Views in the last 30 days: 126
Estimated read time: 48 minute(s)
NEC4 ECC Option C vs Option D — Target Contract Payment & Cost Management
Understand Defined Cost, Disallowed Cost, Price for Work Done to Date (PWDD), and how target Prices drive gain/pain share.
Defined Cost
Actual allowable costs (per Schedule of Cost Components) excluding disallowed items, plus the Contractor’s Fee.
Disallowed Cost
Not payable: unsupported costs, erroneous payments, costs due to failing procedures (e.g., no early warning), unused materials beyond reasonable wastage, post-Completion defect correction, etc.
PWDD (Amount Due)
At each assessment: forecast total Defined Cost paid before the next date (+) Fee, less disallowed items; deductions like retention/advances apply separately.
Aspect | Option C | Option D |
---|---|---|
How “Prices” (Target) are set | Activity Schedule (lump sums per activity) | Bill of Quantities (lump sums + rates × quantities) |
Monthly payment basis | Defined Cost (+) Fee, with forecast to the next assessment date (not activity/BOQ completion) | |
Role of Activity Schedule/BOQ during delivery | Baseline for the original target; generally not revised during the project | |
Risk & incentive | Target cost incentivization; final gain/pain share at Completion vs final Prices | |
Records & audit | Contractor keeps and allows inspection of accounts and records of Defined Cost | |
Multi-currency handling | Foreign currency costs converted to contract currency for fee and share calculations | |
Progressive fee payment | Fee paid as costs are incurred via PWDD | |
Final account | Prepared after the Defects Certificate; includes final share adjustment (gain/pain) |
PWDD Estimator (Defined Cost + Fee)
Read the full explanation (original detailed text)
Comparison of NEC4 ECC Option C vs Option D (Target Contracts)
Payment and Cost Management Mechanisms
Defined Cost and Disallowed Cost: Both Option C and Option D are target cost contracts where the Contractor is reimbursed for actual costs (Defined Cost) plus a fee, within a target price. Under these options, Defined Cost is defined as “the cost of the components in the Schedule of Cost Components less Disallowed Cost”. Disallowed Cost refers to specific categories of cost that are not payable by the Client – for example, costs not supported by the Contractor’s accounts, payments that should not have been made to Subcontractors, or costs incurred due to the Contractor’s failure to follow contract procedures (such as not giving an early warning). It also includes the cost of correcting Defects after Completion, the cost of Plant and Materials not used (beyond reasonable wastage) unless resulting from a scope change, and resources not used or not removed when instructed. In essence, any cost falling into these disallowed categories is excluded from Defined Cost, meaning the Contractor cannot claim it as part of the reimbursable cost. All other costs are deemed included in the Defined Cost, and any cost not covered by Defined Cost is treated as included in the Contractor’s Fee (the fee being the Contractor’s overhead and profit allowance). This ensures that the Contractor only recovers legitimate, allowable costs, and bears the expense of disallowed costs (which in turn affects the Contractor’s share of any overrun, as discussed later).
“Prices” (Target Cost) and Price for Work Done to Date: In NEC terminology, the Prices represent the target price breakdown. Under Option C, the Prices are “the lump sum prices for each of the activities on the Activity Schedule unless later changed”. Under Option D, the Prices comprise “the lump sums and the amounts obtained by multiplying the rates by the quantities for the items in the Bill of Quantities”. In both cases, the sum of the Prices at contract award is the initial Target Cost for the project (this gets adjusted by implemented compensation events to form the current total of the Prices). It’s important to note that under Options C and D, this target cost is an estimate/baseline – not a fixed payable amount – against which actual performance is measured. Meanwhile, the Price for Work Done to Date (PWDD) is the running total that the Contractor is paid as the work progresses. Under Options C and D, PWDD is defined as “the total Defined Cost which the Project Manager forecasts will have been paid by the Contractor before the next assessment date plus the Fee”. In practice, this means at each payment assessment (e.g. monthly), the Contractor is paid actual costs incurred to date plus the agreed fee, with a forecast element to the next period. The Project Manager may forecast costs up to the next assessment date to ensure the Contractor is cash-flow neutral. Unlike fixed-price Options A or B, payment is not tied to completing priced activities or BOQ items; it is based on actual expenditure. For example, under Option C “the Contractor can claim each period the Defined Cost…that they have incurred up to the date of the application plus the Fee… including a forecast of Defined Cost up until the next application date” (with any disallowed costs subtracted). The same cost-reimbursable mechanism applies under Option D. This ensures the Contractor’s cash flow reflects actual cost reality. The Activity Schedule or Bill of Quantities in target contracts is not used for monthly payment calculations (except perhaps as a reference), in contrast to Option A/B where completed activities or quantities determine payments. In fact, under Option C “there is no mechanism (or need) to revise the Activity Schedule…during the life of the project as its only purpose is to ascertain the original target price”, and under Option D “there is no mechanism (or need) to revise the Bill of Quantities…its only purpose is to ascertain the original target price”. Payment is purely Defined Cost + Fee, subject to audit of records (clause 52.2 requires the Contractor to keep and allow inspection of accounts and records of Defined Cost).
