FIDIC 1999 Sub-Clause Definitions 1.1.4.1 to 1.1.4.12 Explained Visually

76 / 100

Views in the last 30 days: 47

Estimated read time: 22 minute(s)

Table of Contents

🔹 1️⃣ Purpose of Sub-Clause 1.1.4.1 – “Accepted Contract Amount”

  • What it defines: This clause introduces a fundamental financial definition in the contract:
    “Accepted Contract Amount” means the amount accepted in the Letter of Acceptance for:
    • the execution and completion of the Works, and
    • the remedying of any defects.
  • Why it matters:
    • Sets the baseline value for the project.
    • Becomes the reference point for many other provisions—like performance security, delay damages, and final account evaluations.
    • Crucial for determining maximum liabilities, insurance, and retention calculations.
  • 🎯 Implication for the parties:
    • Employer: Offers budgetary control and clarity on financial commitments.
    • Contractor: Anchors financial planning, pricing risk, and security obligations.
    • Any deviation from this amount (e.g., due to Variations) doesn’t affect the definition but affects the actual Contract Price (see Sub-Clause 1.1.4.2).

🔹 2️⃣ Breakdown of Sub-Clause 1.1.4.1

📖 Text of the clause (verbatim):

‘Accepted Contract Amount’ means the amount accepted in the Letter of Acceptance for the execution and completion of the Works and the remedying of any defects.”

  • Key Phrases:
    • “Accepted”: This emphasizes the mutual agreement between the parties.
    • “Letter of Acceptance”: A formal document that sets the legal foundation for the contract.
    • “Execution and completion of the Works”: Covers design, procurement, construction, and commissioning.
    • “Remedying of any defects”: Includes obligations during the Defects Notification Period (Clause 11).

🔹 3️⃣ Key Interpretations and Implications

  • Fixed reference value: This amount is fixed at contract award. It does not change with variations, fluctuations, or claims—it remains the contractual reference.
  • ⚖️ Used for calculations such as:
    • Performance Security (Clause 4.2),
    • Delay damages (Clause 8.7),
    • Advance Payment (Clause 14.2),
    • Limitation of Liability (Clause 17.6).
  • Not to be confused with the “Contract Price” (Sub-Clause 1.1.4.2), which includes variations and adjustments.

🔹 4️⃣ Cross-Referencing with Other Clauses 🧩

  • Clause 14.1 – Contract Price: This clause builds on the Accepted Contract Amount to define how the actual price evolves through variations, cost changes, etc.
  • Clause 4.2 – Performance Security: Often expressed as a percentage of the Accepted Contract Amount.
  • Clause 8.7 – Delay Damages: Calculated per day based on a percentage of this amount.
  • Clause 17.6 – Limitation of Liability: Caps the contractor’s liability based on this amount if not otherwise stated.

🔹 1️⃣ Purpose of Sub-Clause 1.1.4.2 – “Contract Price”

  • What it defines: This clause introduces the definition of “Contract Price,” which goes beyond the static value in the Letter of Acceptance.
  • It recognizes the dynamic nature of construction projects—Contract Price includes variations, adjustments, and claims during the contract lifecycle.
  • 🎯 Why it matters:
    • It’s the actual amount payable to the Contractor for executing, completing, and remedying defects in the Works.
    • Unlike the “Accepted Contract Amount” (Clause 1.1.4.1), this figure fluctuates throughout the project.
    • It governs key financial obligations including interim payments, final payments, and claims.

🔹 2️⃣ Breakdown of the Clause 📖

“‘Contract Price’ means the price defined in Sub-Clause 14.1 [The Contract Price], and includes adjustments in accordance with the Contract.”

Key Elements:

  • Defined in Sub-Clause 14.1: This clause houses the actual operational rules about how the Contract Price is determined and adjusted.
  • 🔄 Includes adjustments: Such as:
    • Variations (Clause 13),
    • Claims under Clause 20,
    • Adjustments for changes in cost (Clause 13.8),
    • Currency fluctuation, provisional sums, and more.

