Site icon Navigating Knowledge Across Domains

Interpretation of Clause 6.10 Records of Contractor’s Personnel and Equipment

Clause 6.10

Clause 6.10

🔍 1️⃣ Purpose of Clause 6.10

The purpose of Clause 6.10 is to ensure that the Contractor keeps detailed and regular records of personnel and equipment deployed on the Site. These records serve several purposes:

In the 2017 Edition, the clause was expanded significantly to integrate with progress reporting requirements and enhance accountability.


🧩 2️⃣ Breakdown of Clause 6.10

📘 1999 Edition – Clause 6.10: Records of Contractor’s Personnel and Equipment

“The Contractor shall submit, to the Engineer, details showing the number of each class of Contractor’s Personnel and of each type of Contractor’s Equipment on the Site. Details shall be submitted each calendar month, in a form approved by the Engineer, until the Contractor has completed all work which is known to be outstanding at the completion date stated in the Taking-Over Certificate for the Works.”

Key Features:


📙 2017 Edition – Clause 6.10: Contractor’s Records

“Unless otherwise proposed by the Contractor and agreed by the Engineer, in each progress report under Sub-Clause 4.20 [Progress Reports], the Contractor shall include records of:

  • occupations and actual working hours of each class of Contractor’s Personnel;
  • the type and actual working hours of each of the Contractor’s Equipment;
  • the types of Temporary Works used;
  • the types of Plant installed in the Permanent Works; and
  • the quantities and types of Materials used

for each work activity shown in the Programme, at each work location and for each day of work.”

Key Features:


📌 3️⃣ Key Interpretations and Implications

✅ Benefits:

🚨 Risks if poorly implemented:


🔗 4️⃣ Cross-Referencing with Other Clauses

Clause 6.10 doesn’t exist in isolation—it interplays with several critical clauses throughout the contract that influence project administration, claims, and oversight.

📄 Sub-Clause 4.20 [Progress Reports] (2017):

🕵️‍♂️ Sub-Clause 20.2.3 [Contemporary Records] (2017):

📂 Sub-Clause 1.8 [Care and Supply of Documents] (2017):

📑 Clause 13.5 [Daywork]:

📉 Clause 8.4/8.5 [Extension of Time]:

💡 Practical Interaction Summary:


🤔 5️⃣ What-If Scenarios?

What if the Contractor fails to submit these records regularly?

📉 The Engineer may dispute claims for extensions or costs due to lack of evidence. Repeated failures could be considered a breach of contract.

Can the Contractor propose a different reporting method?

✅ Yes, under the 2017 Edition, with the Engineer’s agreement.

If Plant or Equipment is used off-site, should it be recorded?

📍 Only if the off-site work is part of the Programme and contractually relevant. It should then be reflected in the work location data.

What if the Engineer disputes the accuracy of the submitted records?

🧐 The Engineer may request clarifications or additional verification, and if still dissatisfied, might withhold approvals or certifications linked to those records.

Are these records confidential?

🔐 They may contain sensitive information, but since they are contractual deliverables, they must be disclosed to the Engineer and Employer. Confidentiality terms under Clause 1.12 still apply.


✏️ 6️⃣ Suggestions for Clarity and Improvement

Suggestion AreaDetailExample/Tool
🔍 Define “actual working hours”Clarify whether breaks or idle time countDoes 8-hour shift include lunch? Are standby hours logged?
📆 Frequency of ReportingClarify daily vs. summarized weekly reportsDaily log + Weekly Summary Table
🧩 Standardized TemplatesUse Excel or software like Procore/AconexAuto-fill forms tracking crew/equipment per activity
🗂 Link to ProgrammeMap records to WBS codes and activities“WBS 3.2 – 2 Excavators, 12 m³ Concrete”
🔄 Engineer Review CriteriaEstablish review deadlines and discrepancy thresholdsEngineer responds within 7 days; >10% variance flagged
📌 Record Storage ProtocolSpecify format, retention periodDigital + hard copy for 5 years post-handover

🧠 7️⃣ Final Takeaways

Aspect1999 Edition2017 Edition
FrequencyMonthlyDaily (integrated into reports)
ScopePersonnel & Equipment onlyAlso includes Plant, Temporary Works, Materials
FormatEngineer-approvedIncluded in progress reports
UsefulnessModerateHighly integrated with claims and progress

🛠 Practical Tip: Contractors should treat Clause 6.10 as more than an administrative task—it’s a strategic tool for justifying claims and proving performance. Set up automated data collection wherever possible.

✅ Clause 6.10 Compliance Checklist

ItemDescriptionCompleted
1Are daily records of Contractor’s Personnel maintained?
2Are actual working hours for each class of personnel recorded?
3Are daily records of each type of equipment and usage hours submitted?
4Are records of Temporary Works usage included?
5Are Plant installations in Permanent Works tracked?
6Are quantities and types of Materials used recorded by location and activity?
7Are records properly mapped to Programme activities and WBS codes?
8Are reports submitted as part of Sub-Clause 4.20 Progress Reports?
9Are records stored in both electronic and physical formats on-site?
10Has the Engineer approved the format or provided no objection to the reporting method?
11Is there a review process for identifying discrepancies and resolving them timely?
12Are records available for review in case of claims or disputes under Clause 20?

✉️ Sample Letters under Clause 6.10

ScenarioPurposeSample Letter Title
Contractor submits monthly/daily records (1999/2017)Regular submission of records per Clause 6.10“Submission of Contractor’s Personnel and Equipment Records – [Month/Week]”
Contractor proposes alternative reporting methodRequest Engineer’s approval under 2017 Clause 6.10“Proposal for Alternative Format for Contractor’s Records”
Engineer requests clarification on submitted recordsEngineer raises queries on data accuracy“Request for Clarification on Submitted Contractor Records”
Discrepancy found in reported vs. observed dataNotify Contractor of inconsistency“Notice of Discrepancy in Contractor’s Daily Records”
Engineer rejects submitted records formatOfficial rejection with request for resubmission“Engineer’s Rejection of Submitted Records Format”
Contractor requests confirmation of complianceContractor seeks acknowledgment“Request for Confirmation of Record Compliance under Clause 6.10”

📄 Sample Letter 1: Submission of Daily Contractor Records

To: The Engineer
From: [Contractor Name]
Date: [Date]
Subject: Submission of Contractor’s Daily Records for [Date/Week] – Clause 6.10

Dear Sir/Madam,

In compliance with Sub-Clause 6.10 [Contractor’s Records] of the Conditions of Contract (FIDIC Yellow Book 2017), please find enclosed the daily records for [insert date or week], including:

All data is recorded per activity and location as outlined in the Programme and in accordance with Sub-Clause 4.20 [Progress Reports].

Please confirm receipt and advise if any clarification is required.

Yours faithfully,
[Name]
[Position]
For and on behalf of [Contractor’s Name]


📄 Sample Letter 2: Proposal for Alternative Format

To: The Engineer
From: [Contractor Name]
Date: [Date]
Subject: Proposal for Alternative Format for Contractor’s Records – Clause 6.10

Dear Sir/Madam,

We refer to Sub-Clause 6.10 [Contractor’s Records] of the Conditions of Contract. In order to streamline reporting and ensure alignment with our internal digital systems, we propose the attached format for the submission of daily records.

This format includes:

We request your review and approval (or comments) of this format for implementation from [insert proposed date].

Yours sincerely,
[Name]
[Position]
[Contractor’s Name]

Exit mobile version