Calculation of PWDD and Adjustments: The Project Manager’s assessment of the amount due (clause 50) under Options C/D will include: the Price for Work Done to Date (actual Defined Cost to date + Fee) plus any other amounts to be paid (e.g. for compensation events, materials on site if applicable, etc.), minus any applicable deductions (such as retention under X16 or advance payment recoveries). Since PWDD already factors in the fee, the Contractor’s profit element is being paid as the costs are incurred. Notably, multi-currency contracts are handled by converting foreign currency cost to the contract currency for fee and share calculations. Also, the Contractor must notify the Project Manager when a portion of Defined Cost is finalized and provide records; the Project Manager then has a set period (e.g. 14 weeks) to accept or contest that cost assessment. If the PM does not respond in time, the Contractor’s assessment is treated as accepted. These mechanisms ensure transparency and agreement on costs as the project proceeds.
Summary of Payment Mechanism: In both Option C and D, the Contractor is reimbursed for allowable Defined Cost expenditures plus Fee, meaning the financial risk of cost overrun is shared rather than solely on the Contractor. The target Prices (Activity Schedule or BOQ total) serve as a baseline for incentivization, not as a cap on payment. Payment certificates will essentially cover actual costs incurred (less disallowed) plus the fee percentage. At Completion, a final account (clause 53) is prepared, and the final amount due is assessed, including any final Contractor’s share adjustment for underrun or overrun. The final payment process (clause 53) follows the issuing of the Defects Certificate, and if the PM fails to issue a final certificate, the Contractor can issue their assessment (though this process applies generally to all options). Under Options C/D, that final assessment will incorporate the pain/gain share as discussed below.
Risk & Incentive Structures in NEC4 Target Contracts (Options C/D)
How Target Cost adjusts, how pain/gain share is calculated (Clause 54), and why banding shapes incentives.
Target Cost (Total of the Prices)
Adjusted by implemented compensation events so incentives remain fair as scope/risks change.
Contractor’s Share (Clause 54)
Saving or overrun is split by pre-agreed share ranges. Paid as bonus (gain) or deducted (pain).
Value Engineering (Clause 63.13)
Accepted Contractor proposals can reduce actual cost without lowering the target—sharing the benefit via pain/gain.
Pain/Gain Share Calculator
Read the full detailed explanation (original text)
Risk and Incentive Structures (Target Cost, Pain/Gain Share)
Target Cost and Adjustments: Options C and D establish a Target Cost (the “total of the Prices”) at the outset, which is subject to adjustment for compensation events. This target is a mechanism to incentivize cost control: if the project is completed below target, savings are shared; if above target, the excess is also shared (the Contractor bears some of the pain). The target is managed dynamically – whenever a compensation event (a change or other risk event defined in clause 60) occurs and is implemented, the target cost is adjusted by the assessed cost of that change. In other words, the “total of the Prices” is increased or decreased for scope changes, client instructions, risk allowances realized, etc., ensuring the target remains fair given changed circumstances. Both Option C and D include a clause (in the 63 series) to encourage value engineering proposals by the Contractor: Clause 63.13 provides that if a change to the Scope proposed by the Contractor (under clause 16.1) is accepted and results in a reduced cost, the Prices (target) are not reduced to reflect that saving. This means the target cost stays at the higher level even though the actual Defined Cost may drop – effectively allowing the Contractor (and Client) to share in the benefit of the cost-saving idea. By contrast, in fixed-price Options A/B, an accepted Contractor proposal leads to a partial price reduction via a value engineering percentage (clause 63.12). Under Options C/D, all cost savings from Contractor-initiated changes are realized through the pain/gain share rather than an upfront reduction of the target, providing a strong incentive for the Contractor to identify efficiencies.
Contractor’s Share (Pain/Gain Mechanism): The heart of the incentive structure is Clause 54 (The Contractor’s Share). At completion, the actual cost (Price for Work Done to Date) is compared to the target cost (total of the Prices). If the actual cost is less than the target, a cost saving (underspend) has occurred; if actual exceeds target, a cost overrun has occurred. These savings or overruns are shared between the parties according to pre-agreed ratios (the Contractor’s share percentage) set out in Contract Data part 1. The contract allows for share ranges – bands of cost variance with different sharing proportions – or a single fixed share percentage. Clause 54.1 details the calculation: “The difference between the total of the Prices and the Price for Work Done to Date is divided into increments falling within each of the share ranges… The Contractor’s share equals the sum of the products of each increment and the corresponding Contractor’s share percentage.” In simpler terms, if multiple banded percentages are used (e.g. 50/50 share up to 10% saving, 30/70 beyond that, etc.), the formula applies each band to the portion of savings/overrun in that range. Clause 54.2 then states: if the Price for Work Done to Date is less than the total of the Prices, the Contractor is paid its share of the saving; if the Price for Work Done to Date is greater, the Contractor pays (i.e. the amount due is reduced by) its share of the excess. In practice under Option C/D, the Contractor’s share on a saving means an additional payment at completion (a gain share bonus), whereas for an overrun the final payment is reduced (the Contractor absorbs some pain). The timing is addressed by 54.3 and 54.4: a preliminary assessment of Contractor’s share is made at Completion (using forecasts of final cost) and included in the amount due at Completion, and a final assessment is made once final costs are known (at the end of the defects period) to adjust to actual figures. This ensures cashflow isn’t unduly delayed and the share is trued up when all costs are accounted for.