🔹 3️⃣ Key Interpretations & Implications

  • Distinction:
    • Accepted Contract Amount: Fixed, as per Letter of Acceptance.
    • Contract Price: Live, adjustable value based on actual project progress, claims, and approvals.
  • Impacts:
    • Basis for payments (Sub-Clauses 14.3 to 14.13).
    • Delay damages, advance payment recovery, and price escalation are tied to this amount.
    • If a dispute arises over payments, this is the reference point for quantification.
  • Interpretative Question:
    Can the Contract Price ever be lower than the Accepted Contract Amount?
    👉 Yes, especially in cases involving omissions, terminations, or defects not remedied—see Clause 11.4.

🔹 4️⃣ Cross-Referencing with Other Clauses 🧩

  • 🔗 Clause 14.1 – The Contract Price: Direct reference for understanding the pricing mechanics.
  • 🔗 Clause 13 – Variations and Adjustments: Adjustments are part of the Contract Price computation.
  • 🔗 Clause 20 – Claims: Entitlements under this clause (approved claims) affect the Contract Price.
  • 🔗 Clause 11.4 – Failure to Remedy Defects: May result in a reduction of the Contract Price.

🔹 1️⃣ Purpose of Sub-Clause 1.1.4.3 – “Cost”

  • Definition role: This sub-clause lays the foundation for interpreting any reference to “Cost” throughout the contract. It’s not just a casual word—it’s a defined term with contractual weight.
  • Why it matters:
    • Used extensively in claims, variations, prolongation, and payment disputes.
    • Dictates what the Contractor can recover under circumstances like delays or Employer’s breaches.
  • 👥 For whom is this important?
    • Contractors: To understand what they can claim.
    • Employers: To know what they’re liable to pay.
    • Engineers: To determine and evaluate costs.

🔹 2️⃣ Breakdown of the Clause 📖

“Cost” means all expenditure reasonably incurred (or to be incurred) by the Contractor, whether on or off the Site, including overhead and similar charges, but does not include profit.

Key Components:

  • 💰 “All expenditure reasonably incurred”: Not just invoices—this includes internal costs, logistics, and site-related spending.
  • 🏗️ “On or off the Site”: Covers full project operations—even remote offices, warehouses, or consultant fees.
  • 🔁 “To be incurred”: Includes future cost projections tied to approved entitlements.
  • 🚫 “But does not include profit”: This is huge! It explicitly excludes any mark-up—profit needs to be separately approved (often under the phrase “Cost plus reasonable profit”).

🔹 3️⃣ Key Interpretations and Implications

  • 🔄 Used in almost every claim: Whether it’s time-related or event-triggered (like suspension, force majeure), “Cost” is the bedrock for financial entitlement.
  • ⚠️ No automatic right to profit:
    • If profit is sought, it must be explicitly allowed in that clause (e.g., Clause 20.1 or Clause 13.2).
  • 📋 Reasonableness test:
    • The term “reasonably incurred” places a burden of justification on the Contractor.
    • Cost needs to be proven, not just claimed.

🔹 4️⃣ Cross-Referencing with Other Clauses 🧩

  • Sub-Clause 20.1 – Contractor’s Claims: “Cost plus reasonable profit” may be allowed for certain Employer-caused delays.
  • Sub-Clause 13.3 – Variations: Pricing may be based on actual Cost or agreed rates.
  • Sub-Clause 1.1.4.2 – Contract Price: Adjustments due to Cost (but without profit) impact the Contract Price.
  • Sub-Clause 8.9 – Suspension: Entitles the Contractor to Cost if the suspension is not due to his default.

🔹 5️⃣ What-If Scenarios

🔸 What if the Contractor incurs third-party consultant fees for acceleration requested by the Engineer?
→ These could be claimed as “Cost,” if reasonable and supported by documentation.

🔸 What if a delay occurs due to weather, and the Contractor incurs overheads?
→ If the delay qualifies under a relevant clause (e.g., 8.4), the overheads may be claimed as part of “Cost”—but not profit.

🔸 What if the Contractor claims for unquantified future expenses?
→ “Cost to be incurred” is allowed—but only when reasonably forecast and backed with evidence or logic.

