Mastering FIDIC Clause 15.4: Essential Guide to Contract Termination Settlements

General Overview

Clause 15.4 in the FIDIC Yellow Book 1999 outlines the procedures and obligations regarding payments after the termination of a contract. This clause becomes relevant when a contract is terminated, particularly under the provisions of Sub-Clause 15.2 [Termination by Employer]. It details the steps the Employer must take concerning financial settlements with the Contractor post-termination.

Key Components

  1. Employer’s Actions Post-Termination: The clause specifies actions the Employer may take after issuing a termination notice.
  2. Withholding Payments: The Employer has the right to withhold further payments until certain costs are established.
  3. Recovery of Losses and Damages: The Employer can recover any losses, damages, and extra costs incurred due to the termination, after accounting for any sums due to the Contractor.
  4. Final Settlement: Any balance remaining after recovering losses and extra costs must be paid to the Contractor.

Process Flow

  1. Activation of Clause: Triggered after a contract termination notice under Sub-Clause 15.2.
  2. Employer’s Initial Steps:
    • Proceed in accordance with Sub-Clause 2.5 [Employer’s Claims].
    • Withhold further payments to the Contractor temporarily.
  3. Establishment of Costs:
    • Determine costs of design, execution, completion, remedying defects, and damages for delay in completion.
    • Establish all other costs incurred by the Employer.
  4. Recovery of Losses:
    • Calculate and recover any losses and damages incurred by the Employer.
    • Deduct extra costs of completing the Works from the Contractor’s due sum.
  5. Final Payment:
    • After recovering losses and extra costs, pay any remaining balance to the Contractor.

Applicability

General Considerations


Clause 15.4 serves as a critical component in the FIDIC Yellow Book 1999, providing a clear framework for financial settlements post-contract termination. It balances the need to protect the Employer’s interests in recovering costs and losses with the Contractor’s right to receive any outstanding payments. This clause is essential for maintaining contractual integrity and financial fairness following the termination of a contract.

Diverse Interpretations of Clause 15.4: Payment after Termination

1. Purpose of Clause 15.4

2. Implications of Clause 15.4

3. Primary Aspects of Clause 15.4

4. Uses of Clause 15.4

5. Expert Opinion on Clause 15.4

Deciphering Clause 15.4: A Comprehensive Guide to Its Interplay with Key Contractual Provisions

1. Interaction with Sub-Clause 15.2 [Termination by Employer]

2. Interaction with Sub-Clause 2.5 [Employer’s Claims]

3. Interaction with Clause 20 [Claims, Disputes and Arbitration]

4. Interaction with Clause 16.3 [Cessation of Work and Removal of Contractor’s Equipment]

Main Points to Keep in Mind When Employing Clause 15.4: Payment after Termination

  1. Triggering Event: Recognize that Clause 15.4 is activated following a contract termination, specifically under the provisions of Sub-Clause 15.2 [Termination by Employer].
  2. Employer’s Right to Withhold Payments: Understand that the Employer may withhold further payments to the Contractor until the costs related to the termination are fully established.
  3. Cost Assessment: Be aware that the Employer needs to assess various costs such as design, execution, completion, remedying of defects, and damages for delay in completion.
  4. Recovery of Losses and Damages: The Employer is entitled to recover any losses, damages, and extra costs incurred due to the termination, which should be factored into the final settlement.
  5. Final Settlement with the Contractor: After the recovery of losses and extra costs, the Employer must calculate and pay any remaining balance to the Contractor.
  6. Compliance with Sub-Clause 2.5 [Employer’s Claims]: Ensure that any claims by the Employer are processed in accordance with Sub-Clause 2.5.
  7. Dispute Resolution: Be prepared to resolve any disputes arising from the financial settlements under Clause 15.4 through the mechanisms provided in Clause 20 [Claims, Disputes and Arbitration].
  8. Documentation and Record-Keeping: Maintain thorough documentation and records of all calculations, communications, and transactions related to the termination and subsequent financial settlements.
  9. Fair and Transparent Process: Approach the application of Clause 15.4 with a commitment to fairness and transparency, ensuring that all actions are justifiable and in line with the contract terms.
  10. Legal and Financial Implications: Consider the legal and financial implications of actions taken under Clause 15.4, as they can significantly impact both parties’ rights and obligations.

