Site icon Navigating Knowledge Across Domains

Employer’s Termination NEC: NEC3 vs NEC4 + Letters

NEC4

NEC4

Employer’s Termination under NEC3 vs NEC4 (Core 90–93, plus X11 in NEC4)

In NEC4 the Employer is renamed the Client. I’ll say Employer/Client where it helps both editions read smoothly. We’ll walk clause-by-clause—with friendly commentary, practical tips, and “what-if” scenarios—so you can use these rules, not just read them. 🙂


1️⃣ Purpose of 90–93 (and why these clauses exist)

What these clauses do (in one breath):
They govern how the Employer/Client can end the Contractor’s obligation to Provide the Works, when a valid reason exists, who signs what (the Project Manager’s termination certificate), what physically happens on site (the Procedures P1–P4), and how the final money is calculated (the Amounts A1–A4). In both editions, termination starts with notice and a PM certificate under 90.1 and 90.3—the gate you must pass through before any P- or A-steps kick in.

Why it matters to each party:

NEC3 → NEC4: the big policy shift (historical context):

Key takeaway: In NEC4, convenience termination is opt-in (via X11). If you want it, you must select X11—and you accept its payment consequences.


2️⃣ Breakdown of the Clauses (with close-to-text summaries)

A) Clause 90 — The gate and the Table

B) Clause 91 — Reasons for termination (R-codes)

C) Clause 92 — Procedures on termination (P-steps)

D) Clause 93 — Payment on termination (A-amounts)

Termination Table (both editions): maps who terminates + which reasonwhich P-steps & A-amounts. (NEC4 core omits “any reason”; X11 reinstates it, explicitly calling P1+P2 and A1, A2, A4.)


3️⃣ Key interpretations & implications (what experienced teams watch)

Interpretative question: Can we treat convenience termination as implied in NEC4 if the Table is silent?
Short answer: No—you must **opt-in via X11, which explicitly says “a reason not identified in the Termination Table” and hardwires P1+P2/A1+A2+A4.


4️⃣ Cross-referencing that actually helps in practice


5️⃣ What-If Scenarios (with clause cues)

  1. Performance slipping; PM issues a default notice; no fix in four weeks
    • R11–R13/R14–R15 pathway → Employer/Client may terminate. Expect P1 + (P2/P3 as Table dictates) and A1 + A3 (A3 = deduction for forecast extra completion cost). Keep contemporaneous records to justify the A3 deduction.
  2. Client rethinks design; PM “stop” instruction lingers thirteen weeks, reason is Employer default
    • Contractor has R19 termination right. Payment likely includes A1 + A2 + A4 (no A3 deduction). Ensure Equipment removal is captured under A2 and “expectation costs” under A1 are well-evidenced.
  3. Major unforeseen event (Prevention) forecasts > thirteen weeks delay
    • Employer/Client can invoke R21. Consider whether X11 convenience (if selected) produces a commercially “softer” outcome than R21 (e.g., avoiding A3).
  4. Subcontractor pays a bribe; Contractor promptly informs PM and acts to stop it
    • In NEC4, R22 may not bite if the Contractor meets the knowledge/action carve-out. This is why anti-corruption clauses and training matter.
  5. Client loses appetite (no Contractor default)
    • NEC3: Employer could rely on 90.2 “for any reason” right.
    • NEC4: Only possible if X11 is selected; otherwise no convenience basis exists.

6️⃣ Suggestions for clarity & improvement (drafting tips / Z-clauses)


7️⃣ Final takeaways (for your site notes)


A few reflective prompts 💭


Employer’s Termination — Sample Letters (Core 90–93 & NEC4 X11)

Use these templates with the right sequence: Notice → PM Certificate → Procedures 92 → Amounts 93. Clause timers like four weeks and thirteen weeks are signposted.

Edition: Timers: four weeks cure | thirteen weeks stop/prevention Always cite: Clause 90.1 (notice & PM certificate)

Quick Autofill

Tip: Click Set variables to auto-replace placeholders on copy. Placeholders look like {{Employer}}, {{Contractor}}.