🔹 1️⃣ Purpose of Sub-Clause 1.1.4.4 – “Final Payment Certificate”

  • What it defines: This clause provides the meaning of a “Final Payment Certificate”, marking the contractual closure of payment obligations between the Employer and Contractor (except for any outstanding or deferred obligations).
  • It’s a key milestone in concluding the financial relationship under the contract.
  • 🎯 Why it matters:
    • Certifies that the Contractor has fulfilled all obligations and is entitled to the final amount due.
    • Triggers payment of the final balance, if any.
    • Signifies a point beyond which no further payment certificates will be issued under the Contract (except as per legal rights or unfulfilled obligations).

🔹 2️⃣ Breakdown of the Clause 📖

“Final Payment Certificate” means the payment certificate issued under Sub-Clause 14.13 [Issue of Final Payment Certificate].

Breakdown:

  • 🔗 Reference to Clause 14.13 is critical because that’s where the process and criteria for issuing this certificate are detailed.
  • It’s not merely symbolic—it is a formal declaration by the Engineer that:
    • The Final Statement has been reviewed,
    • All payments, adjustments, and claims are accounted for,
    • And both Parties are nearing contractual closure.

🔹 3️⃣ Key Interpretations & Implications

  • 🧾 Based on the Final Statement (defined in Sub-Clause 1.1.4.5).
  • No further entitlement to additional amounts unless:
    • There’s a contractual dispute or
    • There are unfulfilled obligations under Clause 11.10 (Unfulfilled Obligations).
  • ⏱️ Time trigger: The certificate is issued within 28 days of the Engineer receiving the Final Statement and supporting documentation (Clause 14.13).

🔹 4️⃣ Cross-Referencing with Other Clauses 🧩

  • Sub-Clause 14.13 – Issue of Final Payment Certificate: Core procedure for issuance.
  • Sub-Clause 14.11 – Application for Final Payment Certificate: Contractor’s obligation to apply with a Final Statement.
  • Sub-Clause 11.10 – Unfulfilled Obligations: Even after the Final Payment Certificate, some obligations may still continue.
  • Sub-Clause 20.1 – Contractor’s Claims: If claims are submitted late or unapproved before finalization, they may be barred unless they fall under continuing obligations.

🔹 5️⃣ What-If Scenarios

🔸 What if the Contractor forgets to include an item in the Final Statement?
→ The Engineer may not include it in the Final Payment Certificate unless it’s a continuing obligation.

🔸 What if a claim is still under dispute?
→ The disputed amount may be withheld or excluded, pending resolution under Clause 20 (Disputes).

🔸 What if the Contractor submits the Final Statement late?
→ The Engineer’s obligation to certify is not triggered until it is properly submitted.

🔹 1️⃣ Purpose of Sub-Clause 1.1.4.5 – “Final Statement”

  • 🧾 What it defines: This clause identifies what is meant by the term Final Statement, a crucial financial document in the contract close-out phase.
  • 🎯 Why it matters:
    • It’s the Contractor’s formal submission for final payment after the Works are completed and all known claims are submitted.
    • It kicks off the procedure for the Engineer to issue the Final Payment Certificate.
    • Acts as the financial “wrap-up” of the project, consolidating all claims, changes, and entitlements.
  • 👥 Relevant to:
    • Contractors: Must ensure that it captures all costs and entitlements.
    • Employers: Used to assess final liabilities.
    • Engineers: It starts their duty to certify under Sub-Clause 14.13.

🔹 2️⃣ Clause Text Breakdown 📖

“Final Statement” means the statement defined in Sub-Clause 14.11 [Application for Final Payment Certificate].

  • It refers directly to Sub-Clause 14.11, which outlines:
    • What the Final Statement should include,
    • When and how it must be submitted,
    • The documentation to accompany it.

🔹 3️⃣ Key Interpretations & Implications

  • 📌 The Final Statement must include:
    • The total amount the Contractor believes is due under the Contract.
    • All items that have been agreed upon or are pending determination.
    • All claims, variations, and adjustments to the Contract Price.
  • Timing is critical:
    • The Final Statement must be submitted within 84 days after receiving the Taking-Over Certificate for the whole Works (unless agreed otherwise in writing).
  • ⚠️ Late or incomplete Final Statements can delay or prevent issuance of the Final Payment Certificate under Clause 14.13.

