Clause 15.2 Termination by Employer: Comprehensive Guide to FIDIC Contract Management

Clause 15.2 of the FIDIC Yellow Book outlines specific circumstances under which the Employer is entitled to terminate the Contract with the Contractor. It’s crucial for both parties in a construction project to understand the implications of this clause. Here’s a detailed breakdown:

  1. Non-compliance and Corrective Notices: The Employer can terminate the Contract if the Contractor fails to comply with the Performance Security requirements (Sub-Clause 4.2) or doesn’t rectify a problem after receiving a notice to correct (Sub-Clause 15.1).
  2. Abandonment or Non-performance: Termination is justified if the Contractor abandons the Works or clearly shows an intention not to fulfill their obligations. Also, failure to progress with the Works (Clause 8) or to comply with a notice regarding rejection (Sub-Clause 7.5) or remedial work (Sub-Clause 7.6) within 28 days can lead to termination.
  3. Unauthorized Subcontracting or Assignment: The Contract may be terminated if the Contractor subcontracts the entire Works or assigns the Contract without the necessary agreement.
  4. Financial Instability: If the Contractor becomes bankrupt, insolvent, or undergoes similar financial difficulties, the Employer has the right to terminate the Contract.
  5. Ethical Violations: Offering bribes or other unethical inducements related to the Contract by the Contractor or their personnel can lead to immediate termination.
  6. Procedure and Notice: The Employer must provide 14 days’ notice for termination, except in cases of financial instability or ethical violations, where immediate termination is allowed.
  7. Post-termination Obligations: After termination, the Contractor must leave the Site and hand over all relevant documents and Goods to the Engineer. They must also comply with any reasonable instructions for safeguarding life, property, and the safety of the Works.
  8. Employer’s Rights Post-Termination: The Employer may complete the Works themselves or through other entities, using the Contractor’s Goods and documents.
  9. Disposition of Contractor’s Equipment: The Employer will release the Contractor’s Equipment and Temporary Works to the Contractor for removal. However, if the Contractor owes any payment to the Employer, the Employer may sell these items to recover the payment.

General Overview of Clause 15.2:

Clause 15.2 in the FIDIC Yellow Book provides a structured framework for an Employer to lawfully terminate a contract with the Contractor under specific circumstances. This clause plays a vital role in ensuring that the contractual obligations are met with integrity and professionalism. It safeguards the Employer’s interests against various risks, including non-performance, ethical violations, financial instability of the Contractor, and unauthorized subcontracting or assignment of the contract.

Diverse Interpretations of Clause 15.2 (Termination by Employer) in FIDIC Yellow Book

1. Purpose of Clause 15.2:

  • Primary Intent: This clause is designed to provide a clear, legal pathway for the Employer to terminate the contract under specific circumstances that indicate a breach or failure by the Contractor.
  • Risk Mitigation: It serves as a risk management tool, enabling the Employer to mitigate potential losses or damages arising from the Contractor’s non-compliance, financial instability, unethical practices, or abandonment of work.

2. Implications of Clause 15.2:

  • For Employers: It empowers Employers with a structured process to safeguard their interests. Employers can act decisively in cases of non-performance or contractual breaches.
  • For Contractors: This clause underscores the importance of adherence to contract terms. It highlights the risks Contractors face if they fail to comply with contractual obligations or engage in unethical behavior.

3. Primary Aspects of Clause 15.2:

  • Specific Grounds for Termination: The clause outlines various grounds for termination, including non-compliance with performance security, abandonment of works, failure to rectify issues, unauthorized subcontracting, financial instability, and ethical violations.
  • Notice Requirement: The clause specifies the necessity of a notice period (usually 14 days) before termination, except in cases of ethical violations or financial instability.
  • Post-Termination Obligations: It details the obligations of the Contractor post-termination, like vacating the site and handing over documents and materials.

Expert Opinion and Broader Implications:

  • Risk Management: Understanding this clause helps both parties manage risks associated with contractual breaches and non-performance.
  • Ethical Standards: The clause underscores the importance of ethical conduct in construction projects, particularly concerning financial dealings and subcontracting.
  • Financial Security: The provision related to financial instability serves as a safeguard for the Employer against potential project disruptions due to the Contractor’s financial woes.

