Toggleđ§ FIDIC Clause 4.15 â Access Route đŁď¸
Why does 4.15 Access Route even exist?
Picture your project as a bustling construction âcityâ and the public roads as its only lifelines. If those arteries clog up or crack under your convoys, everyoneâfrom the Employer to the local mayorâfeels the pain.
4.15 is FIDICâs way of saying: âContractor, youâre the one driving the heavy trucks, so you own the road-riskâunless something outside your control yanks the road away.â
Picture your project as a bustling construction âcityâ and the public roads as its only lifelines. If those arteries clog up or crack under your convoys, everyoneâfrom the Employer to the local mayorâfeels the pain.
4.15 is FIDICâs way of saying: âContractor, youâre the one driving the heavy trucks, so you own the road-riskâunless something outside your control yanks the road away.â
đ Key Risks Shifted to the Contractor
You must be âdeemed satisfiedâ that every bridge, bend, and border checkpoint can handle your equipmentâno matter how massive. đ
đĄď¸ Duty of Care & Repair
Take all necessary measures (2017) vs. just âreasonable effortsâ (1999) to prevent and repair any damage your works cause. That means fixing potholes, maintaining curbs, and following every authorityâs safety demand. đ§
đ¸ Youâre Financially Liable
If your convoy causes third-party damage (like vibrations cracking a neighborâs window), the claimâs on your walletânot the Employerâs.
â No Guarantees, No Excuses
The Employer doesnât guarantee any road will stay open or suitable. If you find a bridge is too weak after winning the contract, thatâs a lesson in pre-tender homeworkânot a Variation order.
đ 2017: Relief for Post-Base-Date Surprises
If new road restrictions hit after the Base Date (e.g., a sudden axle-load limit), you can now trigger Clause 20.2 for time/moneyâbut only if itâs after the Base Date and not your fault. Think of it as âdetour insurance.â
In one breath?
4.15 channels all route-related planning, prevention and pay-out responsibilities to the Contractor while shielding the Employer from third-party blowback. The 2017 update just tightens things and hands you a slim escape hatch for unforeseen, post-award route disruptions.
4.15 channels all route-related planning, prevention and pay-out responsibilities to the Contractor while shielding the Employer from third-party blowback. The 2017 update just tightens things and hands you a slim escape hatch for unforeseen, post-award route disruptions.
đĄ Quick Mental Checklist
- Map & survey every kilometre before bidding.
- Budget for haul-route upkeep and emergency repairs.
- Secure all permits, police escorts, and waivers early.
- Monitor local authority noticesâconditions change fast!
- Notify the Engineer immediately if a new restriction pops up (or youâll miss your claim window).
- Treat 4.15 as your logistics âblack boxâârecord every effort to keep wheels turning.
đ
Interested in more FIDIC know-how? Check out these related articles:
Related reading to supercharge your understanding:
Citation: FIDIC Yellow Book, Clause 4.15 â Access Route
đ Side-by-Side Breakdown: FIDIC 4.15 Access Route đđ
đ 1999 Edition (Key Points)
- Contractor âdeemed satisfiedâ as to suitability & availability of access routes.
- Reasonable efforts required to prevent any road/bridge from being damaged.
- Contractor must maintain routes, provide signs/permissions.
- Employer not liable for third-party claims.
- No guarantee of route suitabilityâContractor bears all costs if routes arenât suitable.
đ 2017 Edition (Key Points)
- All necessary measures (not just reasonable efforts) to prevent road/bridge damage; vehicles must meet legal load/width limits.
- Same four obligations, plus explicit duty to repair any damage caused.
- Clearer disclaimer: Employer does not guarantee suitability of routes.
-
New right: Contractor may claim EOT/Cost if a route becomes unavailable
after the Base Date due to Employer or third-party changes.
Citation: FIDIC Yellow Book, Clause 4.15 â Access Route (1999 & 2017 Editions)
Want to explore related topics?
Letâs Compare: FIDIC Clause 4.15 Before ⪠and After âŠ
â
1999 Edition: Softer Boundaries
âThe Contractor shall be responsible for any maintenance required for his use of access routes. The Contractor shall provide signs or other necessary means to prevent damage to any road or bridge.â
The focus? Reasonable effortsâmonitoring road wear, coordinating with authorities, scheduling deliveries to avoid public disruption. But if access routes suddenly became unavailable (think: bridge collapses, emergency road closures, sudden truck bans), there was no explicit right to time extensions or compensation.
Contractors had to argue their case under general law or unforeseeable event clausesâoften ending in negotiation or even dispute.
The focus? Reasonable effortsâmonitoring road wear, coordinating with authorities, scheduling deliveries to avoid public disruption. But if access routes suddenly became unavailable (think: bridge collapses, emergency road closures, sudden truck bans), there was no explicit right to time extensions or compensation.
Contractors had to argue their case under general law or unforeseeable event clausesâoften ending in negotiation or even dispute.