🔹 4️⃣ Cross-References with Other Clauses 🧩

  • Sub-Clause 14.11 – Application for Final Payment Certificate: Governs how and when the Final Statement must be submitted.
  • Sub-Clause 14.13 – Issue of Final Payment Certificate: Can only proceed after receiving and verifying the Final Statement.
  • Sub-Clause 20.1 – Contractor’s Claims: All claims to be included in Final Statement or risk being time-barred.
  • Clause 11.10 – Unfulfilled Obligations: Even after the Final Statement, the contract remains alive for any remaining duties.

🔹 5️⃣ What-If Scenarios

🔸 What if the Contractor fails to submit a Final Statement within the 84 days?
→ The Engineer is not obligated to issue a Final Payment Certificate until it’s received.

🔸 What if a claim is ongoing when the Final Statement is submitted?
→ It should still be included in the Final Statement and marked as “pending determination.”

🔸 What if a dispute arises over the contents of the Final Statement?
→ Clause 20 (Claims & Disputes) provides the mechanism for resolution, including DAB referral.

🔹 1️⃣ Purpose of Sub-Clause 1.1.4.6 – “Foreign Currency”

  • 💱 Definition Purpose: This clause introduces a key commercial term used throughout the contract where payments may not be in the local currency.
  • Why it’s important:
    • Enables multi-currency contracts, often essential for international projects involving overseas Contractors or imported goods.
    • Assures the Contractor of payment in agreed foreign denominations—minimizing exchange rate risk.
  • 🧩 This clause supports financial clarity where the Contract Price includes amounts payable in more than one currency.

🔹 2️⃣ Clause Text Overview 📖

“Foreign Currency” means a currency other than the Local Currency. One particular Foreign Currency may be required.

✅ Key Points:

  • 📌 “Local Currency” is separately defined (in Sub-Clause 1.1.4.7).
  • The clause suggests that only one Foreign Currency may be required, although more could be specified in the Appendix to Tender or Particular Conditions.

🔹 3️⃣ Key Interpretations & Implications

  • 🔄 Used in calculations and payment breakdowns, especially for:
    • Advance payments (Clause 14.2),
    • Interim Payment Certificates (Clause 14.6),
    • Final Payment Certificates (Clause 14.13),
    • Performance Security amounts (Clause 4.2).
  • 💬 The choice of currency must be clearly stated and agreed before contract signing. It is not left open to later interpretation.
  • 🔐 This ensures the Contractor knows exactly what currency will be received, guarding against inflation or devaluation in the project’s country.

🔹 4️⃣ Cross-References with Other Clauses 🧩

  • Sub-Clause 1.1.4.7 – Local Currency: Directly related—this clause sets the contrast to Foreign Currency.
  • Sub-Clause 14.1 – Contract Price: Often broken down by currency proportions (local + foreign).
  • Appendix to Tender: Usually includes a table stating currency splits.
  • Sub-Clause 14.2 – Advance Payment: Advance amounts are commonly paid in the same proportions as the Contract Price currencies.

🔹 5️⃣ What-If Scenarios

🔸 What if the Employer tries to pay the entire Contract Price in Local Currency despite the Contract specifying a Foreign Currency?
→ This would likely be a breach of contract, and the Contractor may raise a claim under Clause 20.1.

🔸 What if exchange controls in the Country restrict outgoing foreign payments?
→ The Employer would still be obligated under the Contract but may face legal challenges—this risk must be assessed during tendering.

🔸 Can more than one Foreign Currency be used?
→ Yes, if defined in the Contract documents. The wording in 1.1.4.6 only mentions “one particular” currency may be required, not that more cannot be.

🔹 1️⃣ Purpose of Sub-Clause 1.1.4.7 – “Interim Payment Certificate”

  • 💰 Why it exists: This clause introduces a formal definition for the Interim Payment Certificate—a critical tool used throughout the construction period to process regular payments to the Contractor.
  • 🎯 What it does:
    • Forms the basis for progress payments under Clause 14 [Contract Price and Payment].
    • Recognizes that payments are made at intervals before project completion.
    • Ensures structured cash flow, preventing payment only at the end.

🔹 2️⃣ Clause Text Breakdown 📖

“Interim Payment Certificate” means a payment certificate issued under Clause 14, other than the Final Payment Certificate.

