![]()
PCA Case No. 2020-14 — Mota-Engil (Paraguay) v. MOPC
Background & Context — in simple words
What was planned? Paraguay wanted a fast bus system (“Metrobus”) in the capital area. In 2016, the Ministry of Public Works (MOPC) hired Mota-Engil (the Paraguay branch of a large contractor) to build parts of the bus corridor.
What went wrong? The contractor could not reach key work areas. Land had not been fully expropriated and some city permits were missing. Without land access and permits, work slowed and then stopped.
How did we reach arbitration? After two 2019 Memoranda of Understanding (MoUs) failed to fix the problems, MOPC terminated the contract in February 2020. Mota-Engil had already filed for arbitration in December 2019 under the contract’s clause. The Permanent Court of Arbitration (PCA) acted as registry; the case followed the UNCITRAL 2013 Rules, with the legal “seat” in Asunción (so Paraguayan law mattered a lot).
Core Issues & Outcomes — explained simply
- Access to the site & expropriation (Employer risk): The State (through MOPC) had the duty to progressively give possession of the areas so the contractor could work. If land titles or “domain strips” were not ready, the State was better placed to fix that. Example: If a 500-m stretch still needs expropriation, the Employer must sort it or adjust the sequence so work can continue elsewhere.
- Permits for permanent works (Employer duty): The tribunal read the contract as making MOPC responsible for the permits for the permanent works. Some permits were blocked because the design clashed with municipal sewer standards. That still pointed back to MOPC (project owner/designer responsibility). Example: If a drainage design conflicts with the city system, the Employer must update design and obtain the permit.
- Multi-tier clause & the 2nd MoU (Admissibility): Although the contract had steps before arbitration (like forming a dispute board), the parties later agreed in a 2019 MoU that disputes could go straight to arbitration. The tribunal applied Paraguayan law and the “favor contractus” principle (keep agreements effective) to accept this. Plain take: If both sides signed an MoU that changes the path, the tribunal can honor that change.
- Termination (failure to renew the Performance Security): MOPC’s termination was valid in principle because renewing the bond/guarantee on time is a fundamental contractor duty under FIDIC-style wording. But the tribunal still controlled how the Employer could use the guarantees while the arbitration was ongoing (see next point).
- Provisional measures (don’t call the bonds): To avoid making the dispute worse, the tribunal ordered MOPC not to draw the performance or advance-payment guarantees, and told the contractor to post arbitration guarantees instead. Because the State did not fully comply, the tribunal imposed a cost sanction (extra share of legal costs against the State).
Mini-Checklist (FIDIC clauses with tiny examples)
Damages & Interest — what the award basically did
- Pay for work done: Sums for certified works and release of retention where due.
- Guarantee/bond adjustments: Refunds where the performance bond was drawn beyond what the tribunal allowed during the case.
- Direct costs (daño emergente): Certain costs linked to the delays split across time windows; the State bore a meaningful portion because it controlled access/permits.
- No lost profits: Lost profits were excluded by the contract’s liability limits (typical FIDIC-style cap/exclusion).
- Interest: Applied by currency using reference rates plus a spread (so USD/EUR amounts did not all use the same rate).
Practical tip: Keep a live Security & Guarantees Register (Performance, Advance, Retention) with reminders. If provisional measures are issued, swap to “arbitration guarantees” promptly and record the timelines.
Learn More (internal links)
Watch (from our playlist)
Key Sources (quick access)
These links help verify dates, tribunal, seat, and the core findings about access, permits, termination, and provisional measures.
Mota‑Engil (Paraguay) v. MOPC — Key Issues in Dispute
1) Site Access & Expropriation — who had to open the work fronts?
In simple terms: The contractor said, “We could not work because the State did not hand over all areas on time.” The State replied, “The tender warned about land problems; you accepted the risk.”
- What mattered Whether the Employer (MOPC) had the duty to progressively give possession of each stretch, and to finish expropriations/rights‑of‑way so the crews could enter.
- Practical example If 1 km is ready and 0.5 km is pending expropriation, the Employer should sequence access so work continues on the available 1 km while it fixes the remaining 0.5 km.