đ 2017 Edition: Raised Standards & Safety Net
âThe Contractor shall be deemed to have been satisfied, at the Base Date, as to the suitability and availability of access routes⌠The Contractor shall take all necessary measures to protect roads and bridges and to prevent interference with the use of access routes by the public.â
Now, âall necessary measuresâ replaces âreasonable effortsââraising the bar. Contractors must actively protect infrastructure, secure permissions, engage authorities, and implement traffic/route safety plans.
These obligations are hardwired into the contract: slack off, and there may be financial consequences or delay penalties.
Now, âall necessary measuresâ replaces âreasonable effortsââraising the bar. Contractors must actively protect infrastructure, secure permissions, engage authorities, and implement traffic/route safety plans.
These obligations are hardwired into the contract: slack off, and there may be financial consequences or delay penalties.
â
2017 Game-Changer:
If access routes become unsuitable/unavailable after the Base Date due to Employer action/inaction or Exceptional Event, the Contractor now has a clear right to time and/or cost relief.
This brings predictability and fairnessâso a bridge closure, flood, or sudden ban doesnât just cause headaches; it triggers structured remedies, reducing disputes and keeping the project on track.
If access routes become unsuitable/unavailable after the Base Date due to Employer action/inaction or Exceptional Event, the Contractor now has a clear right to time and/or cost relief.
This brings predictability and fairnessâso a bridge closure, flood, or sudden ban doesnât just cause headaches; it triggers structured remedies, reducing disputes and keeping the project on track.
Citation: FIDIC Yellow Book, Clause 4.15 â Access Route (1999 & 2017)
Clause 4.15, Line by Line â In Plain English
đŁď¸âThe Contractor is deemed to have been satisfied with the suitability and availability of access routes at the Base Date.â
Translation: Before you bid, youâre expected to check if the roads exist and are fit for your needsâweight limits, weather, legal restrictions, all of it. If you miss a problem at tender, you canât complain later. Do your homework!
â ď¸âThe Contractor shall take all necessary measures to protect roads and bridges⌠and to prevent interference with the use of access routes by the public.â
This means you must keep surfaces safe from your works and make sure you donât block local traffic. Be a good neighbor!
đŚâThe Contractor shall obtain any permits or licenses required⌠and provide any signs or other measures required by authorities.â
All paperwork is your jobâpermits, road notices, even special traffic signs. If you need permission to move a giant crane at midnight, sort it out before you roll.
- If you damage the road, you pay to fix it.
- If the route becomes unavailable after the Base Date because of government restriction, flood, or Employer action, you may be entitled to:
- Extension of time (EOT)
- Compensation for extra cost
But only if you promptly follow Clause 20.2 and submit a proper claim.
How Has the Wording Changed?
1999
âThe Contractor shall be responsible for any maintenance required due to its use, and shall provide all necessary measures to protect roads and bridges.â
2017
âThe Contractor shall take all necessary measures to protect roads and bridges, and shall be entitled to EOT and/or Cost if the suitability changes after the Base Date due to Employer action or an Exceptional Event.â
Related articles for more insights:
Citation: FIDIC Yellow Book, Clause 4.15 â Access Route
How Clause 4.15 Connects with Other Key Clauses
đ§4.15
Access Route
âś
Access Route
Defines what youâre responsible forâsurveying, protecting, and using access routes safely and legally.
đ
4.16
Transport of Goods
âś
Transport of Goods
Lays out how you handle moving equipment/materials: notify the Engineer, plan logistics, and follow safety protocols.
4.15 sets the roads, 4.16 sets the rules.
4.15 sets the roads, 4.16 sets the rules.
đ°ď¸
1.1.4
Base Date
âś
Base Date
Establishes your reference point (28 days pre-tender deadline) for whatâs foreseeable. If the route was okay at the Base Date, and changes later, 4.15(2017) may help you claim.
đ
20.2
Claims
Claims
If things go wrong (e.g., sudden road closure), this clause tells you how to claim time/cost, including strict timelines and procedures.
In Short:
4.15 tells you what youâre responsible for, 4.16 guides how you execute it, 1.1.4 sets the fairness benchmark, and 20.2 gives you your backup plan when the unexpected happens.
4.15 tells you what youâre responsible for, 4.16 guides how you execute it, 1.1.4 sets the fairness benchmark, and 20.2 gives you your backup plan when the unexpected happens.
These clauses form a legal and logistical safety netâthink of 4.15 as the mission, 4.16 as the tactics, 1.1.4 as the starting line, and 20.2 as your emergency backup plan.
Citation: FIDIC Yellow Book, Clauses 4.15, 4.16, 1.1.4 & 20.2
Common Pitfalls & Practical Fixes đ§ąâď¸đ§ž
-
đ§ą Problem: Bridge collapses or is downgraded in load capacityFix: Document the condition of all access routes at the tender stage. Take photos, video logs, or commission engineering surveysâespecially for high-risk bridges or culverts. These records can protect you in claims and help allocate risk fairly if things change after contract award.
-
âď¸ Problem: Authorities revoke access permits mid-wayFix: Build buffer time into your programme and flag access risks early using Clause 8.4 (2017). This means:
- Incorporate contingency periods for possible detours.
