Site icon Navigating Knowledge Across Domains

Failure to Pass Tests on Completion – FIDIC Clause 9.4 Explained with Examples, Letters & Checklists

Tests on Completion

🧩 1️⃣ Purpose of Clause 9.4


🎯 What is Clause 9.4 all about?

Clause 9.4 in both editions deals with the scenario where the Works (or Section) fail to pass the Tests on Completion, which are the technical and performance benchmarks defined to ensure the Works are ready for Taking-Over.

📌 Objective:

📜 Historical Context & Evolution:

AspectFIDIC 1999FIDIC 2017
ToneCompact and directMore detailed and procedural
FocusBroad discretion to EmployerIntroduces clearer option mechanisms and additional performance-based consequences
Risk AllocationAmbiguity in acceptance despite failureMore structured acceptance vs. performance loss logic

🧩 2️⃣ Deep Dive Breakdown of Clause 9.4: Failure to Pass Tests on Completion


Imagine this: the Works are almost done, the site looks great, the Contractor is ready to hand it over. But then… the Tests on Completion fail. Maybe the plant doesn’t reach the promised output, or an automated system isn’t responding as designed. Either way, this clause now takes center stage.

We’re going to explore how FIDIC 1999 and FIDIC 2017 each handle this awkward moment.


📕 FIDIC 1999 Edition – Clause 9.4 Unpacked


🎯 Context:

The Tests on Completion have already been retested under Sub-Clause 9.3, but things are still not working as intended. The Engineer must now make a call.

✅ What Options Does the Engineer Have?

🔁 (a) Order More Retesting

The Engineer can say:

“Let’s give it another go.”

This might seem generous, but here’s the catch: there’s no limit set in the clause. Theoretically, the Engineer could keep asking for more tests unless the Employer puts a foot down. There’s no time trigger or test cap. That’s risky — and arguably, a bit loose.


(b) Reject the Works or Section

This is the hammer. The clause says:

“If the failure deprives the Employer of substantially the whole benefit of the Works or Section…”

Then the Employer can reject them.

But what’s “substantially the whole benefit”? 🤨 That’s the million-dollar question. FIDIC 1999 doesn’t define this phrase, leaving it open to interpretation — and potential dispute.

Let’s say the project was a solar plant expected to generate 5 MW. If it only delivers 3 MW after multiple fixes, has the Employer lost “substantially the whole benefit”? 🤷

📎 The remedy? This rejection triggers Clause 11.4(c) — which allows the Employer to:

🛑 Bottom line: rejection isn’t just a slap on the wrist — it can lead to full contract termination and major cost consequences.


🧾 (c) Accept the Works – With a Price Reduction

Now here’s where it gets nuanced.

The Employer might say:

“We’ll take the Works, even if they underperform — but we expect a discount.”

In this case:

📌 But — and this is crucial — 1999 doesn’t tell us how to calculate the reduction.

So what happens?

If the reduction isn’t pre-defined in the Contract:

  1. The Employer may demand a reduction, and both parties try to agree.
  2. If they can’t agree, it must be determined under:
    • Clause 2.5 [Employer’s Claims]
    • Clause 3.5 [Determinations]

This could lead to delays, disputes, and even DAAB proceedings — simply because there’s no formula.


📘 FIDIC 2017 Edition – Clause 9.4 Explored


Fast forward to 2017. This version takes the old Clause 9.4 and gives it a full structural makeover — clearer paths, better risk management, and firm timelines.

We’re still in the same situation: Tests on Completion failed again, even after retesting under Sub-Clause 9.3.

Now, the Engineer has four distinct options — laid out like a menu.


🔁 (a) Order More Retesting

Just like in 1999, the Engineer can instruct:

“Try again.”

But in practice, the structure of the 2017 Contract encourages moving on to other options faster — there’s more procedural clarity coming up.