Key Components of Clause 15.2:

  1. Non-Compliance and Correction Notices: The Employer can terminate the contract if the Contractor fails to adhere to the Performance Security (Sub-Clause 4.2) or does not rectify an issue highlighted in a ‘Notice to Correct’ (Sub-Clause 15.1).
  2. Project Abandonment or Non-Performance: This includes situations where the Contractor abandons the work, demonstrates a clear intent not to continue, or fails to progress as per Clause 8 (Commencement, Delays, and Suspension) or comply with notices regarding rejected work (Sub-Clause 7.5) or remedial work (Sub-Clause 7.6).
  3. Unauthorized Actions: This involves situations where the Contractor subcontracts the entire work or assigns the contract without appropriate permission.
  4. Financial Instability: The clause covers scenarios where the Contractor faces bankruptcy, insolvency, or similar financial issues.
  5. Ethical Violations: The clause allows termination if the Contractor is involved in unethical practices like offering bribes or inducements related to the contract.
See also  Comprehensive Analysis of Clause 11.3 Extension of DNP

Process Flow for Termination:

  1. Identification of a Breach: The first step involves identifying a breach of contract as outlined in the clause.
  2. Issuance of Notice: Depending on the type of breach, the Employer may be required to give a 14-day notice to the Contractor, except in cases of financial instability or ethical violations where immediate termination is allowed.
  3. Contractor’s Response and Obligations: Post-termination, the Contractor must vacate the site and hand over all relevant documents and materials. They must also adhere to instructions related to safety and preservation of the site.
  4. Employer’s Rights and Actions Post-Termination: The Employer can complete the works themselves or contract it out to other entities, using the Contractor’s resources if necessary.
  5. Disposition of Contractor’s Equipment: The Employer releases the Contractor’s Equipment for removal unless there are outstanding payments due, in which case the Employer may sell the items to recover the cost.

Applicability and Implementation:

  • When to Invoke Clause 15.2: This clause is invoked when there is a clear breach of the terms as outlined. It is crucial for the Employer to document and substantiate the breach.
  • Legal and Ethical Considerations: The application of this clause requires careful consideration of legal standards and ethical practices. In contexts like the United States, local building codes, environmental laws, and business ethics must be considered.

Interaction with Other Clauses

1. Interaction with Clause 4.2 (Performance Security):

  • Direct Connection: Clause 15.2 allows for contract termination if the Contractor fails to comply with the requirements of Performance Security as stipulated in Clause 4.2. This emphasizes the critical nature of the Performance Security in ensuring the Contractor’s commitment to fulfilling the contract.
  • Consequence Management: Clause 4.2 outlines the consequences of failing to maintain valid Performance Security, which directly feeds into the grounds for termination under Clause 15.2.

2. Interaction with Clause 15.1 (Notice to Correct):

  • Precursor to Termination: Clause 15.1 serves as a preliminary step before Clause 15.2 can be invoked. It requires the Employer or Engineer to give notice to the Contractor to correct a failure. Failure to remedy the issue within a reasonable time can then lead to termination under Clause 15.2.
  • Opportunity for Rectification: This interaction offers the Contractor a chance to rectify issues before facing termination, highlighting the fair and procedural approach of the FIDIC contracts.

3. Interaction with Clause 7.5 (Rejection) and Clause 7.6 (Remedial Work):

  • Basis for Termination: Non-compliance with Clauses 7.5 and 7.6 can be grounds for termination under Clause 15.2. If the Contractor fails to correct rejected work or carry out remedial work as instructed, it signifies a breach of contract.
  • Quality and Compliance Assurance: These clauses collectively ensure that the work’s quality meets the contract’s standards and that any deficiencies are promptly addressed.

4. Interaction with Clause 2.5 (Employer’s Claims):

  • Financial Implications: If the Employer has a claim under the contract that the Contractor fails to honor, this can lead to termination under Clause 15.2. Clause 2.5 provides a framework for the Employer to make such claims.
  • Claims Process and Contract Enforcement: This interaction underscores the structured process for handling disputes or claims and the potential consequences of unresolved issues.

5. Interaction with Clause 8.8 (Suspension of Work):

  • Suspension Leading to Termination: While Clause 8.8 deals with the suspension of work, prolonged or unresolved suspensions, particularly if due to the Contractor’s responsibility, could escalate to termination under Clause 15.2.
  • Control Over Work Progression: This interaction highlights the Employer’s and Engineer’s control over the project’s progression and the Contractor’s obligation to comply with directives, failure of which can lead to severe contract repercussions.