Risk Sharing: Through the above mechanism, cost overruns are effectively shared between Client and Contractor, limiting the Contractor’s downside risk compared to a lump-sum contract. Conversely, cost savings are shared, so the Client benefits from lower costs while the Contractor is rewarded. The exact percentages define the incentive strength. For example, a 50/50 share means both parties equally split any deviation; a 30/70 (Contractor/Client) on savings means the Contractor only keeps 30% of savings, etc. Often banded arrangements are used – e.g. the Contractor might get a higher share of savings up to a certain point to encourage modest savings, but if costs greatly underrun (perhaps due to scope reduction) the share might taper. Similarly, for large overruns, the Contractor’s pain share might increase (so that the Contractor has a strong incentive to avoid major overruns). An example given in industry guidance: “90–110% of target may be 50% Contractor share, anything under 90% target the Contractor keeps 25%, anything over 110% Contractor pays 75%”. This banding incentivizes staying close to the target and discourages extreme under-spending (which could imply cutting corners) or over-spending. The Contract Data will list the share ranges and percentages applicable (clause 54 references “the share ranges” stated in Contract Data).
Cost Forecasting and Transparency: Options C and D also include provisions to manage the target proactively. Clause 20.3 requires the Contractor to prepare and submit forecasts of the total Defined Cost for the whole works at regular intervals (specified in Contract Data) from the start until Completion. This means throughout the project, the Contractor and Project Manager review the estimated final cost versus the target. This early warning mechanism for cost helps identify potential overruns or savings trends. It allows the parties to take mitigating actions if the forecast shows a likely overrun, or to acknowledge savings. Essentially, it keeps the “pain/gain” picture transparent during execution, not just at the end. Clause 20.2 also has the Contractor advise on practical implications of design and subcontracting, fostering collaboration to meet the target.
Risk Contingencies: In target contracts, the Prices may include risk allowances (Contractor’s risk contingency) for certain uncertainties. If those risks do not materialize, the cost will come in lower and the Contractor benefits via the share. If they do materialize (but are not compensation events), the Contractor will use that contingency and possibly overrun if insufficient – again sharing the excess cost. In contrast, defined compensation events (events for which the Client bears risk under the contract, such as changes or certain unforeseeable conditions) will adjust the target so the Contractor isn’t penalized for Client risks. Thus, Options C and D create a balanced risk profile: the Client and Contractor both have an interest in controlling costs and avoiding waste. The Contractor does not simply get paid for everything regardless (as in pure cost-reimbursable Option E) – they will lose profit if inefficient – and the Client isn’t rigidly holding a fixed price – they will pay a share of overruns but also get savings back if costs are lower.
Monitoring Defined Cost and Audits: Both options rely on open-book accounting. Clause 52.2/52.3 mandate that the Contractor keep full records of Defined Cost (invoices, timesheets, purchase orders, etc.) and allow the Project Manager or Supervisor to inspect them at any time. This transparency is crucial since payments are based on costs. The Project Manager will closely monitor what constitutes Defined Cost vs Disallowed Cost. The contract explicitly makes certain kinds of costs disallowed (as described above) to protect the Client from paying for Contractor mistakes or inefficiencies. For instance, if the Contractor fails to follow an agreed procurement procedure or neglects to give an early warning of a risk that then inflates cost, those extra costs can be disallowed. This places a degree of risk back on the Contractor to manage the project professionally.
Summary of Incentives: In summary, Options C and D provide a “gain/pain share” model: the Contractor has the upside of extra profit for beating the target and the downside of reduced profit (or even loss on some costs) for exceeding the target. The Client gains cost certainty up to a point and an active partner in value engineering, while still ultimately paying actual costs plus a bonus or minus a deduction. The alignment of interests tends to foster a more collaborative approach to cost management, consistent with NEC’s ethos of mutual trust and cooperation (clause 10.2).
Usage Scenarios: When to Choose NEC4 Option C vs Option D
Use the decision helper to see which option fits your project context, then skim real-world use cases.
Option C – Activity Schedule
Great where the Contractor defines logical work packages (foundations, superstructure, MEP) and exact quantities aren’t the focus. Common in building and design-and-build jobs; simpler admin with no remeasurement routine.
Option D – Bill of Quantities
Ideal for civil & infrastructure where quantities drive cost (excavation, utilities, pavements) and a measurement standard is desired. Client/consultant provides the BoQ; rates × quantities set the target baseline.