✅ Key Terms:

  • “Other than the Final Payment Certificate”: Indicates that this applies to all certificates issued prior to the final settlement under Sub-Clause 14.13.
  • Tied to Clause 14: This includes Sub-Clauses like:
    • 14.3 – Application for Interim Payment Certificate
    • 14.6 – Issue of Interim Payment Certificate

🔹 3️⃣ Key Interpretations & Implications

  • 💵 Issued Monthly or at Agreed Intervals: Often linked to a monthly payment cycle, based on progress of Works.
  • 📝 Engineer’s Review Role:
    • The Contractor submits an application (Sub-Clause 14.3),
    • The Engineer verifies and certifies payment (Sub-Clause 14.6).
  • ⚖️ Not conclusive evidence: These certificates do not imply final acceptance or settlement. Adjustments can still happen in later certificates.

🔹 4️⃣ Cross-Referenced Clauses 🧩

  • Sub-Clause 14.3 – Application for Interim Payment Certificates: The Contractor’s detailed breakdown of amounts claimed.
  • Sub-Clause 14.6 – Issue of Interim Payment Certificate: Engineer’s obligations for verifying and certifying the amount due.
  • Sub-Clause 14.13 – Final Payment Certificate: The defining opposite—issued after full completion and acceptance.
  • Clause 20 – Claims: Any additional entitlement outside of regular progress payments must follow this procedure.

🔹 5️⃣ What-If Scenarios

🔸 What if the Contractor makes an error in the application?
→ The Engineer can correct or reduce the certified amount under Sub-Clause 14.6.

🔸 What if the Employer delays payment after certification?
→ The Contractor may claim financing charges under Sub-Clause 14.8 [Delayed Payment].

🔸 What if quantities change dramatically?
→ Adjustments are reflected in the next Interim Payment Certificate, or dealt with via Clause 13 – Variations.

🔹 1️⃣ Purpose of Sub-Clause 1.1.4.8 – “Local Currency”

  • 🌍 What it defines: The clause provides a specific definition for “Local Currency,” which is fundamental for all contracts involving multiple currencies or international parties.
  • 🎯 Why it’s important:
    • Serves as the default currency of payment, valuation, and pricing within the host country where the project is located.
    • Helps define financial obligations in the native economic context of the country of execution.
  • 👥 Relevant to:
    • Employers: For budgeting and controlling local expenditure.
    • Contractors: For complying with local tax laws, payroll, and procurement.
    • Engineers and Auditors: For accounting and pricing compliance.

🔹 2️⃣ Text Breakdown 📖

“Local Currency” means the currency of the Country.”

  • ✅ Short, precise, and cross-referenced with “Country,” which is separately defined in Sub-Clause 1.1.6.2.
  • 🔁 “Local Currency” is used to:
    • Split the Contract Price between foreign and local portions.
    • Determine retention money, advances, and taxes.

🔹 3️⃣ Key Interpretations & Implications

  • 🧾 Impacts how the Contract Price is structured:
    • Most contracts will specify a percentage of the Contract Price payable in Local Currency and the rest in Foreign Currency (see Sub-Clause 14.1 and Appendix to Tender).
  • 💬 In cases where the Local Currency is unstable (due to inflation, etc.), the risk is usually carried by the Contractor—unless adjusted via Sub-Clause 13.8.
  • ⚠️ Contractual clarity is essential:
    • The term must be consistent with the “Country” defined.
    • All financial documents, such as Interim Payment Certificates, must clearly distinguish amounts in Local vs. Foreign Currency.

🔹 4️⃣ Cross-References with Other Clauses 🧩

  • Sub-Clause 1.1.4.6 – Foreign Currency: Works in contrast to Local Currency; the two are often used together in pricing schedules.
  • Clause 14 – Contract Price and Payment: Most references to currency splits occur here, particularly in:
    • 14.1 – Contract Price
    • 14.2 – Advance Payment
    • 14.6 – Interim Payment Certificate
  • Appendix to Tender: Lists the currency proportions for payments.

🔹 5️⃣ What-If Scenarios

🔸 What if a government changes its currency (e.g., due to redenomination)?
→ The “Local Currency” definition would automatically apply to the new national currency, unless specifically varied in the Particular Conditions.