(b) Reject the Whole Works

If the failure:

“…deprives the Employer of substantially the whole benefit of the Works…”

then the Employer can reject the entire Works, triggering Clause 11.4(d).

🛠️ This clause allows the Employer to:

This is a clean kill — no drawn-out process. It’s intended for catastrophic failures.


(c) Reject Just a Section

Here’s a smart addition by FIDIC.

If:

“…the Section cannot be used for its intended purpose(s)…”

then the Employer can reject just that Section — and apply Clause 11.4(c).

The Engineer then treats that Section as an omission, as if it was never included under Clause 13.3.1. This avoids total project derailment when only part of the Works is problematic.


(d) Accept with a Deduction

This is where things get real-world practical.

The Employer can say:

“Okay, we’ll accept the Works, but you owe us a deduction.”

And now — unlike 1999 — we get exact steps:

🕒 If no agreement is reached within 14 days, the Engineer must make a determination under Clause 3.7.

📣 Also — this path doesn’t limit the Employer’s rights. They can accept the Works and still pursue other contractual remedies if needed.


🎯 Recap Comparison: Side-by-Side Snapshot

📌 FeatureFIDIC 1999FIDIC 2017
Retesting✅ Unlimited✅ Same
Rejection – Whole Works✅ Broadly defined✅ Clearly stated in 9.4(b)
Rejection – Section Only❌ Not specified✅ New in 9.4(c)
Acceptance with Deduction✅ But vague on process✅ Clear path: Clause 11.4(b) applies
Reduction Formula❌ Usually undefined✅ Linked to Performance Damages or Value Loss
Engineer’s Role💬 Implied via 3.5🛠️ Structured via 3.7 (with 14-day deadline)
Employer Rights Reserved?❌ Not specified✅ Explicitly preserved

🧠 Final Thoughts on Breakdown

🧠 3️⃣ Key Interpretations and Implications


When the Works fail to pass the Tests on Completion, it can be a make-or-break moment in a project. Clause 9.4 acts as the fork in the road — where everyone needs to decide: do we fix, reject, or accept with consequences?

Let’s break this down into practical interpretations, uncover the risks and obligations behind each option, and explore how things play out differently in the 1999 vs. 2017 editions.


💥 What does “Failure to Pass Tests on Completion” really mean?

It’s not just a missed benchmark — it’s about whether the performance, capacity, or safety of the Works (or a Section) meets what’s specified in the Employer’s Requirements.

Some common real-world examples:

Failing these tests means the Works aren’t ready to be taken over — unless the Employer accepts them anyway, which comes with strings attached.


📘 Interpretations – FIDIC 1999 Style

In the 1999 edition, Clause 9.4 gives the Engineer three powers:

  1. Repeat the tests
  2. Reject the Works or Section
  3. Accept the Works (with a reduction in price)

But here’s where things get interesting — and murky:


🔁 Repetition of Tests: How far is too far?

Can the Engineer keep ordering test after test?

👉 Interpretation:


❌ Rejection Based on “Substantially the Whole Benefit”

This is one of the most debated phrases in FIDIC:

“…if the failure deprives the Employer of substantially the whole benefit…”

🧠 Key questions:

📌 Implication:


✅ Acceptance with Price Reduction — But Based on What?

The 1999 clause allows the Employer to accept the Works with a price cut — but here’s the catch:

📎 Implication:


📘 Interpretations – FIDIC 2017 Style

Now let’s look at how Clause 9.4 evolved in 2017 — and how those same options were reshaped for better clarity and balance.


🔁 Retesting Still Exists — But Less Open-Ended

Engineers still have discretion to repeat tests — but the structure of Clause 9.4 nudges the project toward resolution:

✅ Implication:


❌ Rejection Split into Two Paths: Whole Works vs. Section

This is a brilliant addition in 2017.

Option (b): If the entire Works fail to deliver the benefit — reject the whole thing.

Option (c): If just one Section fails its purpose — reject only that part.