6. Interaction with Clause 19 (Force Majeure)

  • Clause 15.2 and Clause 19: Although Clause 15.2 outlines grounds for termination by the Employer, Clause 19 (Force Majeure) can provide exceptions where termination might not be justifiable due to extraordinary events beyond the Contractor’s control.
  • Shared Effect: This interaction ensures fairness in contract termination, considering unforeseen and uncontrollable circumstances.

Expert Opinion:

  • Holistic Contract Management: The interactions of these clauses form a comprehensive framework for managing various aspects of a construction contract, from performance security to quality control and financial management.
  • Balanced Approach: These clauses, in conjunction with Clause 15.2, ensure a balanced approach, providing opportunities for correction and compliance before leading to the severe step of contract termination.
  • Risk Mitigation: Understanding these interactions is crucial for both parties to mitigate risks and adhere to contractual obligations effectively.

Main Points to remember while Employing Clause 15.2

  1. Grounds for Termination: Understand the specific conditions under which the Employer is entitled to terminate the contract, such as non-compliance with Performance Security (Clause 4.2), failure to correct issues (Clause 15.1), non-conformity with contract standards (Clauses 7.5 and 7.6), financial instability, or ethical violations by the Contractor.
  2. Notice Requirements: Be aware of the requirement for a notice period, typically 14 days, before termination, except in cases of immediate concerns like ethical violations or financial instability.
  3. Opportunity for Rectification: Prior to termination, there is usually an opportunity for the Contractor to rectify the issue, particularly under Clause 15.1 (Notice to Correct). This step is crucial for procedural fairness.
  4. Documentation and Communication: Maintain clear documentation and communication throughout the process. This includes issuing notices with reasons for rejection or rectification (Clause 7.5 and 7.6) and keeping records of all interactions and breaches.
  5. Implications of Non-compliance with Other Clauses: Be aware of the implications of the Contractor’s non-compliance with other related clauses (like Clauses 2.5, 4.2, 7.5, 7.6, and 8.8) and how they can lead to the invocation of Clause 15.2.
  6. Contractor’s Post-Termination Obligations: Understand the Contractor’s obligations after termination, such as vacating the site and handing over documents and materials.
  7. Employer’s Rights Post-Termination: Recognize the Employer’s rights after termination, including the completion of the works by themselves or through other entities, and the use of the Contractor’s resources if necessary.
  8. Handling of Contractor’s Equipment: Be aware of the procedures for handling the Contractor’s equipment post-termination, especially in cases of outstanding payments.
  9. Legal and Ethical Considerations: Always consider the legal and ethical aspects, ensuring that the termination process is justified, fair, and in compliance with the contractual terms.
  10. Risk Management: Consider the clause as part of broader risk management in project execution, ensuring that it’s employed as a last resort and with due consideration to the implications for both parties.
See also  Clause 4.3 Contractor's Representative of FIDIC Yellow Book 1999

Implementing Clause 15.2 (Termination by Employer) from the FIDIC Yellow Book effectively involves several essential factors:

  1. Clear Understanding of Grounds for Termination: Familiarize yourself thoroughly with the specific conditions outlined in Clause 15.2 under which the Employer is entitled to terminate the contract. This includes non-compliance with key clauses, financial instability, ethical violations, and failure to rectify issues after receiving a notice.
  2. Strict Adherence to Contractual Procedures: Follow the procedures stipulated in the contract precisely. This includes issuing proper notices (as required under Clauses 15.1, 7.5, and 7.6), respecting the notice periods, and ensuring all actions are well-documented and justified as per the contract terms.
  3. Proper Documentation and Record-Keeping: Maintain comprehensive records of all communications, notices, and actions taken in relation to the clause. This includes documentation of any breaches, notices issued to correct these breaches, and responses from the Contractor.
  4. Fair and Reasonable Approach: Ensure that the decision to terminate is fair, reasonable, and a last resort. Give the Contractor an opportunity to rectify the issues, where applicable, and consider the implications of termination for both parties.
  5. Legal Compliance: Ensure that the implementation of Clause 15.2 complies with the local laws and regulations. This is particularly important in terms of financial insolvency and ethical violations.
  6. Risk Assessment and Management: Assess the risks associated with terminating the contract, including the potential impact on project timelines, costs, and quality. Have a plan in place for completing the project post-termination.
  7. Effective Communication: Communicate clearly and promptly with all relevant parties, including the Contractor, Engineer, and legal advisors. Ensure that the reasons for termination are clearly articulated and understood.
  8. Post-Termination Management: Be prepared to manage the project post-termination, which may involve hiring a new contractor, reallocating resources, and addressing any legal or financial implications.
  9. Ethical Considerations: Act ethically and in good faith throughout the process. Ensure that the termination is not based on arbitrary or unfair reasons.
  10. Seeking Expert Advice: Consider consulting with legal experts or professionals experienced in FIDIC contracts to ensure that the clause is implemented correctly and to mitigate any potential legal challenges.