Read the full detailed explanation (original text)
Usage Scenarios and When Each Option is Appropriate
Both Options C and D are suited for projects where price certainty is difficult to achieve at the outset and the Client wants to incentivize the Contractor to control costs. Typical scenarios include projects with incomplete design, complex or unpredictable construction elements, or tight collaboration requirements (e.g. alliancing and shared risk environments). Instead of a pure lump sum with high risk premiums, a target contract allows a fair risk share and flexibility to adapt to change.
Option C – Target Contract with Activity Schedule: Option C is often chosen when the scope can be broken down into discrete activities and the Contractor is in the best position to estimate and structure the pricing of those activities. The Contractor prepares the Activity Schedule during tender, listing logical work packages or milestones with a lump-sum price for each. The sum of these is the tendered target cost. Use cases: Option C is favored where the Contractor’s input in defining the work breakdown is desired and where exact quantities are not the focus. For example, building works or engineering projects where the effort is better estimated as lump tasks (foundations, superstructure, MEP installation, etc.) rather than measured item by item. It works well when the level of design/detail is moderate – not so detailed to have a full BoQ, but enough to identify major activities. It’s also common in design-and-build contracts where the Contractor will both design and construct – an Activity Schedule gives flexibility to price work that isn’t fully detailed yet. The Activity Schedule approach is simpler administratively: it doesn’t require formal measurement rules or re-measure during the project. The focus is on cost management via Defined Cost records, not tracking BoQ line items. Option C is appropriate when the Contractor’s pricing of activities is mainly for establishing the target, and where the Client is comfortable that any changes will be managed through compensation events rather than quantity measurement. Clients may also prefer Option C if they want the Contractor to “own” the work breakdown – it can enhance understanding of the plan.
Option D – Target Contract with Bill of Quantities: Option D is suitable when the project is of a nature that lends itself to measurement with a BoQ, or where a standard method of measurement is required due to client/industry practices. Under Option D, the Client (or its consultants) typically produce the Bill of Quantities as part of the tender documents, specifying estimated quantities of work items based on a measurement standard (e.g. CESMM or NRM). The Contractor tenders unit rates (or lump sums for certain items), which extended by the quantities give the target price. Use cases: Option D is often used in civil engineering and infrastructure projects (roads, earthworks, utilities) where a BoQ is the traditional pricing tool and quantities of work (excavation volumes, lengths of pipe, etc.) are key cost drivers. It’s also chosen when the client wants a detailed breakdown of costs per item for later analysis or for framework contracts where rates might be reused. Additionally, if the scope is not fully firm and quantities may vary, Option D provides a mechanism (detailed below) to adjust the target for significant quantity differences under certain conditions. Clients might prefer Option D when they want to retain control by providing the pricing structure (the BoQ), ensuring all bidders price on the same basis with a uniform method of measurement, which can make tenders more comparable. It also helps if the client has a good estimate of quantities but still wants a target cost approach to manage risk – the BoQ serves as a basis for that estimate.
Comparative Considerations: Option C vs Option D
Balance simplicity, transparency, measurement needs, and client objectives to choose the right NEC4 target option.
Option D — BoQ Transparency
More admin but clear build-up (rates × quantities). Helpful where stakeholders expect traditional measurement and audit trails.
Option C — Administrative Simplicity
No continual remeasurement; target set via Activity Schedule. Great when design is evolving and the Contractor “owns” the WBS.
Consideration | Option C (Activity Schedule) | Option D (Bill of Quantities) |
---|---|---|
Complexity vs Transparency | Simpler admin; no ongoing quantity measurement. Changes via activity adjustments. | More complex admin; strong price transparency with rates and quantities. |
Accuracy of Pricing Info | Avoids false precision when design isn’t mature; flexible risk allocation across activities. | Detailed target when a reliable BoQ exists; helps spot outlier rates/cost drivers. |
Client Objectives | Encourages Contractor input and innovation with freedom to structure the schedule. | Aligns with clients who prefer familiar BoQ norms or need itemized budgets/audit trails frameworks/term. |
Industry Practice | Favored in building/design-and-build where activities are natural units of work. | Favored in heavy civils/highways where quantities dominate cost formation. |
Measurement & Change | No automatic remeasure; quantity swings affect target only if they are compensation events. | Explicit mechanisms for significant quantity variance; can adjust target in defined cases. |
Incentivisation | Both use target cost with pain/gain share; pricing document differs, incentive intent is similar. |
Read the full detailed explanation (original text)
Comparative Considerations:
Complexity vs. Transparency: Option D (BoQ) can be more complex to prepare and administer (because it involves maintaining a BoQ and possibly measuring work done for certain assessments or compensation events). However, it offers transparency in how the price is built up and can be useful where stakeholders expect to see unit rates and quantities. Option C is generally simpler – no ongoing measurement of quantities, and changes are handled by adding or modifying activity line items as needed for compensation events.
Accuracy of Pricing Information: If the design is at a stage where a reliable BoQ can be produced, Option D might yield a more detailed target cost and allow identification of outlier rates or particular cost drivers. If the design is less mature or expected to evolve significantly, an Activity Schedule (Option C) might avoid the false precision of quantities and allow the Contractor to allocate risk money more flexibly among activities.