👉 This reflects how modern infrastructure is built — in modular phases, allowing:

📌 Implication:


📉 Acceptance with Deduction — Now Backed by Clause 11.4

Here’s where 2017 shines:

🧠 But what if they can’t agree on how much?

📎 Implication:


📢 Obligations Recap: Who Does What?

RoleResponsibilities
ContractorMust cooperate in further tests, remedial works, and comply with the Engineer’s instructions.
EngineerMakes critical decisions: retest, reject, accept with deductions, and issue fair determinations.
EmployerCan reject or accept with compensation — but must notify requests (e.g., Taking-Over) and document reductions.

🚨 Risk Zones for Each Party

👷 Contractor:

🧑‍💼 Employer:

🧑‍💻 Engineer:


📚 Key FIDIC Concepts in Play

🔗 4️⃣ Cross-Referencing with Other Clauses


🧭 Why Cross-Referencing Matters in Clause 9.4?

Clause 9.4 (Failure to Pass Tests on Completion) might look like it lives in the “Testing and Completion” zone — but in reality, it’s the epicenter of multiple contract consequences. It’s like a trigger switch that sets off a chain reaction across the contract. If you know which clauses it connects to, you can:


🔗 Step-by-Step Clause Interactions


🧪 Clause 9.3 – Retesting: The Entry Point

“If the Works, or a Section, fail to pass the Tests on Completion, Sub-Clause 7.5 [Rejection] shall apply, and the Engineer or the Contractor may require the failed Tests … to be repeated under the same terms and conditions.”

🔍 What’s going on here?

Clause 9.3 is the prerequisite to 9.4. It governs what happens immediately after a failure — i.e., can the Contractor get a second chance?

Key Takeaway:

🧠 Interpretation Tip:


❌ Clause 7.5 – Rejection (Both Editions)

Clause 9.3 makes a quick reference to Clause 7.5, which enables the Engineer to reject work that fails tests.

✔️ In 1999, it’s titled just [Rejection] ✔️ In 2017, it’s [Defects and Rejection], giving more process.

🔁 The rejection mechanism here is early stage — based on test results, not a full clause 9.4 remedy.

🧠 But once retesting fails and the failure is serious, you move from “rejection of work” to “rejection of the Works” — that’s the bridge from Clause 7.5 ➝ Clause 9.4 ➝ Clause 11.4.


🛠️ Clause 11.4 – Failure to Remedy Defects

This is the engine room of remedies — and 9.4 plugs into it like a power cable. Let’s map the exact links:

From Clause 9.4Connects to Clause 11.4
9.4(b) (1999)11.4(c): Employer may terminate, recover payments, dismantling cost
9.4(b) (2017)11.4(d): Same right, but clarified and immediate
9.4(c) (2017)11.4(c): Treats defective Section as an omission
9.4(d) (2017)11.4(b)(i) or (ii): Determines compensation or reduction in price

💡 Practical wisdom: Clause 9.4 is not the final word. It redirects the real consequences to 11.4, where money, claims, and termination live.


📜 Clause 10 – Taking-Over Certificate

Let’s say the Employer decides:

“We’ll accept the Works, even though they didn’t pass the tests.”

This triggers 9.4(c) (1999) or 9.4(d) (2017), which leads to a Taking-Over Certificate under Clause 10.1.

What’s at stake?

📎 Fun fact: If the reduction isn’t agreed or fairly determined, final payment under Clause 14 might get stuck. So Clause 10 actually acts as a hinge between 9.4 and 14.


💰 Clause 14 – Contract Price and Payment

This is the money zone.

When the Employer accepts the Works under 9.4 but wants a reduction, it needs to be reflected in:

If the reduction isn’t agreed? The Engineer must make a fair determination (Clause 3.5 / 3.7), which then flows into the payment calculation.

📌 Note:


⚖️ Clause 3.5 (1999) / Clause 3.7 (2017) – Engineer’s Determination

💥 If the Contractor and Employer disagree on the price reduction (which is often the case), the Engineer is forced to intervene.

