Site icon Navigating Knowledge Across Domains

Detailed discussion on General Provisions Clause 1.1.2 Parties and Persons

Deep Dive into FIDIC Yellow Book 1999: Clauses 1.1.2.1 to 1.1.2.9 #fidic #projectmanagement

Clause 1.1.2.1: “Party”

Fundamental Aspects:

Detailed Explanation:

The term “Party” is a foundational element in FIDIC contracts, serving as a general term to refer to either the Employer or the Contractor. When used in plural as “Parties,” it indicates a collective reference to both these entities. The use of this term simplifies contract language and ensures clarity when obligations or rights apply to one or both parties.

Key Takeaways:


Clause 1.1.2.2: “Employer”

Fundamental Aspects:

Detailed Explanation:

The “Employer” is essentially the party that commissions the work and enters into the contract with the Contractor. This entity is named in the Contract Data section and has numerous responsibilities, including but not limited to providing site access, facilitating payments, and disseminating necessary information.

Key Takeaways:


Clause 1.1.2.3: “Contractor”

Fundamental Aspects:

Detailed Explanation:

The “Contractor” is the party responsible for carrying out the actual construction works as per the contract. Like the Employer, the Contractor is also named in the Contract Data and holds an array of obligations. These range from executing the work to providing essential documents and ensuring legal compliance.

Key Takeaways:

Clause 1.1.2.4: “Engineer”

Fundamental Aspects:

Detailed Explanation:

The “Engineer” in a FIDIC contract is a multi-faceted role, essentially serving as the Employer’s representative for the project. This person is appointed by the Employer and is responsible for a wide range of duties including supervising the Works, administering the Contract, and certifying payments. The Engineer is a crucial intermediary who also has the authority to issue instructions to the Contractor and make decisions on claims and disputes.

In the FIDIC Red Book, the Engineer has a more extensive role, while in the Yellow and Silver Books, the Contractor assumes more responsibilities, making the Engineer’s role comparatively limited but still crucial.

The Engineer must navigate a complex landscape of duties and responsibilities, as they have an obligation to act neutrally between the Parties while also serving the Employer. This complexity can potentially lead to conflicts of interest, especially if the Engineer is an employee of the Employer.

Key Takeaways:

Clause 1.1.2.5: “Contractor’s Representative”

Fundamental Aspects:

Detailed Explanation:

The “Contractor’s Representative” is a pivotal role within the framework of a FIDIC contract. This individual is the Contractor’s main liaison with the Employer, the Engineer, and other stakeholders. Appointed by the Contractor, this representative manages the day-to-day operations of the project and ensures that all works are performed in line with contractual obligations.

Typically, this person is a senior member of the Contractor’s team with significant experience in the project’s scope. The role is further elaborated in Clause 4.3, which emphasizes that the Contractor’s Representative must be fluent in the contract’s defined language for communications and should be based on-site.

From a legal standpoint, this individual also holds the authority to make decisions and bind the Contractor in matters relating to the contract. This makes the selection of the Contractor’s Representative a strategic decision for the Contractor.

Key Takeaways:

Clause 1.1.2.7: “Contractor’s Personnel”

Fundamental Aspects:

Detailed Explanation:

The term “Contractor’s Personnel” refers to a collective group that includes the Contractor’s Representative and all individuals engaged by the Contractor on the project site. This group is responsible for a myriad of tasks, ranging from planning and arranging to directing and managing the execution of the Works.

These personnel are expected to have sufficient expertise in the domain of the project, as well as fluency in the language specified for communications in the contract. They also have a duty to cooperate with the Employer’s Personnel and any other contractors present on site, including sharing of resources like equipment or temporary works when necessary.

Clause 1.1.2.7 also emphasizes the responsibility of the Contractor’s Personnel to maintain site security, manage waste, and keep the work areas free from unnecessary obstructions. They are the backbone of the project, ensuring not just the technical execution but also the efficient and safe management of the site.

Key Takeaways:

Expanded Explanation of Clause 1.1.2.8: “Subcontractor”

Broad Definition:

The term “Subcontractor” in FIDIC contracts is designed to be broad and inclusive, covering not just those named in the Contract but also those appointed later. It even extends to suppliers of Materials and Plant. This broad scope is designed to ensure that all parties contributing to the Works are included under this term.

Strict Contractor Liability:

Sub-Clause 4.4 is particularly important as it sets the legal framework for the Contractor’s relationship with Subcontractors. The Contractor is held strictly liable for any acts or defaults by the Subcontractor as if they were the Contractor’s own. This is a significant point because it affects the Contractor’s ability to make claims for extensions of time or for force majeure, based on the acts or omissions of its Subcontractors.

Administrative Simplification:

FIDIC offers some administrative relief by stating that the Contractor is generally not required to obtain consent for subcontractors who are solely supplying Materials or those already named in the Contract. This can reduce the administrative burden, especially if a list of pre-approved Subcontractors is included in the Contract.

Contract Administrator’s Role:

The role of the contract administrator is also crucial here. Unless otherwise stated in the Particular Conditions, the Contractor needs to obtain the contract administrator’s consent for other proposed Subcontractors. This consent should not be unreasonably withheld or delayed, as stated in Sub-Clause 1.3.

MDB Form:

The MDB version includes further stipulations. For instance, it obliges the Contractor to ensure that confidentiality requirements are equally applied to each Subcontractor. It also provides for the local contractors from the Country to have fair and reasonable opportunities to be appointed as Subcontractors.

Assignment of Subcontract:

Sub-Clause 4.4(d) in the Red and MDB Books includes a provision allowing the Employer to require the subcontract to be assigned to him under specific conditions, further complicating the Contractor-Subcontractor relationship.

Clause 1.1.2.9: “DAB” (Dispute Adjudication Board)

Fundamental Aspects:

Detailed Explanation:

The Dispute Adjudication Board (DAB) serves as a contractual mechanism for resolving disputes between the parties involved in the contract. Unlike a Dispute Review Board (DRB), the DAB has the authority to issue decisions that are temporarily binding. This means that these decisions must be adhered to until they are either confirmed or overturned by a subsequent arbitration or legal process.

Contractual vs. Statutory Adjudication:

It’s crucial to differentiate between contractual and statutory adjudication. In the FIDIC context, the DAB operates under contractual adjudication, which is defined by the terms agreed upon in the contract. On the other hand, statutory adjudication is a legal process imposed by specific jurisdictional laws, independent of the contract’s terms. In contractual adjudication, the decisions are temporarily binding, while in statutory adjudication, the decisions are often binding and enforceable by law unless overturned by a court.

Key Provisions in Sub-Clauses:

Key Takeaways:

Exit mobile version