Client Objectives: If the client’s objective is to foster innovation and Contractor input, both options do so via the target mechanism, but Option C gives the Contractor more freedom to allocate costs in the schedule. Option D might align better with a client who wants to use a familiar BoQ approach (e.g. government bodies that require a BoQ for budgeting or audit). Option D is also sometimes used in framework agreements or term contracts where work is instructed via BoQ items – it provides a schedule of rates within a target-cost umbrella.
Industry Practice: Some industries (e.g. building construction) lean towards activity schedules, while heavy civils and highway projects lean towards BoQs. NEC allows either: Options C and D are structurally the same except for the pricing document, so often it comes down to which pricing method the project team is more comfortable with. Notably, whichever is chosen, the incentivization is similar. In fact, the NEC4 Users’ Guide notes that the Activity Schedule or BoQ in target contracts is primarily to set the target and does not dictate payments during the project.
Measurement and Change Management: Option D provides explicit mechanisms for quantity variance (detailed below under clause-by-clause differences) – which can be valuable if actual quantities are highly uncertain. If a project has a few major quantity risks (e.g. ground excavation), a BoQ item can be included and significant overrun in that quantity could trigger a compensation event to adjust the target (if conditions in clause 60.4 are met). In Option C, if a similar scenario occurs (e.g. more work needed than envisaged), there is no automatic quantity re-measure; it would only change the target if it qualifies as a compensation event (e.g. unforeseen physical conditions under clause 60.1(12)). Otherwise, the Contractor bears the cost overrun share. Thus, Option D can offer a slight safety valve for quantity deviations not caused by scope change, whereas Option C places all such risk on the target mechanism unless explicitly covered by compensation events.
In summary, choose Option C for simplicity and when the project can be scoped by activities (with the Contractor structuring the price), choose Option D when a detailed BoQ is appropriate or required. Both options align the Contractor’s financial interests with project cost control, making them suitable for collaborative projects aiming for cost transparency and value for money.
Clause-by-Clause Breakdown: NEC4 ECC Option C vs Option D
Side-by-side differences with quick tags, searchable text, and copy-ready notes. Parts 1–3 integrated.
Option C
Defined Cost mirrors D: cost of components in the SSCC, less Disallowed Cost.
Activity Schedule is defined (11.2(21) C).
The Prices (11.2(30) C): lump-sum prices for each activity.
PWDD (11.2(29)): identical in C/D — forecast total Defined Cost to next assessment + Fee.
Option D
Defined/Disallowed Cost mirror C (11.2(24)/(25)).
BoQ is defined (11.2(22) D).
The Prices (11.2(31) D): lump sums + rates × quantities.
Total of the Prices (11.2(32) D): rate × measured quantity + proportion of lump sums.
Option C
20.2: Advise PM on design/subcontracting. 20.3: Rolling forecasts of total Defined Cost with explanations.
Option D
Same duties as C; not present in fixed-price A/B.
Option C
26.4: Submit proposed subcontract pricing to PM (unless waived).
Option D
Same as C — supports transparency and alignment with the target.
Option C
Re-test after a Contractor Defect is treated as Disallowed Cost (not reimbursable).
Option D
41.7 explicitly excludes re-test costs from Defined Cost.
Option C
50.7: Multi-currency conversion for Defined Cost. 50.9: PM has 14 weeks to accept/query finalised cost portions.
Option D
Same as C — stabilises currency/share calcs and de-risks final accounts.
Option C
52.1: Non-Defined Cost covered by Fee; Defined Cost at stated/open-market rates net of discounts/recoverable taxes. 52.2–52.3: Keep/allow inspection of records.
Option D
Same text and intent as C — evidence-based, auditable costs.
Option C
54.1–54.4: Compare Target vs Actual (PWDD); apply share ranges; bonus if saving, deduction if overrun; prelim at Completion, final at final account.
Option D
54.5–54.8: Same content; numbering differs. Share % and bands in Contract Data.
Option C — Clause 55
55.2: Activity Schedule is pricing only; revise when helpful to assess CEs (not every time).
Option D — Clause 56
56.1: BoQ is pricing only; express CEs as BoQ changes via 63.15; monthly payment still cost-based.
Option C
Relies on core 60.1 events; no separate BoQ quantity CE.
63.13: Contractor-proposed savings do not reduce target; gains flow via share.
Option D
60.4: Quantity variance CE if not a Scope change, unit cost changes, and item value > 0.5% of total Prices.
60.5: Quantity variance causing delay is a CE.
60.6: Correcting BoQ mistakes is a CE; may reduce Prices. 60.7: BoQ assumed correct for tender pricing.
Option C
Price CEs from first principles (SSCC). 63.14: Express as Activity Schedule changes. 63.13: Contractor VE savings don’t reduce Prices.
Option D
Same pricing approach. 63.15: Express as BoQ changes (rate/quantity/new item). 63.13: Same VE rule.