- Risk pointer If the tender said “data may be outdated; more expropriation may be needed,” the tribunal had to decide whether that warning moved the site access risk to the contractor or still left it with the Employer.
2) Permits & Design — who fixes clashes with city utilities?
In simple terms: Some municipalities refused permits because the project design clashed with existing drainage/sewer rules. The question was: Who must solve such clashes and obtain the permits?
- What mattered If MOPC controlled the reference design and was responsible for permanent‑works permits, then permit refusals tied to design conflicts tended to be an Employer problem to solve.
- Practical example If a bus‑lane drainage detail doesn’t fit the city’s main sewer, the Employer updates the design or coordinates with the utility so the permit can be issued.
3) Contractual Risk Allocation — what risks did each side sign up for?
In simple terms: The tribunal read the contract and tender together to see who carried which risks (ground conditions, expropriation delays, permit refusals).
- Paraguay’s view The bidding documents warned about old land data and extra expropriations; therefore, the contractor accepted the risk of barriers to access.
- Mota‑Engil’s view Core responsibilities (site possession and permits) stayed with the Employer as project owner; warnings did not transfer those core duties.
- Takeaway Clear drafting about who handles access and permits avoids disputes. If warnings exist, tie them to specific price/time mechanisms (e.g., EOT or price adjustment).
4) Multi‑Tier Dispute Clause — did the parties waive the “steps”?
In simple terms: The contract had steps before arbitration (e.g., a board or amicable phase). The State said the contractor skipped steps; the contractor said later agreements (MoUs) let them go straight to arbitration.
- What mattered If the 2019 agreements meant “go direct to arbitration,” the tribunal could treat the pre‑steps as waived. Many tribunals apply good‑faith and “favor contractus” — keep party agreements effective.
- Tip If you deviate from the multi‑tier ladder, record that in a signed MoU or addendum so admissibility fights don’t derail the case.
5) Termination & Bonds — renewal duties and interim protection
In simple terms: MOPC terminated saying the contractor failed to renew the performance and advance‑payment guarantees. The contractor said the project was stalled by the State’s own breaches. During the case, the tribunal ordered the State not to cash the bonds and to use special “arbitration guarantees” instead.
- What mattered Under FIDIC‑style contracts, timely bond renewal is a fundamental contractor duty. But tribunals can use interim measures to stop unfair cashing while the dispute is decided.
- Non‑compliance If a party ignores provisional orders (e.g., drawing on bonds anyway), tribunals can impose cost/other sanctions.
- Site tip Keep a live Guarantees Register (Performance, Advance, Retention) with renewal alarms and replacement instruments ready.
Related Reading (from Wisdom Waves Hub)
Watch (optional — from your playlist)
Arguments by Each Side — PCA Case No. 2020‑14
Mota‑Engil’s Claims (in simple words)
1) No timely site access
Mota‑Engil says the State did not hand over work fronts on time. Land was not expropriated/cleared, so crews could not enter many zones. Works stalled by late 2018.
What this means
- The Employer should progressively deliver possession so the contractor keeps working.
- Delays in expropriation/rights‑of‑way block progress and create idle costs.
2) Permits were missing
Mota‑Engil argues MOPC failed to obtain key municipal permits (even where physical access existed). Design under MOPC’s control conflicted with city drainage rules, leading to permit refusals.
Plain take
- If design clashes with utility standards, the project owner should resolve it and secure the permit.
- No permit = legally barred from building, even if the site is open.
3) Losses & payment
Mota‑Engil seeks payment for certified work, idle costs and other damage. Public reports note initial claims around USD 18m, later around USD 25m.
Relief asked
- Pay for work done + retention release where due.
- Compensate direct losses caused by access/permit failures.
4) Urgent protection on bonds
When MOPC moved to terminate and call the guarantees, Mota‑Engil asked the tribunal to stop any calls during the case. The tribunal issued provisional measures in its favour.
Why urgent?
- Cashing the performance/APG could cause irreparable harm and pre‑judge the dispute.
- Provisional orders required not calling the bonds and using “arbitration guarantees”.