1) PM Notice of Contractor Default — start the four weeks cure (Clause 91 R11–R15)

Sender: Project ManagerTo: ContractorCC: Employer/Client
{{Today}} To: {{Contractor}} Cc: {{Employer}} (Employer/Client) From: {{PM}} (Project Manager) Project: {{Project}} | Contract No.: {{ContractNo}} | Contract Date: {{ContractDate}} Subject: Notice of Contractor Default and Requirement to Remedy — Clause 91 (R11–R15) Dear Sirs, Under Clause 90.1 and Clause 91, this is a notice that the following default(s) have occurred: • [Describe the failure precisely: e.g., failure to provide the Performance Bond / substantial failure to comply with the Works Information / serious health & safety breach.] • [Reference evidence: dates, instructions, meetings, photographs, test results, etc.] You are required to stop defaulting and/or correct the default(s) within four weeks of receipt of this notice (Clause 91, R11–R15). Please submit a corrective action plan within seven days, with dates, responsible persons, and verification steps. If the default(s) are not stopped/corrected within four weeks, the Employer/Client may proceed to termination in accordance with Clauses 90–93. This notice is issued under the contract’s communication provisions. All rights are reserved. Yours faithfully, {{PM}} Project Manager
This letter creates the Clause 91 precondition for Employer/Client termination for default.

2) Employer/Client — Notice of Termination for Contractor Default (post-cure) — Clauses 90.1–90.3, 91 R11–R15, 92–93

Sender: Employer/ClientTo: ContractorCC: Project Manager
{{Today}} To: {{Contractor}} Cc: {{PM}} (Project Manager) From: {{Employer}} (Employer/Client) Project: {{Project}} | Contract No.: {{ContractNo}} | Contract Date: {{ContractDate}} Subject: Notice of Termination — Contractor Default not remedied (Clauses 90.1–90.3, 91 R[11–15], 92–93) Dear Sirs, We refer to the Project Manager’s notice of default dated [date] under Clause 91 (R[11–15]). The default(s) were not stopped/corrected within the required four weeks. Accordingly, under Clause 90.1 we hereby give notice to terminate the Contractor’s obligation to Provide the Works for the reason stated (Clause 91, R[11–15]). We request the Project Manager to issue the termination certificate promptly in accordance with Clause 90.1/90.3. Upon certification, the procedures under Clause 92 and the amounts due under Clause 93 applicable to this reason will be implemented. In particular, we will proceed on the basis set out in the Termination Table for R[11–15], which includes the deduction of the forecast additional cost to complete by others (Amount A3). Please secure the Works and cooperate with site handover and records transfer as instructed by the Project Manager. This notice is served under the contract’s communication provisions. All rights and remedies are reserved. Yours faithfully, {{Employer}} Employer/Client

3) Employer/Client — Notice of Termination for Insolvency — Clause 91 (R1–R10) & Clauses 90–93

Sender: Employer/ClientTo: Contractor / Insolvency PractitionerCC: Project Manager
{{Today}} To: {{Contractor}} [and the appointed insolvency office-holder] Cc: {{PM}} (Project Manager) From: {{Employer}} (Employer/Client) Project: {{Project}} | Contract No.: {{ContractNo}} Subject: Notice of Termination — Insolvency Event (Clause 91 R[1–10]; Clauses 90–93) Dear Sirs, An insolvency event under Clause 91 (R[1–10]) has occurred, evidenced by [copy of court/administrator/bankruptcy filing dated …]. Under Clause 90.1 we give notice to terminate the Contractor’s obligation to Provide the Works for this reason and request the Project Manager to issue the termination certificate promptly under Clause 90.1/90.3. Following certification, we will implement the procedures under Clause 92, including securing the site, taking title/possession of Plant and Materials where applicable, and arranging completion by others. The assessment of the amount due will be made under Clause 93 as stated in the Termination Table for this reason. Please arrange an orderly handover of keys, records, design data, and consents. Yours faithfully, {{Employer}} Employer/Client

4) Employer/Client — Notice of Termination for Prevention — Clause 91 (R21) after thirteen weeks

Sender: Employer/ClientTo: ContractorCC: Project Manager
{{Today}} To: {{Contractor}} Cc: {{PM}} (Project Manager) From: {{Employer}} (Employer/Client) Project: {{Project}} | Contract No.: {{ContractNo}} Subject: Notice of Termination — Prevention Event (Clause 91 R21; Clauses 90–93) Dear Sirs, A prevention event has occurred which stops completion or is forecast to delay planned Completion by more than thirteen weeks (Clause 91, R21). Evidence is set out in the attached programme analysis and contemporaneous records. Under Clause 90.1 we give notice to terminate for this reason and request the Project Manager to issue the termination certificate promptly under Clause 90.1/90.3. Upon certification, we will implement Clause 92 procedures and assess the amount due under Clause 93 as per the Termination Table row for R21. Yours faithfully, {{Employer}} Employer/Client