In 1999:

In 2017:

📌 In Clause 9.4(d) (2017), this pathway is clearly linked:

“…shall be subject to Sub-Clause 11.4(b)(ii), and if no agreement is made within 14 days, the Engineer shall make a fair determination…”

That’s tight procedural control — designed to prevent endless back-and-forth.


🧾 Clause 20 – Claims for Payment, EOT, or Disagreement

If the Employer:

…then we’re into claims territory.

In 1999:

In 2017:

📣 Big Upgrade:

In 2017, both parties must follow the claim process or risk losing rights.


🛑 Clause 15.2 – Termination for Default (2017 only)

Sometimes, the failure to pass tests isn’t just technical — it’s contract-breaking.

In 2017, Clause 11.4(d) (referenced from 9.4(b)) bypasses Clause 15.2 and allows immediate termination if failure deprives Employer of the “whole benefit.”

This is fast-track exit — not based on notice or cure period, just functional non-performance.

✅ Important nuance: Clause 15.2 is not required — this is a separate “kill switch.”


🎯 Visual Summary Table

🔗 Clause🔄 Interaction with 9.4📚 Applies to
9.3Authorizes retesting before 9.4Both
7.5Enables rejection after failed testBoth
11.4Supplies remedies for each 9.4 pathBoth
10.1 / 10.2Taking-Over triggered if Works acceptedBoth
14.11 / 14.13Reduction must reflect in final paymentBoth
3.5 / 3.7Engineer determines price cut if disputedBoth
20.1 / 20.2Claims/disputes over test failures or deductionsBoth
15.2Termination route in case of fundamental failureMainly 2017

✅ Final Takeaways

Clause 9.4 is the nerve center of post-completion decisions — but its teeth, triggers, and consequences all come from other clauses. You cannot understand 9.4 in isolation.

🔍 Key Reflection:

When interpreting Clause 9.4, always ask:
“What clause gets activated if this road is taken?”

This way, you can predict outcomes, control risk, and prepare your client or team for what lies ahead.

🎭 5️⃣ What-If Scenarios? – Clause 9.4 in Real Life


Let’s play out scenarios where Tests on Completion fail, and see how both the 1999 and 2017 editions respond. These examples will help you grasp the practical implications, spot grey areas, and understand how to manage them.


🧪 Scenario 1: “The Test Failed, But Only Slightly – Can the Employer Still Reject It?”

🧷 Background:

🔍 FIDIC 1999:

💬 Interpretation:

There’s no defined threshold. This could go to the Engineer for determination under Clause 3.5, or even to the DAAB/arbitration if disputed.

🔍 FIDIC 2017:

📌 Risk Tip: Contractors should quantify the value impact of the shortfall — if the remaining capacity still serves the Employer’s needs, rejection may be challenged.


🔁 Scenario 2: “The Employer Accepts the Works Despite the Failure – Now What?”

🧷 Background:

🔍 FIDIC 1999:

💬 Catch:

There’s no fixed timeline for resolution. Contractor cash flow can get stuck.

🔍 FIDIC 2017:

📌 Bonus: The Employer can accept the Works and still pursue other rights (e.g., damages) — this is explicitly protected in 2017.


🧯 Scenario 3: “The Contractor Thinks the Test Failure Was the Employer’s Fault”

🧷 Background:

🔍 FIDIC 1999:

🔍 FIDIC 2017:

📌 Pro Strategy:

Contractors should document all test inputs and dependencies — especially if failure could be due to Employer-side inputs.


🧩 Scenario 4: “The Engineer Keeps Asking for More Tests – Can This Go On Forever?”

🧷 Background:

🔍 FIDIC 1999:

🔍 FIDIC 2017:

📌 Best Practice:

After 2 failed tests, both parties should request the Engineer to formally record the next steps, rather than looping.


