NEC3 vs NEC4: Option A vs Option B 💼
Option A uses a lump-sum contract based on a Contractor-prepared Activity Schedule. Payments are tied to completed activities, not quantities. Perfect for clearly scoped projects. 💰
📋 Pricing Model
Fixed prices per activity. Less flexibility for changes.
🔁 Compensation Events
Handled through adjustment of Activity Schedule.
🕒 Payment Logic
Paid on completion of each activity – clean milestone-based approach.
Option B is based on a client-provided Bill of Quantities (BoQ). It’s ideal where quantity risk lies with the Employer. Useful for re-measurable works. 🧮
📋 Pricing Model
Measured quantities × rates. Greater flexibility for varying site conditions.
🔁 Compensation Events
BoQ is updated; event rates can be derived from the BoQ or new quotations.
🕒 Payment Logic
Paid for actual work done (quantities installed × agreed rates).
Terminology & Structural Changes in NEC4 📜
NEC4 refined the NEC3 framework with cleaner, clearer, and more consistent language. Below are key terminology upgrades and structural refinements:
- 🔄 “Employer” → “Client” (used consistently across all NEC4 contracts)
- 📘 “Works Information” → “Scope” (simpler, more intuitive)
- ⚠️ “Risk Register” → “Early Warning Register” (more proactive risk handling)
- 🧍 Gender-neutral language adopted throughout
- 🧩 New contract forms introduced like Design, Build and Operate
Clause References and Practical Implications 🧐
NEC3: “Employer provides Works Information”
NEC4: “Client provides the Scope”
Introduced clearer definitions, including “Defined Cost” and “Assessment Interval”
Compensation event assessments more formula-driven in NEC4
Clause 11 – PWDD & “The Prices” Explained 📖
Price for Work Done to Date (PWDD) in Option A means the sum of completed activities – no payment for partial progress. Each activity must be fully completed without defects delaying next steps.
🔐 Lump Sum Logic
Activity 5 – “Install Roof” priced at $80,000. Contractor receives full amount only once roof is done and defect-free.
📉 No Part Payments
Even 90% progress earns nothing until the activity hits 100% completion.
🧾 The Prices
Total of all activity prices = The Prices. Adjusted via compensation events if scope changes.
PWDD in Option B is based on measured quantities × rates in the BoQ. Partial payments are allowed as quantities progress. Lump sums are also paid pro-rata.
📊 Rate-Based Logic
Concrete item in BoQ: 200 m³ × $200/m³. If 100 m³ done → Payment = $20,000.
💵 Proportional Payment
Partial completion = proportional payment. Supports better cash flow during long projects.
📄 The Prices
Sum of BoQ rates × estimated quantities. Subject to remeasurement.
Other Definitions – Clause 11 🔍
Both Option A and Option B in NEC3 and NEC4 share common definitions in Clause 11, many of which were retained with slight refinements in NEC4. Below are some of the most relevant shared terms:
🧾 What is “Defined Cost”?
In both Options A & B, Defined Cost helps calculate changes via the SSCC (Shorter Schedule of Cost Components).
✨ NEC4 Upgrade
NEC4 clarified that quote preparation costs can be included in Defined Cost.
Also simplified cost component schedules.
Clause 50 – Payment Assessments & Timing 💰
How Payment Works in Option A: Contractor is paid for completed activities only. Payments are “lumpy”: each interim payment is made once an activity is fully finished (not partially).
Sum of Completed Activities
Clause 53 introduces a final account and certificate process after project completion—this was missing in NEC3. Payment only for finished activities means contractors may face delayed cash flow, but the Client gets strong cost control.
How Payment Works in Option B: Contractor is paid monthly (or as stated) for measured quantities of work completed. Payment flows smoothly as work progresses.
Measured Qty × Rate
+ Lump Sums Pro-Rata
Final account process (Clause 53): Ensures all parties agree on the final sum and closes out disputes. Payment is proportional to progress—better for contractor cash flow, but the Client takes quantity risk if actuals exceed BoQ.
Clause 60 – Compensation Events (Risk, Changes & Relief) 🔀
If the Scope changes, unforeseen conditions arise, or the Client/PM causes delay, the Contractor may be compensated for time/money.
(within 8 weeks)
Time and/or Money
- New CE: Cost of Quotes i If the Project Manager asks for a quote for a proposed change (Clause 65), but then cancels, the Contractor is paid for the cost/time of quoting (new in NEC4).
- Custom CEs in Contract Data i NEC4 lets parties pre-list extra compensation events (like “third-party delay” or “archaeology”) in Contract Data—no need for amendments.
- Time Bar (8 weeks): Contractor must notify within 8 weeks or lose entitlement (same as NEC3).
- Deemed Acceptance: If PM does not respond in time, event is accepted by default (Clause 61.4).
- Changes to the Scope (PM instruction)
- Unforeseen physical conditions
- Client/PM-caused delays
- Exceptional weather, artifacts, legal changes, etc.
- But: No CEs for quantity overruns or errors in Activity Schedule—Contractor takes the risk for activity pricing!
Under BoQ, the Contractor is protected from extreme quantity risk and BoQ errors, since BoQ is Client’s document.