5) NEC4 — Client Termination for Convenience (Option X11) — reason not in the Table

Sender: ClientTo: ContractorCC: Project Manager
{{Today}} To: {{Contractor}} Cc: {{PM}} (Project Manager) From: {{Employer}} (Client) Project: {{Project}} | Contract No.: {{ContractNo}} Subject: Notice of Termination for Convenience — NEC4 Option X11 (Clauses 90–93) Dear Sirs, Option X11 applies. We hereby give notice under Clause 90.1 to terminate the Contractor’s obligation to Provide the Works for a reason not identified in the Termination Table (Option X11). We request the Project Manager to issue the termination certificate promptly pursuant to Clause 90.1/90.3. Following certification, the procedures and amounts specified for Option X11 will apply (typically Procedures P1 + P2 and Amounts A1, A2, A4). Please coordinate demobilisation, removal of Equipment, records transfer, and the delivery/assignment of materials on order. This notice is served under the contract’s communication provisions. All rights are reserved. Yours faithfully, {{Employer}} Client
NEC4 core has no at-will right; it exists only if X11 is selected.

6) NEC3 — Employer Termination “for any reason” — Clause 90.2

Sender: EmployerTo: ContractorCC: Project Manager
{{Today}} To: {{Contractor}} Cc: {{PM}} (Project Manager) From: {{Employer}} (Employer) Project: {{Project}} | Contract No.: {{ContractNo}} Subject: Notice of Termination — Employer’s right “for any reason” (Clause 90.2 & Clauses 92–93) Dear Sirs, Under Clause 90.2 the Employer may terminate for any reason. We hereby give notice under Clause 90.1 to terminate the Contractor’s obligation to Provide the Works on this basis and request the Project Manager to issue the termination certificate promptly in accordance with Clause 90.1/90.3. After certification, we will implement the procedures under Clause 92 and assess the amount due under Clause 93 in accordance with the Termination Table row for Employer termination under Clause 90.2. Please cooperate with demobilisation, site handover, and records transfer as instructed by the Project Manager. Yours faithfully, {{Employer}} Employer

7) Project Manager — Termination Certificate (Clauses 90.1/90.3)

Sender: Project ManagerTo: Both Parties
{{Today}} To: {{Employer}} (Employer/Client) and {{Contractor}} (Contractor) From: {{PM}} (Project Manager) Project: {{Project}} | Contract No.: {{ContractNo}} Subject: Termination Certificate — Clauses 90.1/90.3 I, the Project Manager, certify that a reason for termination under Clause 91 [or Option X11 (NEC4) / Clause 90.2 (NEC3)] applies, namely: [state the reason/R-code]. Accordingly, the procedures under Clause 92 are to be implemented immediately and the amount due will be assessed under Clause 93 in accordance with the applicable row in the Termination Table. Signed: {{PM}} Project Manager
Issue promptly once the reason is established.

8) Project Manager — Instruction to Stop / Not Start (Clause 34) — starts the thirteen weeks clock

Sender: Project ManagerTo: ContractorCC: Employer/Client
{{Today}} To: {{Contractor}} Cc: {{Employer}} (Employer/Client) From: {{PM}} (Project Manager) Project: {{Project}} | Contract No.: {{ContractNo}} Subject: Instruction to Stop / Not Start Work — Clause 34 (administrative register for potential R18–R20) You are instructed to [stop / not start] the following work: [describe scope/areas]. The reason is: [Employer default / Contractor default / other reason]. Record this in the stop/not-start register. This instruction does not of itself terminate the Contract. Unless withdrawn or replaced within thirteen weeks, this instruction may give rise to termination rights under Clause 91 (R18–R20), depending on culpability per the Termination Table. Please secure the Works and mitigate costs. Confirm receipt and your protective measures within 48 hours. Yours faithfully, {{PM}} Project Manager

9) Contractor — Notice of Termination for Non-Payment (Clause 91 R16 after thirteen weeks)