🧾 Scenario 5: “The Section Works, but Only for One Purpose – Is It Still a Failure?”

🧷 Background:

🔍 FIDIC 1999:

🔍 FIDIC 2017:

“…if the Section cannot be used for its intended purpose(s)…”

📌 Real Advantage:

Allows phased handover and avoids holding up the entire project due to a non-critical failure in one part.


🚫 Scenario 6: “The Failure is So Bad the Employer Wants to Terminate the Contract”

🧷 Background:

🔍 FIDIC 1999:

🔍 FIDIC 2017:

📌 Key Insight:

Clause 9.4 failure can become a standalone cause for termination, especially in critical infrastructure projects.


🧠 Big Picture Learning from These Scenarios

Situation1999 Edition2017 Edition
Small shortfall in test?Risk of dispute due to vague wordingEngineer’s fair determination required
Employer accepts anyway?Vague process for reductionLinked to Clause 11.4(b), clear paths
Employer at fault for test failure?Claims process not well-structuredStrong 28-day claim window (Clause 20.2)
Endless retesting?No cap, vague discretionPushes Engineer toward decisions faster
Partial functionality of Works?Reject all or accept allReject or omit only the failed Section
Catastrophic failure?Can terminate via 11.4(c)Immediate termination via 11.4(d)

✅ Final Thoughts on What-Ifs

Clause 9.4 is deceptively short — but it can explode into different directions depending on how it’s triggered, how the Engineer acts, and whether the Employer accepts or rejects the Works.

🔧 In 1999: You need to build protections through Particular Conditions and strong Engineer interpretations.

🧠 In 2017: The logic tree is clearer, but you still need to follow procedures, respect deadlines, and document performance shortfalls or Employer-side obstacles.

🛠️ 6️⃣ Suggestions for Clarity and Improvement


🧩 1. Ambiguity: “Substantially the Whole Benefit”

This phrase appears in Clause 9.4(b) (both 1999 and 2017) and is notoriously vague.

🔍 Issue:

🧠 Golden Principle (GP2) says: Particular Conditions must be drafted clearly and unambiguously.

Suggested PC Wording:

“For the purposes of Sub-Clause 9.4(b), a failure shall be deemed to deprive the Employer of ‘substantially the whole benefit’ of the Works if the actual performance deviates by more than 15% from the minimum performance levels stated in the Schedule of Guarantees.”

🎯 Why this helps:


🔁 2. Ambiguity: “Reduction in Contract Price” — But How?

In both 1999 and 2017 versions, the Employer may accept the Works and impose a reduction in price. But…

🔍 Issue:

Golden Principle (GP2) demands: PCs must explicitly describe how they alter or extend GCs, especially when adding financial consequences.

Suggested PC Addition:

“If the Engineer issues a Taking-Over Certificate under Sub-Clause 9.4(c)/(d), the reduction in Contract Price shall be calculated as a percentage of the Schedule of Performance Guarantees shortfall, based on the following:
(i) 1% reduction for each 1% deviation below guaranteed performance,
(ii) up to a maximum reduction of 10% of the Contract Price.”

📌 Bonus Tip: Include this clause in both:

This makes the connection between performance and payment crystal clear — exactly what GP2 and GP3 advocate.


🔄 3. Problem: Retesting Can Be Endless (Loop Risk)

Clause 9.4(a) gives the Engineer the right to order further retesting, but doesn’t limit how many times this can happen.

🔍 Risk:

✅ Suggested PC Enhancement:

“The Engineer shall not order more than two further repetitions of the Tests on Completion under Sub-Clause 9.4(a), unless the Contractor provides, at its own cost, a written plan with modifications or improvements justifying additional testing.”

🎯 Why it works:


🧾 4. No Timeframe for Price Reduction Agreement Before Taking-Over

🔍 Problem in 1999:

Clause 9.4(c) says Taking-Over can occur only after the reduction is paid or determined — but doesn’t set a time limit. This may delay the DNP or project closure.