Option C
93.4: At termination, PM assesses the Contractor’s share using PWDD as the Defined Cost paid/committed for work done up to termination and uses, for Total of the Prices:
• the lump-sum price of each completed activity, and
• a proportion of each incomplete activity equal to the proportion completed.
93.6: The assessed share is then added (saving) or deducted (excess) from the termination amount due.
Option D
Same principle, applied through the BoQ lens:
• PWDD = Defined Cost paid/committed for work done up to termination.
• Total of the Prices for termination is derived from measured completed work (rate × quantity for each BoQ item) plus proportion of any lump-sum items completed — aligning with D’s running definition.
Contractor’s share of any under/overrun at termination is similarly added/deducted in the termination assessment.
Where C & D are aligned
Target-cost mechanics (PWDD, Defined/Disallowed Cost, open-book records), forecasting (20.3), subcontract transparency (26.4), pain/gain share (54), CE pricing via SSCC (63), and termination principle (93).
Where they differ
Pricing doc: C uses Activity Schedule (55); D uses BoQ (56).
Quantity CEs: D adds 60.4–60.7 for variance/mistakes; C does not.
Complexity: D carries more admin/transparency via BoQ; C is simpler administratively.
CE formatting: C uses Activity Schedule changes (63.14); D uses BoQ changes (63.15).
NEC4 ECC — Options C vs D: Interactive Comparison & Cost Share Simulator
Deep-dive table, card view, and a live pain/gain calculator—plus search, lens tips, and CSV export.
Aspect | Option C — Target with Activity Schedule | Option D — Target with Bill of Quantities |
---|---|---|
Pricing Mechanism Different |
Activity Schedule: Contractor lists activities with lump sums. Sum = Target Cost. No rate×quantity.
✔ High flexibility to structure work packages for execution planning.
|
BoQ: Client supplies items with quantities; Contractor tenders rates/lumpsums; extended totals = Target Cost (method of measurement per Contract Data).
✔ Comparable bids, transparent quantities for budgeting & audit.
|
Who Prepares Pricing Document Different | Prepared by Contractor (tender Part 2). ✔ Ownership of WBS & risk allocation within activities. |
Prepared by Client/Consultant and issued with tender. ✔ Consistent basis across bidders; easier benchmarking. |
Role of Pricing Doc During Project Same intent | Baseline only for target; not used for monthly payment; not Scope (55.2). CE values adjust target; schedule may get extra items for CEs. | Baseline only; payment not by remeasurement; not Scope (56.1). CEs expressed as BoQ changes to maintain target trail. |
Payment Basis (Interim) Same | Defined Cost + Fee with forecast to next assessment; Disallowed Cost excluded; pay as incurred (no need to finish an activity). | Same as C. BoQ progress irrelevant to payment; partial work still reimbursed by allowable cost. |
Defined Cost Calculation Same | Full SSCC; actuals less Disallowed Cost; Fee applied. | Identical SSCC/Disallowed rules; BoQ doesn’t change what’s reimbursable. |
Cost Reporting & Forecasting Same | Regular 20.3 forecasts; records & audit (52.2/52.3); early warnings & collaboration. | Same requirements; BoQ may help pinpoint item-level trends. |
Target Cost Adjustments Different | CEs adjust target via Activity Schedule changes (63.14). 63.13: VE savings don’t reduce target. No automatic quantity CE. | CEs as BoQ changes (63.15). Quantity variance CEs (60.4/60.5) for significant differences; BoQ errors (60.6) corrected (can reduce target). VE savings don’t reduce target (63.13). |
Pain/Gain Share Mechanism Same | Compare PWDD vs total of Prices; apply Contract Data share bands (54). Prelim share at Completion; final at final account. | Same calculation; BoQ only affects how the target evolves through CEs. |
Termination Calculation Different lens | Termination: defined cost of work done + share. Use completed activities + proportion of incomplete (93.4); add/deduct share (93.6). | Same principle using BoQ: measured completed quantities × rates + proportion of lump-sum items; then add/deduct share. |
Option C
Activity Schedule (lump sums per activity). Sum = Target; no rate×qty.
Option D
BoQ with quantities & rates; extended totals = Target.
Option C
Contractor prepares Activity Schedule (tender).
Option D
Client/Consultant prepares BoQ.
Option C
Baseline only; not Scope; target adjusted via CE (63.14).
Option D
Baseline only; not Scope; CEs expressed as BoQ changes (63.15).
Option C
Defined Cost + Fee with forecast; Disallowed excluded.
Option D
Same; BoQ progress not needed for payment.
Option C
CEs via Activity Schedule; VE savings don’t reduce target; no quantity CE.
Option D
CEs via BoQ; quantity variance & BoQ error CEs available.
Option C
Compare PWDD vs total of Prices; apply bands in Contract Data (54).
Option D
Same; BoQ affects only how target is structured/adjusted.
Option C
Completed + proportional activities form “total of Prices” at termination; add/deduct share.
Option D
Measured quantities × rates + proportional lump sums; add/deduct share.
Pain/Gain Calculator
Note: Both Options C and D use the same share math. Option D’s quantity-variance CEs can adjust the target in certain cases before sharing.