- 60.4: Significant difference between final and BoQ quantity for an item (impacts unit cost & exceeds 0.5% of Prices)
- 60.5: Quantity difference delays Completion/Key Date
- 60.6: BoQ mistakes (missing/erroneous items)
- 60.7: Discrepancy between BoQ & Scope/drawings
- Changes to the Scope
- Unforeseen conditions
- Delay/obstruction by Client or PM
- Legal, regulatory, or third-party issues
- Weather, artifacts, and more
- Change in quantity alone ≠ CE—unless it impacts cost/unit or causes delay
- CE for “mistakes” in BoQ, not in Scope
- Early warning still required: Notify events ASAP!
Clause 63 – Assessment of Compensation Events 🧮
NEC4: If a CE is due to a PM/Supervisor instruction, the dividing date is the communication date; otherwise, it’s the CE notification date.
Prices are not reduced unless the contract says so.
- Impact on time: Assessed as the extra time needed (using the Accepted Programme at dividing date).
- Impact on cost: Lump-sum increase to Prices, calculated using actual + forecast Defined Cost (plus Fee).
- NEC4 clarifies dividing datei Now spelled out: For PM/Supervisor instructions, it’s the instruction date; otherwise, the notification date. Ends confusion from NEC3.
- Principle: Contractor “no better, no worse off” (No Gain/No Loss).
📅
Actual Cost
(before)
+ Forecast Cost
(after)
Adjusted
- If CE adds/removes work with BoQ rates, use those rates for assessment (NEC4/NEC3 Clause 63.13+).
- If no suitable rate, build up a new rate/lump sum from Defined Cost + Fee.
- For work already done, assess as a lump sum at actual cost.
- PM/Contractor can agree ad hoc rates or lump sums (flexibility remains).
- NEC4 refined the wording and process, but basics are unchanged.
Use BoQ Rate × Qty
Build New Rate
(or agreed lump sum)
Contractor’s Cash Flow vs Employer’s Risk: Option A vs Option B 💱⚖️
(Activity Schedule – Lump Sum)
⏳ Less flexible cash flow for Contractor
- Best for clearly defined projects (e.g. office building with full design).
- Contractor bears risk for own activity pricing/quantities.
- Client’s cost is fixed (unless scope changes or CEs).
- Contractor gets paid on full completion of each activity – fewer but larger payments.
- Simpler admin (no regular measurement).
(Bill of Quantities – Remeasurement)
⚠️ Variable cost for Employer
- Suited for projects with uncertain or variable quantities (e.g. road, drainage, earthworks).
- Client carries risk of quantity increases or BoQ mistakes.
- Contractor is paid monthly for actual measured work – steady cash flow.
- BoQ needs to be accurate; discrepancies are CEs.
- More admin (monthly measurement, progress agreement).
Examples in Practice 🏗️🌉
- Activity Schedule: Site setup $50k, Foundations $120k, Superstructure $200k, Roof $80k, etc.
- Payment made only upon full completion of each activity.
- Extra works (e.g. a new room) = compensation event and new activity (price added).
- If actual quantities increase (e.g. more concrete in foundations), Contractor bears extra cost unless Scope changes or CE applies.
- Failure to update programme = up to 25% payment withheld (Clause 50.3).
- Client knows exact cost for each milestone (cash flow is predictable).
- Contractor finishes foundations → $120k paid. 90% done = $0 until 100% is reached.
- Unexpected client change (extra room) is a CE, paid as an added activity (e.g. +$20k).
- Contractor funds ongoing work until each chunk is 100% finished. Strong incentive to complete each stage efficiently!
- BoQ: Excavation 100,000 m³ @$10/m³; Rock breaking 5,000 m³ @$50/m³; 1mØ pipe 2,000 m @$300/m, etc.
- Monthly payment: Measured quantities × BoQ rates (e.g. 8,000 m³ excavated = $80k paid).
- Significant overrun (e.g. 110,000 m³ instead of 100,000) triggers CE to adjust rates (Clause 60.4) or grant time (60.5).
- Missing BoQ items but present in Scope = CE (Clause 60.6); Employer pays for required work not in BoQ.
- Client must actively manage and agree measurements each period (joint survey).
- Contractor is paid for exactly what’s done, month by month (better cash flow).
- Quantity overruns: paid at BoQ rate unless impact is extreme (then rate can be adjusted via CE).
- Scope rules: if BoQ undercounts work, CE claim corrects it—client pays for the true requirement.
- Client faces uncertain total outturn cost but pays only for real work delivered.
- System encourages transparency, collaboration, and fairness.
Key NEC4 Updates/Improvements over NEC3 🔧
Less legalese, more clarity!
No more “indefinite limbo” on payments!
Conclusion: Option A vs Option B Under NEC4
- Simple, milestone-based payment (each activity).
- Best for clear scope, predictable quantities.
- Strong price certainty for Client.
- Contractor manages activity/cost risk.
- Contractor’s cash flow can be less flexible (waits for activity completion).
- Low admin burden.
- Continuous, measured payments (per BoQ item completed).
- Suited to uncertain or variable quantities.
- Employer takes quantity risk; final price may vary.
- Contractor enjoys steady cash flow.
- Higher admin: regular measurement, more records.
🚧🏗️