Detail the Sequence of Interactions related to Clause 15.2

  1. Identification of a Potential Breach:
    • The process begins when the Employer identifies a potential breach of contract by the Contractor, which could fall under the conditions outlined in Clause 15.2, such as failure to comply with Performance Security (Clause 4.2), failure to rectify issues (Clause 15.1), or non-compliance with quality standards (Clauses 7.5 and 7.6).
  2. Issuance of Notice to Correct (Clause 15.1):
    • If applicable, the Employer or Engineer issues a ‘Notice to Correct’ under Clause 15.1. This notice requires the Contractor to rectify the identified failure within a specified reasonable time.
  3. Evaluation of Contractor’s Response:
    • The Employer evaluates the Contractor’s response to the Notice to Correct. If the Contractor fails to address the issues within the given timeframe, it escalates the matter.
  4. Consideration of Termination (Clause 15.2):
    • Based on the Contractor’s response (or lack thereof), the Employer considers terminating the contract under Clause 15.2. This decision is taken in light of the severity of the breach and the potential impact on the project.
  5. Issuance of Termination Notice (Clause 15.2):
    • If the decision to terminate is made, the Employer issues a termination notice as per Clause 15.2. This notice typically provides a 14-day period before termination takes effect, except in cases of immediate concerns like ethical violations or financial instability.
  6. Contractor’s Obligations Post-Termination:
    • Upon termination, the Contractor is obligated to follow the procedures outlined in Clause 15.2, which include vacating the site and handing over all relevant documents and materials.
  7. Employer’s Actions Post-Termination:
    • The Employer may take over the completion of the project, either by themselves or through other contractors. They may use the Contractor’s resources if necessary as outlined in Clause 15.2.
  8. Handling of Financial and Legal Matters:
    • The Employer and Contractor settle any financial matters arising from the termination, including the handling of Performance Security (Clause 4.2) and addressing any claims (Clause 2.5).
  9. Resolution of Remaining Obligations and Rights:
    • The Employer and Contractor address any remaining obligations and rights, including the handling of equipment and materials as per the contractual terms.
  10. Review and Learning:
  • After termination, it’s advisable for both parties to review the sequence of events leading to termination, to learn and improve future contract management and project execution.
See also  Clause 9.2 Delayed Tests

Structured Checklists

1. Checklist for Proficient Execution and Deployment of Clause 15.2

StepAction ItemDetailsResponsible Party
1Identify Potential BreachReview contract terms to identify non-complianceEmployer
2Document EvidenceGather documentation or evidence of the breachEmployer
3Internal ReviewAssess the severity and impact of the breachEmployer
4Communicate with ContractorNotify the Contractor of the identified breachEmployer
5Await Contractor’s ResponseAllow time for the Contractor to acknowledge or dispute the breachEmployer
6Decision to TerminateDecide whether the breach warrants contract terminationEmployer
7Issue Notice of TerminationIf terminating, issue a 14-day notice to the ContractorEmployer
8Oversee HandoverEnsure the Contractor hands over documents and goodsEngineer
9Confirm Completion of HandoverVerify all necessary items are receivedEngineer
10Release Contractor’s EquipmentArrange for the release and removal of Contractor’s equipmentEmployer
11Complete the WorksPlan and execute the completion of the worksEmployer
StepAction
Identify Potential BreachMonitor contract compliance; identify breaches eligible under Clause 15.2.
Issue Notice to Correct (Clause 15.1)Formally issue a ‘Notice to Correct’ under Clause 15.1 if applicable.
Evaluate Contractor’s ResponseAssess if the Contractor has adequately addressed the issues within the specified timeframe.
Consider Termination (Clause 15.2)Decide on contract termination, considering the severity and impact of the breach.
Issue Termination NoticeProvide a formal termination notice, respecting the required notice period.
Oversee Contractor’s Post-Termination ActionsEnsure the Contractor vacates the site and hands over necessary documents/materials.
Manage Project Post-TerminationTake over or reassign completion of the project, using available resources.
Resolve Financial and Legal MattersSettle any outstanding payments, claims, and handle Performance Security.
Review and Learn from ProcessAnalyze the termination process for insights and future improvements.