Results
“What If” Scenarios — NEC4 ECC Options C vs D
Try realistic situations and see how Option C and Option D behave on target, time, and pain/gain.
Scenario 1: Client-Initiated Scope Change
How it works Same principle (C & D)
Context: Client adds an extra structure mid-project. It’s a Scope change and a compensation event; target increases by the agreed cost, and time extends accordingly.
Option C: Add/adjust Activity Schedule (change value). Option D: Add BoQ item(s) or adjust rates/quantities. In both, monthly payment remains Defined Cost + Fee; no upfront lump sum.
Share impact: The change itself doesn’t create pain/gain; any variance on that new work (your actual vs the +target) will be shared at completion.
Scenario 2: Quantity Overrun (No Scope Change)
Key difference Different
Option C: No BoQ → no automatic quantity CE. Extra volume raises actual cost but doesn’t raise target, so overrun is shared.
Option D: BoQ variance rules can trigger a CE (e.g., if value change > 0.5% of the Prices and unit cost changes). Target and (if applicable) dates are adjusted.
Scenario 3: Contractor Value Engineering (Cost Saving)
How it works Same (C & D)
Contractor proposes an accepted alternative that reduces Defined Cost. Target is not reduced; the saving flows into the pain/gain share at completion.
Because the target stays higher than actual, both parties benefit from the saving per the agreed share.
Scenario 4: Contractor Error (Disallowed Cost)
Core rule Same (C & D)
Rework/waste from Contractor error is Disallowed Cost → not reimbursed. Time impact is not excusable. Depending on how the final share is assembled, the non-reimbursed amount may still influence the apparent underrun/overrun calculation.
“What If” Scenarios — NEC4 ECC Option C vs Option D
Interactive, example-driven walkthroughs with live target & share calculators, quantity-variance logic, and value-engineering savings.
Scenario 1: Scope Change (Client-Initiated)
Context. Client adds a new structure worth £100,000 (Defined Cost), moving Completion by 2 weeks. Payment remains cost-based; the target increases by the CE value (format differs between C and D).
Option C — Activity Schedule
PM instructs CE; quotation built from Defined Cost (time included). Target increases by £100k (plus fee if applicable) by adding/adjusting an activity; Completion Date moves +2 weeks. Payments continue as Defined Cost + Fee.
Option D — Bill of Quantities
Same CE; expressed as BoQ additions/changes (e.g., new lump-sum item). Target +£100k; time +2 weeks. Monthly payments still follow Defined Cost + Fee; BoQ tracks the target ledger, not interim payment.
Flow
CE Impact (quick)
Results
Scenario 2: Quantity Overrun (No Scope Change)
Context. Excavation was initially 10,000 m³; actual need is 12,000 m³. Not a Scope change; not an unforeseeable condition.
Option C — Activity Schedule
No automatic CE for pure quantity variance. Extra 2,000 m³ increases Defined Cost and likely creates an overrun vs target, which is shared per the percentages.
Option D — Bill of Quantities
60.4 can trigger a CE if unit cost changes and ΔQ×rate > 0.5% of total; 60.5 grants time if Completion is delayed.
Quantity CE Explorer (Option C vs D)
Threshold test uses ΔQ × base rate vs 0.5% × Total of the Prices. If all 60.4 conditions pass, Option D can raise a CE; Option C does not.
Results
Scenario 3: Contractor’s Value Engineering Proposal (Cost Saving Change)
Context. Contractor proposes an alternative (e.g., cladding) with equal performance but lower cost. PM accepts the Scope change. Under 63.13, the target (total of the Prices) is not reduced; the saving appears in the actual Defined Cost when the work is done, creating an underspend shared at Completion.
Options C/D — How it plays out
Target stays as-was. If the change saves £50,000 of actual cost, the Price for Work Done to Date finishes £50k below target. With a 50/50 share, the Contractor receives a £25k gain; the Client effectively pays £25k less than target.
Contrast with Options A/B
In fixed-price forms, VE typically reduces the contract price upfront by a VE percentage. If VE% retained by Contractor is, say, 25%, the Contractor keeps £12.5k and the Client’s price reduces by £37.5k.
VE Savings Explorer (63.13)
Under 63.13, the CE is implemented with no reduction to target. Savings appear in Defined Cost and are shared at Completion.
Results
Clarity & Usability Upgrades for NEC4 ECC Options C & D
Plain-English glossary, copy-ready notes, and actionable guidance — without changing the contract mechanics.
Quick Glossary (Plain Language)
-
The Prices the target
Think “target cost” (initial + implemented CEs). A comparison baseline — not what you pay each month. -
Price for Work Done to Date actual cost + fee
The Project Manager’s forecast of Defined Cost paid/committed to next assessment plus the Fee. That’s your interim payment basis. -
Defined Cost vs Disallowed Cost
Defined Cost = allowable, evidenced costs per the Schedule of Cost Components. Disallowed = specific categories you cannot recover (e.g., not evidenced, late warnings, correcting defects after Completion, etc.). -
Activity Schedule / Bill of Quantities target-only
Under Options C/D they exist to set the target, not monthly payments.