Paraguay (MOPC)’s Defence (in simple words)
1) Procedural objection
MOPC says the arbitration was premature: the contract required pre‑arbitration steps (amicable path/committee). Those steps were not taken, so the case should be inadmissible.
Key question
- Did later MoUs effectively waive those steps and allow direct arbitration?
2) Risks were on the contractor
The State cites tender warnings: land data might be outdated and extra expropriations could be needed. In their view, Mota‑Engil priced/accepted these risks.
On permits
- MOPC argues municipal denials were due to contractor shortcomings (e.g., traffic detours).
3) Delays & abandonment
MOPC maintains the contractor fell behind and abandoned works in late 2018. Therefore consequences should fall on the contractor.
Effect
- Losses flow from the contractor’s own delay/abandonment, so damages should be reduced or rejected.
4) Termination & calling bonds
MOPC says termination was lawful because the contractor failed to renew the performance and advance‑payment guarantees. After termination, it considered calling the bonds proper.
Bottom line
- Bond renewal is a strict, time‑critical obligation; failure justifies termination and calls.
Related Reading (from Wisdom Waves Hub)
Watch (optional)
Key Sources (highlighted)
Mota‑Engil (Paraguay) v. MOPC — Consolidated Overview
Background & Timeline (in simple words)
Paraguay planned a rapid bus system (“Metrobus”). In 2016, MOPC hired Mota‑Engil to build key sections. Work slowed because many areas weren’t handed over and some permits didn’t issue. Two MoUs in 2019 failed to restart the project. MOPC terminated in Feb 2020; arbitration had been filed in Dec 2019.
Key Issues in Dispute — what the fight was about
- Site access & expropriation: Was MOPC obliged to progressively hand over work fronts and finish rights‑of‑way, or did the contractor bear the access risk?
- Permits & design: If municipal permits were refused due to design clashes (e.g., drainage), was that MOPC’s responsibility to fix?
- Risk allocation: Did tender warnings shift risks (outdated land data, extra expropriations) to the contractor, or did core duties remain with the Employer?
- Multi‑tier clause: Did the 2019 MoU let the parties go straight to arbitration, waiving pre‑steps?
- Termination & bonds: Was termination valid for non‑renewal of guarantees, and what was the legal effect of the tribunal’s interim orders on bond calls?
Arguments by Each Side — side‑by‑side
Claimant: Mota‑Engil
- No timely access: State didn’t hand over stretches; crews couldn’t enter many zones; works stalled by late 2018.
- Permits missing: Municipal permits weren’t obtained; design under MOPC clashed with city standards.
- Losses: Payment for work done + direct costs; public reports mention claims ≈ USD 18m → ≈ USD 25m.
- Urgent relief: Asked tribunal to bar bond calls during the case; provisional measures granted.
Respondent: Paraguay (MOPC)
- Procedural objection: Multi‑tier steps not followed → inadmissible.
- Risk on contractor: Tender warned of outdated land data/extra expropriation; permits denied due to contractor failings (e.g., detours).
- Delays/abandonment: Contractor fell behind and abandoned works.
- Termination & bonds: Non‑renewal of guarantees justified termination and calling bonds.
Arbitral Tribunal’s Findings — what the award decided
- Admissibility: Case could proceed. Parties had moved away from the strict ladder and the 2019 MoU allowed direct arbitration (favor contractus under Paraguayan law).
- MOPC breaches: Employer had to progressively grant access and obtain permanent‑works permits; design clashes were MOPC’s to fix.
- Contractor breach: Mota‑Engil’s failure to renew guarantees gave MOPC a valid ground to terminate (early 2020).
- Delays share: Of 691 days claimed, ≈ 258 days (~37%) attributable to the State; remainder to contractor/others (affects quantum).
- Interim orders: Bonds not to be called; non‑compliance could be sanctioned in costs. One‑time substitute “arbitration guarantee” required.
Mini‑Checklist (FIDIC examples)
Related Reading (Wisdom Waves Hub)
Watch (one‑time — no duplicates)
Key Sources (highlighted)
Support for admissibility, access/permits duty, bond orders, and 37% delay share.