🔸 What if the Contract specifies Local Currency for payment but does not define the Country?
→ This may lead to ambiguity and could become a dispute point if project jurisdiction is unclear.

🔸 Can Local Currency include multiple types (e.g., regional & national currencies)?
→ No. It strictly means the currency of the defined Country under the contract.

🔹 1️⃣ Purpose of Sub-Clause 1.1.4.9 – “Payment Certificate”

  • 💵 Definition Scope: This clause defines what is meant by a “Payment Certificate”—a central instrument used throughout the contract to certify payments due from the Employer to the Contractor.
  • 🎯 Why it matters:
    • It’s the official confirmation by the Engineer of the amount payable.
    • Without a Payment Certificate, the Employer is not obligated to pay.
    • It ensures payment claims are substantiated, verified, and contractually approved.

🔹 2️⃣ Clause Text Breakdown 📖

“Payment Certificate” means a payment certificate issued under Clause 14 [Contract Price and Payment].

✅ This definition serves as a generic umbrella for all types of Payment Certificates, including:

  • Advance Payment Certificate (Sub-Clause 14.2),
  • Interim Payment Certificates (Sub-Clause 14.6),
  • Final Payment Certificate (Sub-Clause 14.13).

🧩 The specific form and procedure for each type of Payment Certificate is detailed in the relevant sub-clauses of Clause 14.

🔹 3️⃣ Key Interpretations & Implications

  • 🧾 Not a guarantee of payment by itself:
    • A Payment Certificate is an acknowledgment of entitlement, but payment still depends on the Employer’s financial standing and Clause 14.7 (Time for Payment).
  • 🕒 Triggers time obligations:
    • The date of issuance starts the countdown for when the Employer must pay (usually within 56 days under Sub-Clause 14.7 unless amended).
  • 🔐 Legal safeguard:
    • Issuance of a Payment Certificate limits disputes—it’s a neutral Engineer-led process that validates claims.

🔹 4️⃣ Cross-Referenced Clauses 🧩

  • Clause 14 – Contract Price and Payment:
    • This is the central operational framework for all payment-related procedures.
  • Sub-Clause 14.2 – Advance Payment: Leads to an advance payment certificate.
  • Sub-Clause 14.6 – Interim Payment Certificate: Issued monthly for progress payments.
  • Sub-Clause 14.13 – Final Payment Certificate: Closes financial obligations after Final Statement.
  • Clause 20 – Claims: Any unapproved claims must be pursued separately and don’t form part of the Payment Certificate automatically.

🔹 5️⃣ What-If Scenarios

🔸 What if the Engineer delays issuing a Payment Certificate?
→ The Contractor can serve notice under Clause 20.1 (Contractor’s Claims) and may also be entitled to interest under Sub-Clause 14.8.

🔸 What if the Employer doesn’t pay even after certification?
→ The Contractor can suspend work (Sub-Clause 16.1) or terminate the contract (Sub-Clause 16.2).

🔸 Can the Employer dispute a Payment Certificate after it’s issued?
→ Generally no, unless fraud or error is proven. Otherwise, disputes must go through the DAB or arbitration process under Clause 20.

inal Takeaways 💡

ItemDescription
DefinitionA formal certificate issued by the Engineer confirming the payment due
TypesAdvance, Interim, Final
Governing ClauseClause 14
TriggersEmployer’s obligation to pay
Legal WeightHigh—it is the basis for enforcing payment claims

🔹 1️⃣ Purpose of Sub-Clause 1.1.4.10 – “Provisional Sum”

  • 💼 Why it exists: A Provisional Sum is a placeholder in the Contract Price for works or items that are not clearly defined at tender stage. It’s a strategic allowance for unpredictable or discretionary work.
  • 🎯 Key Objective:
    • Provides budget flexibility without changing the Contract Price immediately.
    • Allows the Employer (via the Engineer) to instruct work later without needing a full Variation process upfront.
  • 👥 Who uses it:
    • Employers: Use it to retain discretion over certain work scopes.
    • Contractors: Must execute such works only upon instruction.