- Communicate proactively with local authorities to get advance notice of policy changes.
- Periodically reassess access risks during the project to spot problems early.
- Notify the Engineer promptlyâthis can help your claim under Clause 20.
-
đ§ž Problem: Vague contract documents about âwhich access routes are intendedâFix: Clearly list and map all intended access routes in the Employerâs Requirements or Particular Conditions.
- Mark every major/minor road, bridge, culvert, and seasonal route.
- Note all restrictions, such as weight limits or authority controls.
- Review with both parties at award stage and clarify whoâs responsible for permits, signage, and maintenance.
Want to dig deeper?
Citation: FIDIC Yellow Book, Clause 4.15 â Access Route
Best Practices & Suggestions: Making Clause 4.15 Stronger đĄď¸đ
đDefine âSuitabilityâ Clearly
Spell out whether suitability covers: structural strength, weather-resistance, weight/size limits, legal access, right-of-way disputes, or just basic existence. Set the bar in the Contract Data or Particular Conditions to reduce ambiguity and arguments later.
đşď¸Include a Route Access Plan
Map both primary and alternative access routes (with GPS points). Highlight risky segments, seasonal roads, and pinch points. Add traffic flow/congestion data to help everyone plan logistics.
đRequire Pre-Construction Inspection Reports
Treat roads like site assetsâinspect them before works begin. Include photos, load ratings, and sign-off from local authorities. This sets a fair baseline for future claims or repairs.
đTie Maintenance to the Programme
Schedule access route inspections and maintenance in your project plan. Allocate time for joint walk-downs and set clear responsibilities for roadwork, signage, or local authority coordination.
Quick Checklist for Future-Proofing Your Contract:
- Explicitly define âsuitabilityâ in contract documents.
- Attach a detailed access route map, with backup routes and notes on limitations.
- Document route condition and authority sign-off before starting work.
- Link route monitoring/repairs to your construction programme.
Want more practical FIDIC advice?
Citation: FIDIC Yellow Book, Clause 4.15 â Access Route
đď¸Visual Workflow: Sequence Diagram for Clause 4.15
đ View Full Sequence Diagram (opens in new tab)

Tip: Open the full-size image for a detailed view or to download for reference in your next project briefing!
đşď¸Step-by-Step: Clause 4.15 Flow Chart
đ View Full Flow Chart (opens in new tab)

Tip: Click the link above for the full-size chart, perfect for team training or claims workshops!
đ Sample Letters for Clause 4.15 (FIDIC 2017)
References: Clause 4.15, Clause 20.2
[Contractorâs Letterhead] To: The Engineer Date: [Insert Date] Subject: Notice of Unsuitability of Access Route and Request for Relief â Clause 4.15 / 20.2 Dear [Engineerâs Name], Pursuant to Sub-Clause 4.15 [Access Route] and Sub-Clause 20.2 [Claims for Payment and/or EOT] of the Contract, we hereby notify you of a significant change in the suitability of the previously used access route [insert description, e.g., Main Service Road â Section B]. On [insert date], we were informed by [insert authority name or evidence] that the route has been closed to vehicles exceeding [insert specification], owing to [e.g., emergency bridge repairs/flooding/local restrictions]. This change has occurred after the Base Date and was unforeseeable at the time of tender. As a result, we are now required to use a detour that increases transport distances by [X] km, impacts delivery schedules, and incurs additional costs related to fuel, labor hours, and traffic permit requirements. We respectfully request that this letter serve as our Notice of Claim under Sub-Clause 20.2.1. A detailed assessment of the impact, including delay analysis and cost substantiation, will be submitted within the timeframe set out under Sub-Clause 20.2.4. We seek your acknowledgment of this Notice and request consultation in accordance with Sub-Clause 3.7.1 [Agreement or Determination]. Yours faithfully, [Name] [Title] [Contractorâs Company Name]
Adapt for the 1999 edition by removing âBase Dateâ and Clause 20.2 references.
Reference: Clause 4.15
[Contractorâs Letterhead] To: The Engineer Date: [Insert Date] Subject: Notification of Intended Access Routes â Clause 4.15 Compliance Dear [Engineerâs Name], In accordance with Clause 4.15 [Access Route], we are submitting our intended access plan for transporting equipment, personnel, and materials to the Site. The primary routes identified for use are as follows: Route A: [Insert road name and description] Route B (Alternative): [Insert road name and description] We confirm that these routes were reviewed and deemed suitable and available as of the Base Date. Route inspections were conducted on [insert dates], and we have initiated the necessary applications for permits and signage with the relevant local authorities. We intend to commence bulk transport along Route A beginning [insert date], and will comply with all requirements concerning road protection, load limits, and public safety as stated in Clause 4.15. We kindly request your acknowledgment of receipt of this notification and advise whether any further approvals or coordination measures are required. Yours sincerely, [Name] [Title] [Contractorâs Company Name]
Use this as a proactive compliance and communication tool with the Engineer/Employer.