Sender: ContractorTo: Employer/ClientCC: Project Manager
{{Today}} To: {{Employer}} (Employer/Client) Cc: {{PM}} (Project Manager) From: {{Contractor}} (Contractor) Project: {{Project}} | Contract No.: {{ContractNo}} Subject: Notice of Termination for Non-Payment — Clause 91 (R16); Clauses 90–93 We refer to the unpaid certified amount(s) due on [dates], remaining unpaid for more than thirteen weeks. Under Clause 90.1 we give notice to terminate for the reason in Clause 91 (R16) and request the Project Manager to issue the termination certificate promptly under Clause 90.1/90.3. Following certification, the procedures under Clause 92 and the amount due under Clause 93 will be applied as per the Termination Table for this reason. Yours faithfully, {{Contractor}} Contractor

Service & Attachments Aide

  • Serve through the contract’s communication clause (portal/courier/email as specified). Keep proof of service.
  • Annex evidence: default file, programme analysis, stop/not-start register, insolvency evidence, payment schedule, title & equipment registers.
  • On certification, prepare the P-step plan (Clause 92) and the A-amounts working papers (Clause 93).

Employer’s Termination Checklists — Core **90–93** (plus **X11** in NEC4)

Friendly, clause-cued lists you can actually use. Timers like **four weeks** and **thirteen weeks** are highlighted where they drive decisions.

NEC3: Employer may terminate “for any reason” under **90.2** NEC4: Convenience termination only if **X11** is selected

1) Gate & Notice — **90.1–90.3**

No Project Manager certificate = no termination. Use this pre-check to avoid a false start.

Action / QuestionNEC3 cueNEC4 cueNotes / EvidenceDone
Have we served a clear written notice to terminate stating the reason and the R-code (where applicable)? Core **90.1** Core **90.1** Attach notice, service proof, dates.
Has the Project Manager issued a termination certificate promptly, confirming the reason applies? Core **90.1** Core **90.1** File the PM certificate; log date/time.
Are we ready to implement the applicable Procedure (P1–P4) immediately upon certification? See **92** See **92** Identify which P-step your Table row calls.
Have we planned the final assessment under **93** (Amounts A1–A4) and evidence trail for Defined Cost/Forecasts? Core **93** Core **93** Set up a scheduler and cost file index.

2) Reason Validation — **91** (R-codes)

Confirm the right to terminate exists before you lean on procedures and payment rules.

Reason familyNEC3 cueNEC4 cueProof to captureDone
Insolvency events (R1–R10) Core **91** R1–R10 Core **91** R1–R10 Public filings; administrator letters; PM record.
Contractor default & not remedied within **four weeks** (R11–R15) Core **91** R11–R15 Core **91** R11–R15 PM default notice; cure end date; evidence of non-cure.
Employer/Client non-payment for **thirteen weeks** (R16) — Contractor’s right Core **91** R16 Core **91** R16 Payment certificate; due date; bank statements.
Release by law (R17) Core **91** R17 Core **91** R17 Statute/court order; legal memo.
Stop/not-start persists **thirteen weeks** (R18–R20) Core **91** R18–R20 Core **91** R18–R20 Original PM stop instruction; log of reminders; day-count register.
Prevention event delays Completion by > **thirteen weeks** (R21) Core **91** R21 Core **91** R21 Programme impact analysis; contemporaneous records.
Corrupt Act (R22) — NEC4 only (with subcontractor carve-out) n/a Core **91** R22 Investigation notes; prompt PM notice; steps taken to stop.

3) Contractor Default Cure Path — **R11–R15** (the **four weeks** drill)

StepNEC3 cueNEC4 cueProof / How we show itDone
PM issues a default notice describing the failure and the required remedy. Core **91** (R11–R15) Core **91** (R11–R15) Copy of notice; service proof; date time-stamped.
Diary the end of the **four weeks** cure period. TimerTimer Calendar entry; reminder alerts shown.
Collect evidence of non-cure or continued default. EvidenceEvidence Photos, site reports, QA logs, correspondence.
Confirm the Table row → P-steps and A-amounts for an R11–R15 termination. Table → **92**, **93** Table → **92**, **93** Expect A3 deduction (forecast extra completion cost).

4) Non-payment — **R16** (Contractor’s right after **thirteen weeks**)

QuestionNEC3 cueNEC4 cueEvidenceDone
Is the sum certified and overdue by at least **thirteen weeks**? Core **91** R16 Core **91** R16 Certificates; payment schedule; bank statements.
Has the Contractor given a clear termination notice referencing **R16**? NoticeNotice Notice copy; service proof.