🔹 2️⃣ Clause Text Breakdown 📖

“Provisional Sum” means a sum (if any) which is specified in the Contract as a provisional sum, for the execution of any part of the Works or for the supply of Plant, Materials or services under Sub-Clause 13.5 [Provisional Sums].

Key Elements:

  • 📦 “Specified in the Contract”: The Provisional Sum must be pre-listed in the Bill of Quantities or Pricing Schedule.
  • 🔧 For execution/supply: Can be used for:
    • Construction tasks,
    • Equipment or Plant,
    • Services (e.g., testing, third-party works).

🔹 3️⃣ Key Interpretations & Implications

  • 🛠️ Engineer’s Control:
    • The Contractor may not act on a Provisional Sum item until instructed by the Engineer.
  • 🔍 Defined in Sub-Clause 13.5:
    • Payment for Provisional Sums depends on:
      • Instructions received,
      • Actual cost incurred,
      • Percentages for overheads/profit added as defined in the Appendix to Tender.
  • ⚖️ It’s not a claimable amount until work is done—having a Provisional Sum in the contract doesn’t grant entitlement unless it’s activated.

🔹 4️⃣ Cross-Referenced Clauses 🧩

  • Sub-Clause 13.5 – Provisional Sums: Core procedure for how and when Provisional Sums are used and valued.
  • Clause 14 – Contract Price and Payment: Governs how Provisional Sums are processed through Payment Certificates.
  • Appendix to Tender: States the percentage to be applied to Provisional Sums (e.g., 10% OH + 5% profit).

🔹 5️⃣ What-If Scenarios

🔸 What if the Employer decides not to use a Provisional Sum?
→ Then no amount is added to the Contract Price. The sum remains unused.

🔸 What if the actual cost is more than the Provisional Sum?
→ The Contract Price is adjusted to reflect the actual value, subject to the Engineer’s determination under Sub-Clause 13.5.

🔸 What if the Contractor executes Provisional Sum work without instruction?
→ It may not be payable. Work must be initiated only upon instruction.

Final Takeaways 💡

ElementSummary
DefinitionA placeholder amount for undefined works/items
Not automaticOnly payable upon Engineer’s instruction
Valued underSub-Clause 13.5
PurposeProvides flexibility for discretionary/emerging scope
Payment triggerInstruction + actual execution

🔹 1️⃣ Purpose of Sub-Clause 1.1.4.11 – “Schedule of Payments”

  • 📆 Why it’s important: This clause defines what a Schedule of Payments is—an essential planning and payment tool that specifies when and how the Contractor will be paid during the course of the Contract.
  • 🎯 Main Objectives:
    • Establishes pre-agreed payment milestones (instead of monthly valuations),
    • Assures the Employer of payment control aligned with project stages,
    • Helps the Contractor maintain cash flow predictability based on progress targets.
  • 👥 Key users:
    • Contractor: For billing and cash flow planning,
    • Engineer: For verifying and certifying payments,
    • Employer: For controlling disbursements tied to deliverables.

🔹 2️⃣ Clause Text Breakdown 📖

“Schedule of Payments” means the schedule stated in the Appendix to Tender and any revised schedule prepared by the Contractor and approved by the Engineer under Sub-Clause 14.4 [Schedule of Payments].

✅ This definition includes both:

  • 📑 The initial schedule (included with the Tender), and
  • ✍️ Any Engineer-approved revisions submitted later during contract execution.

🔹 3️⃣ Key Interpretations & Implications

  • 🔄 Dynamic & Adjustable:
    • The Contractor may propose updates, but approval by the Engineer is mandatory.
    • Schedule must align with actual progress and sequencing of the Works.
  • 💵 Used in milestone-based contracts:
    • Payments are linked to completion of specific work sections or deliverables, not just time-based progress.
    • Must reflect realistic and measurable outputs to avoid disputes.
  • 🔒 Binding Framework:
    • Once approved, the Employer is obligated to pay according to the certified milestones in the schedule.

🔹 4️⃣ Cross-Referenced Clauses 🧩

  • Sub-Clause 14.4 – Schedule of Payments:
    • Details the procedure for submission and revision of the Schedule.
  • Sub-Clause 14.3 – Application for Interim Payment Certificate:
    • Ties the payment application process directly to the agreed schedule.
  • Appendix to Tender:
    • The original Schedule of Payments is typically included here.
  • Clause 4.1 – Contractor’s General Obligations:
    • Requires execution in accordance with all approved documents, including payment schedules.

