📘 FIDIC Clause 10.1 Quiz – Test Your Knowledge on TOC Rules

76 / 100 SEO Score

Views in the last 30 days: 80

Estimated read time: 3 minute(s)

📖 Want to Deepen Your Knowledge?

Now that you’ve tested yourself on Clause 10.1, explore the complete breakdown, comparisons, scenarios, and expert commentary in the full article.

Read Full Article on Clause 10.1

📘 FIDIC Clause 10.1 – Taking-Over Certificate Quiz

Test your knowledge of TOC procedures under FIDIC Yellow Book 1999 & 2017.

  1. When can the Contractor request a Taking-Over Certificate?
    After DNP ends
    After completing the Works and passing Tests on Completion
    At the start of the project
  2. What is the Engineer’s response time after receiving a TOC request?
    7 days
    14 days
    28 days
  3. Under FIDIC 2017, TOC request must be accompanied by:
    Bank guarantee
    Test results from Clause 9.1
    Training certificates
  4. Can the Engineer issue TOC with minor outstanding works?
    Yes, if they don’t affect intended use
    No, all work must be 100% complete
    Only with Employer’s written permission
  5. What starts immediately upon TOC issuance?
    Final payment
    Retention release
    Defects Notification Period
  6. If the Engineer rejects TOC, what must be provided?
    List of reasons and actions needed
    Verbal explanation
    Nothing, rejection is final
  7. Under FIDIC 2017, if Engineer doesn’t respond in 28 days:
    TOC is deemed issued
    Contractor submits claim
    Contractor waits for further notice
  8. The Final Statement is submitted:
    Immediately after TOC
    After Performance Certificate
    Before testing
  9. Sectional Taking-Over Certificates are:
    Not allowed
    Only allowed for roads
    Permitted under Clause 10.1
  10. Taking-Over Certificate marks:
    Completion of DNP
    Transfer of care and risk to Employer
    Termination of Contract
  11. What must the Engineer state in a rejection notice under Clause 10.1?
    That the Works are not fully paid
    That the Employer is unavailable
    The reasons for rejection and the actions required to comply
  12. Who assumes responsibility for care of the Works after TOC is issued?
    Contractor
    Engineer
    Employer
  13. Can TOC be requested for individual Sections of the Works?
    Only if specified in Particular Conditions
    No, only the entire Works
    Yes, Clause 10.1 allows TOC for Sections
  14. In absence of Engineer’s response within 28 days (2017) and if allowed by Particular Conditions:
    Contractor automatically paid in full
    TOC deemed issued
    DNP is void
  15. Which of the following is not required with a TOC request under FIDIC 2017?
    Copy of Test on Completion results
    As-built drawings
    Defects Notification Period schedule
  16. What happens if the Employer starts using the Works before TOC is issued (Clause 10.2)?
    Nothing changes legally
    It’s deemed as Taking Over of that part used
    Contract is terminated
  17. TOC signifies which of the following milestones?
    Start of liability for Contractor default
    Completion of payment terms
    Transfer of possession and risk
  18. What is the typical duration of the DNP under FIDIC unless stated otherwise?
    14 days
    90 days
    365 days
  19. Which clause in FIDIC 2017 defines the conditions for Tests on Completion?
    Clause 5.1
    Clause 3.6
    Clause 9.1
  20. Who issues the Taking-Over Certificate under Clause 10.1?
    Employer
    Contractor
    Engineer