Site icon Navigating Knowledge Across Domains

NEC4 DBO Payment: Service-Period Flow + Calculator

NEC4 DBO Payment

NEC4 DBO Payment

NEC4 DBO: How payment works during the Service Period 💸🛠️

If you’ve used NEC before, the DBO flavour flips a familiar switch: after the “build” bit, you’re paid for operating the asset. The money still flows by assessment dates and certificates—but the ingredients and tweaks are a little different. Let’s unpack it step by step, in plain English, with just enough detail to run a real contract.


1) The monthly rhythm: application ➜ assessment ➜ certificate ➜ invoice ➜ payment ⏱️

⚠️ No accepted plan yet? The SM retains ¼ of the Price for Service Provided to Date until the first plan is submitted for acceptance.


2) The core metric: Price for Service Provided to Date (PFSPTD) 🧮

PFSPTD is the heart of each assessment and is built differently for Part A and Part B of the Price List:

🔎 Defined Cost controls (Part B): keep proof of payments, accounts, and CE communications; SM may inspect.


3) The performance lever: Performance Table 🎯

During the Service Period, performance against the Operational Requirements can adjust payment:

There’s also a Part-B cost sharing check at the dates stated in the Performance Table:


4) Indexation: Price Adjustment Factor (PAF) 📈

Every amount due includes price adjustment:

ℹ️ The contract defines PAF using indices B (latest before base date) and L (latest before the assessment), mirroring the familiar NEC mechanism.


5) Currency and forecasting details 💱🔭


6) Corrections, interest & tax 🧾


7) The final assessment after the Service Period 🧮🏁

The SM assesses the final amount due and certifies a final payment no later than 13 weeks after the end of the Service Period (or after a termination certificate)—unless Contract Data states a different period. Invoices follow within one week, and payment is made by the later of one week after invoice and three weeks after the assessment date (or the periods in Contract Data). If the SM doesn’t do it in time, the Contractor may issue its own assessment; the contract then sets out challenge windows (W1/W2).

🇬🇧 If Y(UK)2 is used, UK statutory timings/“notified sum” rules overlay the above (payment becomes due on invoice or 14 days after assessment, whichever is later; final date typically 7 days after due date; “pay less” notices etc.).


8) Worked example (GBP) — one monthly assessment during the Service Period

Assumptions (for illustration):

i) Build the PFSPTD (Price for Service Provided to Date)

Part A (completed outputs)

Part B (Defined Cost forecast to next assessment + Fee)

PFSPTD = Part A + Part B = £340,000 + £168,000 = £508,000


ii) Apply performance adjustments (bonuses/abatements)

Net performance adjustment = £7,500 − £2,000 = +£5,500


iii) Part-B cost sharing (as per Performance Table dates)

Part-B sharing adjustment = +£3,500


iv) Price adjustment (indexation) via PAF

Total price adjustment this assessment = £2,040.00 + £1,001.95 = £3,041.95


v) Pull it together → Amount due this assessment (before any withholdings)

Start from PFSPTD and add the moving pieces:

Amount due (pre-withholdings) = £520,041.95


vi) Two quick scenarios you’ll actually see on jobs

(If the delta since last time was negative, you could see a “payment from Contractor to Client” month. Also note the usual UK due date / final date dance under Y(UK)2 when you invoice and when the money must clear.) 💬


vii) What to attach with the application (so it sails through) 📎


9) What usually trips teams up on live jobs—and how we handle it 🧰


10) Quick checklist ✅


NEC4 DBO · Service-Period Payment Assistant 💷

Live month-end helper

1) Contract & Cycle

Due date is the later of “invoice” or “assessment + offset”. Final date = Due + offset.

2) Price Adjustment (PAF) 📈

You can also just type the PAF directly.

PAF applies to Part A directly; Part B uses PAF/(1+PAF).

3) Part A — Completed Outputs (lump sums & measured) 🧰

Description Type Rate/Price Qty (this assessment) Line total
Part A subtotal£0.00
“Completed” excludes notified Defects that would delay others.

4) Part B — Forecast Defined Cost → next assessment + Fee 🧮

Category Cost (forecast)
Defined Cost subtotal£0.00
Fee (12%)£0.00
Part B subtotal£0.00

5) Performance Table 🎯 (bonus or abatement)

KPI / NoteAmount (+/-)
Net performance£0.00

Enter positive for bonus, negative for abatement.

6) Part-B Sharing 🤝

If PFSPTD(Part B) < “total of the Prices”, Contractor is paid the share; if greater, Contractor pays the share.

Waiting for inputs…

7) Result — Amount Due this Assessment 🧾

PFSPTD£0.00
+ Performance£0.00
+ Part-B sharing£0.00
+ Price adjustment (PAF)£0.00
= Amount due (pre-withholdings)£0.00
− 25% PFSPTD hold (if no accepted plan)£0.00
Amount certified (pre-VAT)£0.00
+ VAT£0.00
Invoice total (incl. VAT)£0.00
Heads-up: negative month → payment from Contractor to Client.

Payment Timeline ⏱️

Due = later of Invoice or Assessment+offset. Final = Due+offset.


  

Friendly note: This assistant helps you build the amount due each assessment. Always align with your Contract Data and agreed procedures.

Exit mobile version