✅ Suggested Fix:

“If the Parties are unable to agree the price reduction within 14 days, the Engineer shall issue a determination under Clause 3.5. Such determination shall be binding until revised under Clause 20.4 [DAAB] or by arbitration.”

✅ Aligns with:


⚖️ 5. Engineer’s Role Must Remain Independent

Real problem in India (often seen in modified Yellow Books):

The Engineer is asked to “obtain Employer approval” before issuing a determination — this violates GP1!

✅ FIDIC Says:

“It would be a breach of GP1 for a Contract to require the Engineer to seek approval from the Employer before issuing any determination under Sub-Clause 3.7”​1. FIDIC Yellow Book 20…

✅ Suggested PC Clause (to ensure GP1 compliance):

“In carrying out determinations under Sub-Clause 3.7 related to Sub-Clause 9.4, the Engineer shall act independently and is not required to seek or obtain prior approval from the Employer.”

📌 This one’s a Golden Principle must-have.


✍️ Sample Particular Conditions for Indian Projects

If you’re drafting for Indian infrastructure (say NH, MRTS, or thermal power), consider integrating this model PC:


🔹 Sample PC for Sub-Clause 9.4 (2017 Edition)
(Modification to the last paragraph of the Clause)

“In the event of the Employer electing to issue a Taking-Over Certificate under sub-paragraph (d) of this Sub-Clause, the reduction in Contract Price shall be calculated in accordance with the criteria set out in the Schedule of Performance Guarantees.
Where such criteria are not defined, the Engineer shall determine the reduction based on the diminished value to the Employer, provided that the total reduction shall not exceed 10% of the Contract Price.
The Engineer shall make this determination within 14 days after failure to reach agreement, and such determination shall be subject to Sub-Clause 3.7.
The Engineer shall act independently and neutrally, without seeking prior approval of the Employer.”


🎯 Final Takeaways for Section 6

🧱 Area🔧 Problem💡 Suggested Fix
“Substantially the whole benefit”Too vagueDefine in PCs (e.g., 15% performance deviation)
Reduction in Contract PriceNo formulaTie to % shortfall in guarantees
Endless RetestingLoop riskLimit to 2 retests unless justified
Delays in Taking-OverNo agreement deadlineEngineer decides in 14 days
Engineer’s RoleCan be compromisedMake independence explicit in PCs

🎓 7️⃣ Final Takeaways – Clause 9.4 Unlocked


📌 What is Clause 9.4 Really About?

It’s about what happens when the Contractor hands over the Works — but they don’t pass the Tests on Completion. That could mean:

📣 Clause 9.4 is the crossroads between:

And depending on which road is chosen, you unlock a different set of contract remedies.

⚖️ Key Differences: 1999 vs. 2017

🔍 FeatureFIDIC 1999FIDIC 2017
Retesting LimitNot definedNot defined, but structured remedy paths encourage finality
Rejection OptionsWorks or SectionClearly split into Works (9.4(b)) and Section (9.4(c))
Acceptance with DeductionVague price reductionLinked to Clause 11.4(b), with timeline and fallback
Price Reduction MechanismOnly if agreed or determinedStructured: 14-day window, then Engineer must act
Engineer’s DeterminationClause 3.5Clause 3.7 (more procedural clarity)
Finality of Employer’s RightsNot statedExplicitly preserved even after Taking-Over

💬 The Clause in Plain English

Let’s simplify the logic so you can explain it in a meeting:

“If the Works don’t pass their final test, the Engineer can ask for retesting. But if they fail again, the Employer can either:

  • Reject the Works or just the failed part,
  • Or take it over, but reduce the price. If there’s disagreement about the reduction, the Engineer steps in and decides.”

And remember — it’s not just about performance. It’s about value to the Employer and functional usability.


