Site icon Navigating Knowledge Across Domains

Commencement of Works: NEC3 vs NEC4 (Clause 30.1)

Commencement of Works

Commencement of Works

Commencement of Works — Deep-Dive on Clause 30.1 (NEC3 vs NEC4) 🚧


1️⃣ Purpose of Clause 30.1 — what is it really doing?

Think of Clause 30.1 as the “site gatekeeper.” It sets two non-negotiables:

  1. No physical work on the Site until the first access date.
  2. Do the works so that Completion lands on or before the Completion Date.
    This is true in both NEC3 and NEC4 (the wording is almost identical).

Why does this matter?

A quick history note (NEC3 ➜ NEC4): the rule itself didn’t change. NEC4 cleans up language (“Employer” ➜ “Client”, “Works Information” ➜ “Scope”), and it tightens some surrounding processes (e.g., the PM’s follow-on instruction when stopping work under 34.1), but your commencement trigger—first access date—stays the same.

Bonus timing anchors you’ll live by: the PM certifies Completion within one week of the date of Completion (NEC3 & NEC4). That cadence matters for end-game milestones, but it also frames how disciplined the contract is with time events.


2️⃣ Breakdown of Clause 30.1 and its closest “wingmen” (31, 32, 33, 34, 60)

Let’s map the commencement ecosystem. Clause 30.1 sits at the centre, surrounded by five clauses that make it work in practice.

A) The commencement gate — Clause 30.1

B) The control tower — Clause 31.2 (The Programme)

Your programme must show the starting date, access dates, Key Dates, Completion Date, planned Completion, logical sequence, and interfaces (Client/Others). It must also show when you’ll need later-than-access-date access, acceptances, Client-provided items, and information from Others. That is how you operationalise commencement. (NEC3 & NEC4.)

C) Access obligation — Clause 33.1

The Employer/Client must allow access to each part of the Site on or before the later of (i) its access date and (ii) the date for access shown on the Accepted Programme. That “later of” is subtle and important. (NEC3 & NEC4.)

D) Stop/Not to start — Clause 34.1

The PM can instruct you to stop or not to start any work. Under NEC4 the PM subsequently instructs to re-start/start or to remove the work from the Scope—this extra follow-on instruction is clearer than NEC3’s simpler “may later instruct to restart.” (NEC4 & NEC3.)

E) Late access is a compensation eventClause 60.1(2)

If the Employer/Client does not allow access by the later of the access date and the date shown on the Accepted Programme, it’s a CE—opening time and money relief routes. (NEC3 & NEC4.)

And yes—CE process mechanics (notify, quote, assess, implement) and time modelling (delay = delta to planned Completion on the Accepted Programme) are explicitly set out in clauses 61–65 and 63.


3️⃣ Key interpretations & practical implications (with the “why” behind NEC4 tweaks)

“On the Site” means… only on-Site work is barred pre-access

30.1 restricts physical work on the Site pre-access; off-site design, procurement, fabrication can proceed to protect the Completion Date—just make sure the programme shows it, and that any pre-start acceptances are timed. (See the programme content rules.)

The sneaky “later of” in 33.1

Access is compliant if given by the later of the access date and the Accepted Programme date. Translation: if you’ve pencilled in earlier access on your programme than the Contract Data access date, a slip to the Contract Data date alone is not automatically a CE. Keep your time risk allowances and float honest.

Late access? Use the CE route fast

If access misses even the later of the two dates, notify a 60.1(2) CE, keep contemporaneous records, and update the Accepted Programme to show the delay’s effect on planned Completion. That is the yardstick for time relief under 63.5 (NEC4) / 63.3 (NEC3).

PM’s “do not start” instruction under 34.1

If the PM instructs “not to start,” comply—but push for clarity on restart conditions. NEC4 added a crisper obligation on the PM to later instruct restart or removal from Scope, which reduces the limbo of unresolved stoppages. If a stop/not-start drifts past thirteen weeks with no resolution, it even feeds into termination triggers (both editions, 91.6).

NEC3 ➜ NEC4 “why the polish?”


4️⃣ Cross-referencing that really matters (how commencement interacts)


5️⃣ “What-If” Scenarios 🧩 (walkthroughs you can copy-paste into your playbook)

Scenario A — Partial access only (Area A open, Area B closed)

Scenario B — PM says “do not start” even though access is fine

Scenario C — Off-site fabrication before access dates

Scenario D — You planned earlier access than Contract Data


6️⃣ Suggestions to sharpen clarity (editions-agnostic, but NEC4 pairs nicely)


7️⃣ Final takeaways (and a few prompts to sanity-check your strategy) ✅

Quick interpretative questions to ask yourself 🤔


Exit mobile version