests to the Contractor without moving acceptance, risk, or remedies.
PC — 12.1 Procedure (delegation + programme)
Make the Contractor run the tests as agent; keep the Engineer’s control and the timing language of your chosen edition.
📄 Model PC wording
PC — 12.2 Delayed Tests (claims preserved)
Delegation must not dilute delay remedies or “deemed pass” safety valves.
📄 Model PC wording
PC — 12.4 Failure to Pass (mods, deemed pass & damages)
Keep the Performance/Non-performance Damages regime and the 2017 “access not given within DNP” relief.
📄 Model PC wording
PC — Retesting after remedy
📄 Model PC wording
PC — Risk & Insurance during agent testing
📄 Model PC wording
PC — Payments (Clause 14)
📄 Option A — Reimbursable
📄 Option B — Lump Sum
What-if scenarios (how this plays out)
- Data-center load bank: Contractor brings temporary load bank, operates as Testing Agent; Engineer issues ≥ 21 days notice with programme; acceptance by Engineer; if utility fault blocks run within DNP → deemed pass route stands.
- WTP chemical dosing: Contractor’s chemists and skids; Employer provides raw water & PTW. Upstream fluctuation trips pump → retest planned within 14 days; Contractor recovers Cost (and Profit if 2017) under Clause 20.
- Heat-rate shortfall: Contractor proposes burner tweaks; Employer defers outage beyond DNP → (2017) relief + deemed pass; damages apply only if specified and not cured.
Edition-aware toggles adjust only wording that differs (notice cadence, claims plumbing, retesting route). Core risk, Engineer’s role, and remedies remain balanced in line with FIDIC Golden Principles.
Clause 12 — Tests after Completion: 12 Ready-to-Use Letter Templates
Edition-aware templates for 📒 2017 and 📘 1999 with one-click copy. Filter, toggle edition, and export. Click to reveal.
1) Engineer’s Notice — Tests after Completion (programme attached)
Use this to formally notify tests and share the programme, instruments, and pass/fail logic.
2) Contractor’s Acknowledgment & Comments on Test Programme
3) Contractor Readiness & Request for Access / PTW
4) Delayed/Blocked Tests — Notice & Claim (Employer-side cause)
5) Test Failure — Contractor’s Modification Proposal & Access Request
6) No Access within DNP → Deemed Pass
7) Submission of Test Data Pack
8) Engineer’s Determination Request (procedure/instrument dispute)
9) Retesting after Remedy (schedule & scope)
10) Seasonality/Exceptional Event — Propose Correction or Deferral
11) Employer Notice — Performance Damages & Set-Off
12) Appointment of Independent Test Witness
Editions differ mainly in notice cadence (12.1), retesting route (11.6 vs 12.3), and claims plumbing (20.2 vs 20.1). Always confirm against your executed Contract and Contract Data.
1) Edition & Parties
2) Scheduling & Notice
3) KPIs & Measurement Methods
KPI | Target | Unit | Method | Avg Period | Instrument ±% | Pass if |
---|