⚠️ Risks to Watch Out For

For the Contractor:

For the Employer:


📚 Key Cross-References to Always Consider

When Clause 9.4 comes into play, you should immediately think of:

🔗 ClauseWhy It Matters
9.3Must fail a retest before 9.4 activates
11.4Remedies triggered (termination, omission, reduction)
10Taking-Over Certificate may be delayed
14Final payment needs to reflect deductions
3.5 / 3.7Engineer determines if no agreement
20.1 / 20.2Disputed deductions must be claimed timely
15.2 (2017)Clause 11.4(d) allows direct termination for total failure

🧰 Pro Tips & Best Practices

✔️ Define reduction formulas in Particular Conditions (e.g., 1% deduction per 1% underperformance)

✔️ Document all retesting attempts (time, data, root cause, Employer’s involvement)

✔️ Train Engineers on making fair, reasoned determinations — no rubber-stamping

✔️ Prepare claims promptly if you think failure is due to Employer-side reasons

✔️ Structure Section testing criteria clearly — especially in EPC contracts with multiple handovers

✔️ Limit retesting cycles to avoid getting stuck in a loop


✍️ Sample One-Liner for Your Report

“Clause 9.4 transforms technical test failure into legal and commercial decision-making — making it one of the most consequential clauses at the handover stage of any EPC contract.”


🎯 Final Reflection

If you remember nothing else, remember this:

📌 Clause 9.4 is not just about passing or failing a test.
It’s about deciding what happens next — with money, responsibility, and risk on the line.


✅ Clause 9.4 Compliance & Action Checklist

🔧 A. Contractor’s Checklist

✅ TaskDescription✔️ Check
1.Confirm if Tests on Completion were performed under agreed conditions.
2.Document failure reasons with technical evidence (incl. inputs from Employer).
3.Request retesting formally under Clause 9.3 if failure is questionable.
4.Cooperate with Engineer’s instructions on retesting or remedial works.
5.If accepted with reduction, verify how deduction is calculated (Clause 11.4).
6.Submit claim under Clause 20.1 (1999) / 20.2 (2017) if failure is not Contractor’s fault.
7.Track and preserve evidence in case of disagreement or potential DAAB referral.

🧑‍💼 B. Employer’s Checklist

✅ TaskDescription✔️ Check
1.Assess whether failure affects “substantially the whole benefit” (or purpose of Section).
2.Decide formally (with reasons): reject, accept, or retest.
3.If accepting Works, propose Contract Price reduction (per PC or Clause 11.4).
4.Ensure Taking-Over Certificate isn’t issued until reduction agreed/determined.
5.If rejecting, follow up with Clause 11.4 actions (termination or omission).
6.Ensure Engineer acts independently in making determinations.
7.Keep written records to justify rejections or deductions in case of claims.

🧑‍🔧 C. Engineer’s Checklist

✅ TaskDescription✔️ Check
1.Confirm that failure occurred after valid testing under Clause 9.3.
2.Limit retesting orders to reasonable cycles (2–3) to avoid open-ended delay.
3.Document all failure results and related instructions in writing.
4.If reduction is proposed but disputed, trigger Clause 3.5 (1999) / 3.7 (2017) process.
5.Issue a fair determination within 14 days (2017) if agreement isn’t reached.
6.Avoid seeking Employer approval for determinations (per GP1).
7.Ensure deduction appears in final payment calculations (Clause 14.13).

✉️ Sample Letters under Clause 9.4 Scenarios


📩 1. Contractor to Engineer – Request for Retesting (Clause 9.3/9.4)

Subject: Request for Retesting under Clause 9.3 following Test on Completion Failure

Date: [Insert Date]
To: The Engineer
From: The Contractor
Contract: [Project Name/Number]

Dear Sir/Madam,

We refer to the outcome of the Tests on Completion conducted on [insert date], where certain parameters did not meet the Employer’s Requirements as specified in the Contract.