2. Checklist for Applying and Overseeing Clause 15.2

StepAction ItemDetails
1Breach IdentificationIdentify and document the specific breach of contract
2Evaluate Breach ImpactAssess the impact and severity of the breach
3Contractor NotificationInform the Contractor of the breach and await response
4Review Contractor’s ResponseEvaluate the Contractor’s acknowledgment or dispute
5Termination DecisionDecide on contract termination based on the breach and response
6Notice of TerminationIssue a formal 14-day termination notice if required
7Handover SupervisionOversee the handover of documents and goods from the Contractor
8Equipment ReleaseFacilitate the release and removal of Contractor’s equipment
9Project CompletionPlan for the completion of the works post-termination
TaskDescription
Documenting BreachMaintain clear records of breaches and corresponding notices.
CommunicationEnsure clear, timely communication with all parties involved.
Legal ComplianceVerify compliance with local laws and contractual terms.
Risk ManagementAssess and manage risks associated with termination.
Ethical ConsiderationsAct ethically and in good faith throughout the process.

3. Checklist for Execution and Supervision of Clause 15.2

StepAction ItemDetails
1Breach VerificationConfirm the occurrence of a contract breach
2DocumentationCollect and organize evidence of the breach
3Internal DeliberationConduct an internal review to evaluate the breach
4Contractor CommunicationDiscuss the breach with the Contractor
5Response AnalysisAnalyze the Contractor’s response to the breach
6Termination JudgementMake a judgement on contract termination
7Termination NoticeProvide the Contractor with a termination notice
8Handover CoordinationCoordinate the handover of necessary items
9Equipment HandlingManage the release and removal of equipment
10Work Completion StrategyDevelop a strategy for completing the remaining works
AspectGuideline
Breach IdentificationRegularly review contract performance to identify potential breaches.
Notice IssuanceIssue corrective notices as per Clause 15.1 when necessary.
Response AssessmentClosely monitor the Contractor’s response to notices.
Termination DecisionCarefully consider the need for contract termination.
Post-Termination ManagementEffectively manage the transition and completion of the project post-termination.

FAQs on Clause 15.2 (Termination by Employer) of FIDIC Yellow Book

What constitutes grounds for termination under Clause 15.2?

A: The Employer can terminate the contract under Clause 15.2 for reasons such as failure to comply with performance security (Clause 4.2), failure to correct issues (Clause 15.1), non-conformance to contract standards (Clauses 7.5 and 7.6), financial instability, or ethical violations by the Contractor.

Is a notice period always required before termination?

A: Generally, a 14-day notice period is required before termination. However, immediate termination is allowed in cases of ethical violations or financial instability.

What happens after the contract is terminated under Clause 15.2?

A: After termination, the Contractor must vacate the site and hand over all relevant documents and materials. The Employer may then complete the project either by themselves or through other contractors.

Common Misunderstandings Associated with Clause 15.2

  1. Termination Without Notice: There’s often a misconception that the Employer can terminate the contract without any notice. However, except in cases of ethical violations or financial instability, a 14-day notice is generally required.
  2. Grounds for Termination: A common misunderstanding is that the Employer can terminate the contract for minor or subjective reasons. In reality, the grounds for termination are specific and typically relate to significant breaches or failures by the Contractor.
  3. Contractor’s Liability Post-Termination: Some may incorrectly assume that the Contractor’s liabilities and obligations end immediately upon termination. However, the Contractor is often required to fulfill certain obligations post-termination, such as vacating the site and handing over documents.
  4. Employer’s Unilateral Rights: It’s sometimes misunderstood that the Employer has unilateral and arbitrary rights to terminate the contract. In fact, the exercise of this clause must be justified and based on the contractual terms agreed upon.
  5. Damages and Compensation: There is often confusion over whether the Employer is entitled to damages or compensation after termination. This depends on the specific terms of the contract and the nature of the breach that led to termination.