Flowchart 1: Clause 15.4 Payment after Termination Process

Detailed Explanation:

  1. Start: The process begins with a contract termination under Sub-Clause 15.2.
  2. Employer Initiates Clause 15.4 Process: The Employer starts the Clause 15.4 procedures.
  3. Withhold Further Payments: The Employer withholds further payments to the Contractor.
  4. Assess Costs and Damages: The Employer assesses costs related to design, execution, completion, defects, and delay damages.
  5. Decision Point: Determine if recoverable costs are established.
    • If Yes, proceed to recover losses and damages from the Contractor.
    • If No, reassess and review the costs.
  6. Calculate Final Settlement: After recovery, calculate the final settlement amount.
  7. Pay Balance to Contractor: Pay any remaining balance to the Contractor.
  8. End: The Clause 15.4 process is completed.

Flowchart 2: Application of Clause 15.4 and Its Relationship to Other Clauses

Detailed Explanation:

  1. Start: The application of Clause 15.4 begins.
  2. Contract Termination: Linked to a termination notice under Sub-Clause 15.2.
  3. Employer Initiates Actions: The Employer starts actions as per Clause 15.4.
  4. Withholding of Payments: Payments to the Contractor are withheld.
  5. Interaction with Sub-Clause 2.5: The Employer’s claims are addressed as per Sub-Clause 2.5.
  6. Assessment of Costs and Damages: Costs related to the termination are assessed.
  7. Decision Point: Determine if costs and damages can be recovered.
    • If Yes, recover costs from the Contractor.
    • If No, reassess and review the costs.
  8. Final Settlement Calculation: Calculate the final settlement amount.
  9. Payment of Balance to Contractor: Pay any remaining balance to the Contractor.
  10. End: The application of Clause 15.4 concludes.

Structured Checklists

1. Checklist for Proficient Execution and Deployment of Clause 15.4

StepAction ItemDetailsResponsible Party
1Confirm TerminationVerify contract termination under Sub-Clause 15.2Employer
2Initiate Clause 15.4Start the Clause 15.4 processEmployer
3Withhold PaymentsTemporarily withhold further payments to the ContractorEmployer
4Assess CostsDetermine costs related to terminationEmployer
5Establish Recoverable CostsDecide if costs and damages are recoverableEmployer
6Recover CostsIf recoverable, proceed to recover from the ContractorEmployer
7Calculate Final SettlementDetermine the final amount due to the ContractorEmployer
8Make PaymentPay the remaining balance to the ContractorEmployer
9Document ProcessKeep detailed records of all steps and decisionsEmployer

2. Checklist for Applying and Overseeing Clause 15.4

StepAction ItemDetailsResponsible Party
1Verify Contract TerminationEnsure termination aligns with Sub-Clause 15.2Employer
2Activate Clause 15.4Begin the Clause 15.4 procedureEmployer
3Hold PaymentsWithhold further payments as necessaryEmployer
4Cost EvaluationAssess all relevant costs and damagesEmployer
5Decision on CostsDetermine recoverability of costsEmployer
6Recover ExpensesRetrieve costs from the Contractor, if applicableEmployer
7Finalize SettlementCalculate and finalize the settlement amountEmployer
8Execute PaymentDisburse final payment to the ContractorEmployer
9Maintain RecordsDocument all actions and calculationsEmployer

3. Checklist for Guiding and Monitoring Execution of Clause 15.4

StepAction ItemDetailsResponsible Party
1Confirm Termination BasisEnsure termination is based on Sub-Clause 15.2Employer
2Implement Clause 15.4Start procedures under Clause 15.4Employer
3Payment SuspensionTemporarily stop further paymentsEmployer
4Analyze Termination CostsReview and assess costs due to terminationEmployer
5Determine Cost RecoveryDecide on the recoverability of costsEmployer
6Cost Recovery ProcessInitiate recovery of costs from the ContractorEmployer
7Settlement CalculationCompute the final settlement amountEmployer
8Disburse Final AmountPay any balance owed to the ContractorEmployer
9DocumentationKeep comprehensive records of the entire processEmployer
Exit mobile version