Pursuant to Sub-Clause 9.3 [Retesting], and further to Sub-Clause 9.4 [Failure to Pass Tests on Completion], we hereby request that the failed tests and associated related works be retested under the same terms and conditions, following our remedial measures completed on [insert date].

We remain available to coordinate all test arrangements and ensure that proper records are maintained.

Kind regards,
[Name]
[Title]
For and on behalf of the Contractor

📩 2. Engineer to Contractor – Notice of Price Reduction Following Employer’s Acceptance (Clause 9.4(c)/(d))

Subject: Notification of Contract Price Reduction due to Non-Compliance with Tests on Completion

Date: [Insert Date]  
To: The Contractor
From: The Engineer
Contract: [Project Name/Number]

Dear [Contractor’s Name],

Following the Employer’s decision to accept the Works under Sub-Clause 9.4(c)/(d) despite the Works not meeting certain performance parameters, please be informed that the Contract Price shall be reduced accordingly.

As required under Sub-Clause 11.4(b)(ii), and in the absence of Performance Damages, we propose a reduction of [insert amount or %], based on the value reduction determined due to the failure of the Works to meet the guaranteed [insert performance parameter].

Please confirm your agreement within 14 days. Failing agreement, we shall proceed with a determination in accordance with Sub-Clause [3.5 (1999) / 3.7 (2017)].

Yours faithfully,
[Name]
The Engineer

📩 3. Employer to Engineer – Instruction to Reject Works due to Failure (Clause 9.4(b))

Subject: Instruction to Reject Works under Clause 9.4(b) due to Failed Tests

Date: [Insert Date]  
To: The Engineer
From: The Employer
Contract: [Project Name/Number]

Dear [Engineer’s Name],

In view of the Contractor’s repeated failure to pass the Tests on Completion under Sub-Clause 9.3, and based on the latest test results dated [insert date], we hereby instruct you to reject the Works under Sub-Clause 9.4(b), as the failures have deprived the Employer of substantially the whole benefit of the Works.

Please proceed with issuing the relevant notices and initiating the remedies available under Sub-Clause [11.4(c) – 1999 / 11.4(d) – 2017].

Kind regards,
[Name]
[Title]
For and on behalf of the Employer

📩 4. Contractor to Engineer – Objection to Proposed Price Reduction (Clause 20.1 / 20.2 Claim)

Subject: Notice of Claim – Objection to Proposed Reduction Following Acceptance under Clause 9.4

Date: [Insert Date]  
To: The Engineer
From: The Contractor
Contract: [Project Name/Number]

Dear Sir/Madam,

We refer to your letter dated [insert date], proposing a reduction in the Contract Price pursuant to Sub-Clause 9.4(d) due to failed Tests on Completion.

We hereby notify a claim under Sub-Clause [20.1 – 1999 / 20.2 – 2017], on the basis that the failure arose due to circumstances attributable to the Employer, including but not limited to [e.g., late supply of Employer-Furnished Materials, incorrect inputs, lack of access].

We reserve our rights under the Contract and request that this claim be assessed as per the procedures set out in Clause 20.

Yours sincerely,
[Name]
[Title]
For and on behalf of the Contractor

📩 5. Engineer to Contractor – Determination of Reduction (after 14-day Disagreement Window, 2017)

Subject: Engineer’s Determination of Reduction under Clause 9.4(d) and 11.4(b)(ii)

Date: [Insert Date]  
To: The Contractor
From: The Engineer
Contract: [Project Name/Number]

Dear [Contractor’s Name],

Following the Parties’ failure to agree on the reduction in Contract Price pursuant to Sub-Clause 9.4(d) and 11.4(b)(ii) within the stipulated 14-day period, and in accordance with Sub-Clause 3.7, I have determined the reduction to be [insert amount or percentage], which represents the reduction in value to the Employer based on the failed performance of [insert details].

This determination is binding unless and until revised under Clause 21 [Dispute Avoidance/Adjudication] or arbitration.

Kind regards,
[Name]
The Engineer
Exit mobile version