Flowcharts

Initiation of Termination Process

The process starts with the initiation of the termination process under Clause 15.2.

Identify Potential Breach

A decision is made to determine if there is a potential breach by the Contractor. If not, the process loops back to monitoring the contract.

Issue Notice to Correct (If Applicable)

If a potential breach is identified, a Notice to Correct is issued under Clause 15.1, if applicable, with a 28-day period for the Contractor to rectify the issue.

Contractor’s Response

A decision is made to assess if the Contractor rectified the issue within 28 days. If yes, the process ends with no termination. If no, an immediate decision is made on contract termination.

Consider Termination

A decision is made on whether the contract should be terminated. If not, it returns to monitoring the Contractor’s performance. If yes, a termination notice is issued immediately.

Issue Termination Notice

The process of issuing a termination notice is initiated.

Immediate Termination Requirement

A decision is made to determine if immediate termination is required, considering cases like ethical violations or financial instability.

Contractor’s Post-Termination Actions:

Depending on the immediacy of the termination:
If immediate termination is required, the Contractor vacates the site and hands over documents immediately.
If not, the Contractor is given a 14-day notice to vacate and hand over documents.

Employer’s Post-Termination Actions

The Employer manages the completion of the project, either immediately or after the 14-day period, depending on the termination urgency.

Handle Financial and Legal Matters

Financial and legal matters are resolved, including settling any outstanding payments or claims.

Review and Learning

The process ends with a review and learning from the termination process.

End of Process

The termination process concludes.
Clause 15.2 Termination by Employer

Detailed Explanation of the Flowchart with Durations:

  1. Start of the Process: The process begins when a trigger for Clause 15.2 is identified.
  2. Identification of Specific Breaches: The Employer identifies the specific breach, such as non-compliance with performance security, failure to correct issues, non-proceeding with works, or ignoring rejection/remedial work notices.
  3. Decision Points:
    • Decision to Terminate Contract: The Employer decides whether to terminate the contract based on the identified breach.
  4. Employer Terminates Contract:
    • If the decision is to terminate, a 14-day notice is given to the Contractor.
    • The Contractor then leaves the site and delivers all relevant documents.
  5. Continuation of Contract:
    • If the decision is not to terminate, the contract continues as per the agreed terms.
  6. Employer Completes Works: The Employer may proceed to complete the Works, either independently or through other entities.
  7. Release of Contractor’s Equipment: The Contractor’s equipment and temporary works are released as required, subject to the settlement of any outstanding payments.
  8. End of Process: The process concludes once all actions following the decision are completed.

Clause 15.2 Termination by Employer

Clause 15.2 Termination by Employer

Clause 15.2 Termination by Employer

Detailed Explanation of the Sequence Diagram:

  1. Identification of Breach: The process begins with the Employer identifying a breach of contract by the Contractor. This could be due to various reasons outlined in Clause 15.2, such as non-compliance with performance security or failure to proceed with the works.
  2. Contractor’s Response: Upon notification, the Contractor either acknowledges or disputes the breach. This step is crucial as it can influence the Employer’s subsequent decision.
  3. Employer’s Decision: The Employer internally deliberates whether to terminate the contract based on the breach and the Contractor’s response.
  4. Issuing Notice of Termination: If the decision is to terminate, the Employer issues a 14-day notice to the Contractor, formally initiating the termination process.
  5. Handover of Documents and Goods: The Contractor is required to hand over all relevant documents and goods to the Engineer. This step is vital for ensuring that all necessary information and materials are transferred for the completion of the works.
  6. Confirmation of Handover: The Engineer confirms the receipt and completion of the handover to the Employer. This confirmation is essential for the Employer to proceed with the next steps.
  7. Release of Contractor’s Equipment: The Employer then releases the Contractor’s equipment, allowing the Contractor to arrange for their removal.
  8. Removal of Equipment: The Contractor arranges for the removal of their equipment from the site. This step marks the physical exit of the Contractor from the project.
  9. Completion of the Works: Finally, the Employer takes over and completes the works, either independently or through other entities.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top
Verified by MonsterInsights