Site icon Navigating Knowledge Across Domains

Mastering Subcontractor Claims and Compliance

Clause 2.3: Instructions and Determinations under Main Contract is a pivotal provision in the FIDIC Yellow Book of Conditions of Subcontract for Plant and Design-Build (2019 Edition). This clause outlines the Subcontractor’s obligations concerning instructions and determinations issued by the Engineer under the Main Contract (MC). It ensures that the Subcontractor aligns its actions with directives that impact the Subcontract Works, even if such instructions were not validly given under the MC. Clause 2.3 also delineates the protocol when the Subcontractor receives direct instructions from the Employer or the Engineer, emphasizing the necessity for these to be confirmed as a Contractor’s Instruction before compliance. By establishing clear guidelines, this clause fosters effective communication and coordination among all parties, thereby facilitating the smooth execution of the project.

Key Components and Definitions

Compliance with Engineer’s Instructions: The clause mandates that the Subcontractor must “comply with all instructions and determinations of the Engineer which are notified to him as a Contractor’s Instruction, irrespective of whether the instructions and determinations were validly given under the Main Contract.” This means the Subcontractor is bound to follow instructions relayed by the Contractor, even if there’s a question about their validity under the MC.

Subject to Sub-Clause 3.1 [Contractor’s Instructions]: The obligation to comply is “subject to Sub-Clause 3.1 [Contractor’s Instructions],” which specifies that the Subcontractor shall take instructions only from the Contractor’s Subcontract Representative. This underscores the chain of command and communication protocol within the contractual relationship.

The  Subcontractor  shall  take  instructions  only  from  the  Contractor’s  Subcontract Representative who shall  have the authority in  relation  to the Subcontract Works to give instructions as  the Engineer has under Main Contract Clause 3.3 [Instructions of the  Engineer].  The  Subcontractor  shall  comply  with  all  instructions,  given  or confirmed  in  writing , of the  Contractor’s  Subcontract Representative  on  any  matter related to the Subcontract.   

Direct Instructions from Employer or Engineer: Clause 2.3: Instructions and Determinations under Main Contract

The  Subcontractor  shall,  in  relation  to  the  Subcontract  Works,  comply  with  all instructions  and  determinations  of  the  Engineer  which  are  notified  to  him  as  a Contractor’s Instruction,  irrespective  of whether  the  instructions and  determinations were  validly  given  under the Main  Contract.  This obligation shall be subject to Sub-­Clause 3.1 [Contractor’s Instructions]. If the Subcontractor shall receive any direct instruction from the Employer or the Engineer:

  1. Immediate Notification: “He shall immediately inform the Contractor’s Subcontract Representative and shall supply him with a copy of the direct instruction if given in writing.” This ensures that the Contractor is aware of any directives that may affect the Subcontract Works.
  2. No Obligation to Comply Until Confirmed: “He shall have no obligation to comply with any such direct instruction unless and until it has been confirmed in writing as a Contractor’s Instruction.” This protects the Subcontractor from acting on unendorsed instructions that may conflict with contractual obligations.

Subcontract Variations: If an instruction or determination constitutes a Subcontract Variation, “Clause 13 [Subcontract Variations and Adjustments]” applies. This means adjustments to the Subcontract Price or schedule may be warranted, and procedures outlined in Clause 13 must be followed.

Interaction with Clause 3.1 [Contractor’s Instructions]: Clause 2.3 is intrinsically linked to Clause 3.1, which states that “the Subcontractor shall take instructions only from the Contractor’s Subcontract Representative who shall have the like authority in relation to the Subcontract Works to give instructions as the Engineer has under MC Clause 3.3 [Instructions of the Engineer].” This establishes that the Subcontractor’s primary point of contact for instructions is the Contractor’s designated representative.

Key Definitions:

Interactions with Other Clauses:

By adhering to these clauses, the Subcontractor ensures compliance with contractual obligations, maintains proper communication channels, and safeguards against unauthorized instructions that could impact the project’s scope or cost.

Challenges and Solutions

Challenges:

  1. Direct Instructions from Employer or Engineer: Subcontractors may inadvertently act on direct instructions from the Employer or Engineer without proper authorization, leading to contractual breaches or unapproved variations.Solution: The Subcontractor should implement a strict internal protocol to ensure that any direct instructions are immediately reported to the Contractor’s Subcontract Representative. Training staff on contractual obligations and communication procedures can mitigate this risk.
  2. Validity of Instructions: Determining whether an instruction is valid under the Main Contract can be complex, especially if the instruction is contested between the Contractor and the Employer.Solution: The Subcontractor should focus on the requirement to comply with instructions notified as Contractor’s Instructions, as per Clause 2.3. This shifts the responsibility of validating instructions to the Contractor, ensuring the Subcontractor operates within its contractual scope.
  3. Subcontract Variations and Adjustments: Unclear processes for handling variations can lead to disputes over pricing and scheduling adjustments.Solution: Adhering to the procedures in Clause 13 ensures that any variations are properly documented, valued, and agreed upon. The Subcontractor should proactively engage with the Contractor when variations arise to reach timely agreements on adjustments.

Interaction with Other Clauses:

Best Practices:

By proactively addressing these challenges and adhering to the stipulated clauses, the Subcontractor can navigate the complexities of instructions and determinations effectively, minimizing risks and fostering a collaborative project environment.

Exit mobile version