5) Stop/Not-start & Prevention — **R18–R21** (the **thirteen weeks** clock)

StepNEC3 cueNEC4 cueRecords to maintainDone
Maintain a stop/not-start instruction register with dates and reasons. Core **91** R18–R20 Core **91** R18–R20 Copy of PM instructions; running day counts.
Assess whether delay to planned Completion will exceed **thirteen weeks** (Prevention, R21). Core **91** R21 Core **91** R21 Programme analysis; risk log; expert note if needed. Table mappingTable mapping Board paper; PM rationale; correspondence trail.

6) NEC4 Option **X11** — Termination for Convenience (if selected)

In NEC4, at-will termination lives in X11. If it’s not selected, there’s no core convenience right.

QuestionNEC3 cueNEC4 cueNotesDone
Is X11 expressly selected in Contract Data? NEC3 had core “any reason” under **90.2** X11 applies Screenshot/scan Contract Data Part one.
Have we confirmed X11’s P-steps and A-amounts (usually P1+P2 and A1, A2, A4)? n/a X11 mapping Note that A3 deduction (extra completion cost) generally doesn’t apply on convenience.
Do Z-clauses cover demobilisation, cancellation of materials on order, IP/design use, and data handover? Z-clausesZ-clauses Attach Z-clause pack; ensure flow-down to subs.

7) Procedures on Termination — **92** (P1–P4)

ProcedureNEC3 cueNEC4 cueWhat to line upDone
P1 — Employer/Client completes the works; uses Plant/Materials with title. Core **92** Core **92** Title register; site access; completion strategy; insurance cover.
P2 — Contractor leaves; removes Equipment/Plant not owned by Employer; assignments. Core **92** Core **92** Vacate plan; security; assignment notices; IP/data handover list.
P3 — Employer/Client may use Contractor’s Equipment to complete (then Contractor removes it). Core **92** Core **92** Insurance, indemnity, operating competence, redelivery condition report.
P4 — Contractor leaves Working Areas and removes Equipment. Core **92** Core **92** Gate pass plan; waste management; H&S close-out.

8) Amounts Due — **93** (A1–A4)

AmountNEC3 cueNEC4 cueWhat to include / expectDone
A1 — Normal assessment items + Defined Cost of Plant/Materials to which Employer/Client has title; reasonable costs incurred in expectation of completing; retention/advance adjustments. Core **93** Core **93** Evidence pack; materials on order; cancellation charges policy.
A2 — Forecast Defined Cost of removing Equipment. Core **93** Core **93** Demobilisation plan; third-party quotations; schedule.
A3 — Deduction for Employer/Client’s forecast additional cost to complete (applies to Contractor default rows). Core **93** Core **93** Market test; like-for-like scope; prudent basis; approval trail.
A4 — Fee % application to defined “excess” as per main option. Core **93** Core **93** Check Option (A–F); align with Contract Data; avoid double counting.

9) Communications & Records — admin that wins disputes

ItemNEC3 cueNEC4 cueWhat good looks likeDone
Service of notices (termination, default, stop, etc.) under the contract’s communication clause. Core commsCore comms Follow form/method; keep courier/portal logs; time stamps.
Programme & day-count registers for **four weeks** and **thirteen weeks** gates. TimersTimers Single source register; reviewed weekly.
Title & equipment registers (enabling P1–P3 smoothly). Core **92**Core **92** Serial numbers; location; condition; insurance position.
Defined Cost evidence index (for A1–A2) and forecasting method memo (for A3). Core **93**Core **93** Folder structure; named owner; version control.

10) Risk Controls & Z-Clauses (optional but smart)

ControlNEC3 cueNEC4 cuePractical implementationDone
Anti-corruption protocol & flow-down (helps with NEC4 R22 carve-out). n/aCore **91** R22 Training; reporting hotline; contract obligations on subs.
Convenience playbook (only if X11): demob schedule; cancellation policy; IP & data handover. NEC3 had **90.2** “any reason”X11 Z-clause pack; template letters; procurement standby plan.
Completion-by-others sourcing & assurance (for P1 and A3 forecasting). Core **92**, **93**Core **92**, **93** Market soundings; framework lots; QA/HS&E vetting.

Tip: Pair these checklists with a one-page flow (Notice → PM Certificate → 92 P-steps → 93 A-amounts). Happy administering! 🎯

Exit mobile version