Final Award & Compensation — PCA Case No. 2020‑14
Plain‑English Summary
The tribunal issued its final decision on 8 December 2023. It confirmed that the case could proceed and then split responsibility between the parties. Because both sides breached some duties, the award ordered reciprocal payments. However, the State’s payments to Mota‑Engil were much larger, mainly for the wrongful bond call, unpaid work, and direct costs caused by termination. A separate, smaller sum was ordered against Mota‑Engil to cover unremedied defects and a reporting fine.
Headlines
Jurisdiction confirmed
- The tribunal rejected Paraguay’s admissibility objections and confirmed it had jurisdiction to decide the case.
- Reasoning relied on good‑faith interpretation and parties’ 2019 MoU allowing direct arbitration.
Reciprocal payments
- Mota‑Engil → State (PYG): ~625,081,537.30 for unremedied defects + 19,500,000 in fines; interest at BCP facility rate +1% from award date until payment.
- State → Mota‑Engil (EUR, USD): Major items below; interest and costs added.
Breakdown of Amounts Awarded
Note: The tribunal did not award lost profits (lucro cesante); focus was on proven, direct losses and withheld amounts.
Costs & Sanctions
- Legal fees: State to reimburse 40% of Mota‑Engil’s legal fees (~€591,443 + $4,157 expenses).
- PCA & tribunal costs: State to reimburse 40% of PCA costs (~$258,776 advanced by Mota‑Engil).
- Interest on costs: Fed primary +3% from award date.
- Sanction uplift: The 40% reflected an extra ~10% penalty for the State’s willful non‑compliance with provisional orders (bond call).
Practical tip: Record interim‑order compliance in a Guarantees Register (renewals, replacements, calls) to avoid cost sanctions.
Net Effect & Public Figures
After offsetting the small PYG amounts owed by Mota‑Engil, the State’s liability remained much larger. Public summaries in Dec 2023 estimated roughly $13m in damages plus around $2.4m in accrued interest and about $2m in legal/arbitration costs — totaling about $16–17m due to Mota‑Engil (depending on interest accrual dates and exchange effects).
Related Reading (Wisdom Waves Hub)
Key Sources (highlighted)
Support for reciprocal payments, component amounts, interest bases, and cost sanctions.
Aftermath & Reactions — PCA Case No. 2020‑14
Public & Official Reactions (Dec 2023)
Public debate in Paraguay focused on the State’s defeat and the cost to the treasury. On 15 December 2023, Procurador General Marco Aurelio González held a press conference to disclose the award and to critique choices that increased exposure. He highlighted the prior decision to execute the performance bond despite the tribunal’s order—calling it a “negligent act” that triggered sanctions and repayment with interest. Officials lamented that about USD $5 million was immediately lost by calling the bond and argued those funds—and the costs of litigation—could have been better used to advance the project.
Seat‑Court Challenge & Partial Annulment (Oct 2024)
Because the seat was Asunción, the award was subject to local review. The Procurador announced in Dec 2023 that a recours de nullité (annulment) would be filed. By October 2024, the Court of Appeal (Third Chamber) partially annulled the award. According to official statements, the court voided the main payment orders against Paraguay and left standing only two items: (1) Mota‑Engil’s obligation to pay roughly Gs. 600 million (defects + fines), and (2) Paraguay’s obligation to return about USD $2.6 million for withheld payments. Reports note this saved the State over $16 million in liabilities.
Follow‑On Case at ICSID (2025)
After losing most of the award through annulment, Mota‑Engil pursued investment‑treaty arbitration. In July 2025, the company submitted a case at ICSID, and by 28 August 2025 Paraguayan media reported that an ICSID arbitration had been registered, reportedly under the Portugal–Paraguay BIT. The ICSID case is pending as of late 2025.
Lessons Observed by Commentators (2024)
- Multi‑tier pragmatism: Tribunals may honor later party agreements and conduct over rigid step‑ladder formalism (favor contractus).
- Risk clarity matters: If a State entity takes on site‑access and permitting duties, it will likely bear consequences if those fail.
- Interim‑order compliance: Disobeying provisional measures can boomerang via costs and interest even without direct coercive power.
Note: This module intentionally has no video embeds to avoid duplication on pages where a single “Watch” block already exists.