🔹 5️⃣ What-If Scenarios

🔸 What if the Contractor doesn’t submit a revised Schedule despite changed circumstances?
→ The Engineer may withhold or delay payment certification under Sub-Clause 14.6, citing inconsistency.

🔸 What if progress doesn’t match the payment milestone?
→ Payment may be withheld or adjusted until the milestone is achieved and certified.

🔸 Can the Employer unilaterally revise the schedule?
→ No. Only the Contractor can propose a revised schedule, and the Engineer must approve it.

Final Takeaways 💡

TopicSummary
What it isA timeline or milestone-based payment plan
Set byContractor (initial or revised), approved by Engineer
Used forDetermining when payments are due
Legal weightForms a binding structure for progress-linked payments
FlexibilityCan be revised with proper justification and Engineer’s approval

📌 Pro Tip: For projects with uneven cash flow or staged deliverables, always ensure the Schedule of Payments matches the actual resource deployment and execution plan 🧾.

🔹 1️⃣ Purpose of Sub-Clause 1.1.4.12 – “Statement”

  • 🧾 Definition Role: This clause defines what a “Statement” means in the context of project payments.
  • 🎯 Main Objective:
    • Serves as the Contractor’s formal request for payment, submitted in accordance with Clause 14 [Contract Price and Payment].
    • It triggers the Engineer’s review and certification process.
    • Ensures there’s a standardized format for financial documentation.
  • 👥 Who it matters to:
    • Contractor: To claim progress payments.
    • Engineer: To assess compliance and issue Payment Certificates.
    • Employer: For processing and releasing funds.

🔹 2️⃣ Clause Text Breakdown 📖

“Statement” means a statement submitted by the Contractor as part of an application, under Clause 14 [Contract Price and Payment], for a payment certificate.

📌 Highlights:

  • It includes Advance Payment Statements, Interim Statements, and Final Statements.
  • Structured submission that must comply with timing and content rules under Sub-Clause 14.3 and others.

🔹 3️⃣ Key Interpretations & Implications

  • 📅 Must be submitted monthly (unless otherwise agreed) per Sub-Clause 14.3 – Application for Interim Payment Certificates.
  • 📋 Typical content includes:
    • Value of work executed,
    • Materials delivered to Site,
    • Advance payment adjustments,
    • Retention,
    • Deductions for taxes, penalties, or employer claims,
    • Variation adjustments,
    • Supporting documentation.
  • 🔁 Dynamic & Cumulative: Each new Statement builds on previous ones, adjusting figures as needed.

🔹 4️⃣ Cross-References with Other Clauses 🧩

  • Clause 14 – Contract Price and Payment:
    • Especially Sub-Clause 14.3, which dictates how Statements are to be formatted and submitted.
  • Sub-Clause 14.11 – Application for Final Payment Certificate:
    • Final Statement is the last and most critical Statement in the contract lifecycle.
  • Sub-Clause 20.1 – Contractor’s Claims:
    • Additional amounts not included in routine Statements must follow this claims procedure.

🔹 5️⃣ What-If Scenarios

🔸 What if the Contractor fails to submit a Statement on time?
→ The Engineer may delay issuing the Payment Certificate, which could impact cash flow.

🔸 What if an item is missed in a Statement?
→ It can be added in a subsequent Statement, but may raise disputes if it relates to completed work or expired claim periods.

🔸 What if the Statement includes unsubstantiated claims?
→ The Engineer may reject or reduce the claimed amount under Sub-Clause 14.6, and request clarification.

Final Takeaways 💡

TopicSummary
DefinitionA formal document submitted by the Contractor to request payment
Used inAll stages: advance, interim, final payments
Reviewed byThe Engineer, who then issues the Payment Certificate
Basis forCash flow, progress verification, claim processing
RiskIncorrect/incomplete Statements can delay payments 🛑

📌 Pro Tip: A well-prepared Statement backed by solid documentation is the fastest route to securing your payment on time 💼.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top