Tip: Use this page in kickoff workshops — switch the accent to match your brand.
Suggestions to Improve Clarity in These Options
Clarify Terminology in Plain Language High impact
Your point (kept verbatim)
Actionable snippet (copy-ready)
📝 Guidance note: • “The Prices” = the TARGET (initial + implemented CEs). • “PWDD” = ACTUAL defined cost to date + FEE (reimbursable). • Use these as: comparison baseline (Prices) vs payment basis (PWDD).
Guidance on Activity Schedule/BoQ Usage Quick win
Your point (kept verbatim)
Actionable snippet (copy-ready)
📝 Payment note (Options C/D): Interim amount due is PWDD only (Defined Cost + Fee). The Activity Schedule/BoQ does not determine monthly payment.
Simplify Disallowed Cost Definition
Your point (kept verbatim)
Checklist template (copy-ready)
✅ Disallowed Cost quick-check: [ ] Not evidenced by accounts/records [ ] Caused by failure to follow early-warning/procedures [ ] Correcting Defects after Completion [ ] Plant/Materials not used (beyond reasonable wastage) [ ] Resources not removed when instructed [ ] Any Z-clause additions (project-specific)
Expand Guidance on Measurement (Option D)
Your point (kept verbatim)
Workshop prompt (copy-ready)
🗂️ Agree BoQ LS proportions upfront: • Define “substantial element” milestones per item • Align with “no Defects delaying following work” • Use simple % tables (e.g., install 100m = 1%/m; testing = final 10%)
Tie Early Warnings to Forecasts (20.3)
Your point (kept verbatim)
Trigger rule (copy-ready)
⏰ Early-warning trigger: If EFC > Target by ≥ X% or trend ≥ Y% over 2 periods → raise EW, log actions, re-forecast, and minute decisions in risk-reduction meeting.
Final Takeaways — NEC4 ECC Options C & D
Interactive TL;DR, decision tuner, and pain/gain visualiser — plus your full text preserved below.
Executive TL;DR
Decision Tuner — Should you lean C or D?
Pain/Gain Visualiser
Full “Final Takeaways” (verbatim)
Both Option C and Option D are target cost contracts that foster a partnership approach: the Contractor is paid actual cost plus a fee, and both Client and Contractor share the benefits of efficiency or the pain of overrun. This aligns incentives for project success and cost control.
Key Difference – Pricing Document: Option C uses a Contractor-developed Activity Schedule (lump-sum breakdown of tasks) while Option D uses a Client-provided Bill of Quantities (quantities & rates) to set the target price. This choice often hinges on the nature of the project (discrete activities vs measurable items) and industry norms. Activity Schedule = flexibility and simplicity; BoQ = detail and traditional measurement.
Payment is Actual Cost-Based: Under both options, the Contractor’s cash flow is based on reimbursable costs, not on completing listed items. This means improved cash flow and reduced risk of under-payment for partially completed work – a major difference from fixed-price options. It also requires diligent cost reporting and trust.
Cost Management and Transparency: Defined Cost, Disallowed Cost, and the Schedule of Cost Components form the engine of cost management. The Contractor must maintain open accounts and justify expenditures. Disallowed Cost provisions protect the Client from paying for inefficiency or non-compliance. Both parties should clearly understand what is allowable.
Risk Sharing and Contractor’s Share: The target cost with a Contractor’s share mechanism (clause 54) creates a balanced risk distribution. The Contractor isn’t solely exposed to overruns as in a lump sum – the Client covers a portion – but also the Contractor doesn’t get all the savings – the Client benefits too. This arrangement motivates both to collaborate on cost-saving ideas and efficient project delivery, as both stand to gain.
Option D’s BoQ-Specific Features: Option D has extra clauses to deal with quantity variations and BoQ errors, preventing the target from being unfair if quantities significantly differ. This makes Option D advantageous when quantity uncertainty is high – it blends a measure-and-value approach with target cost principles. Option C lacks that specific adjustment mechanism, meaning quantity changes mostly play out in the pain/gain at the end (unless captured by other compensation events).
When to Choose Option C vs D: In practice, Option C is often chosen for building works, multidiscipline projects, or when the Contractor’s planning is key – it’s somewhat more straightforward and gives the Contractor ownership of the breakdown. Option D is chosen for civil works or when a BoQ exists or is required for funding/valuation reasons. Clients who prefer to control the pricing format or have established schedule of rates may lean to D. However, if a BoQ would be forced or based on guesswork, Option C might be safer to avoid the illusion of precision.
Administrative Effort: Both options require strong administrative effort in cost monitoring and change management. Option D might require more work in terms of measurement and managing the BoQ (e.g. tracking quantities, applying 0.5% rules). Option C requires discipline in managing the Activity Schedule for changes, but otherwise is primarily focused on cost ledgers. In either case, the Project Manager’s role is crucial in auditing costs and agreeing changes promptly so the target is up-to-date.
Success Factors: For either option, success relies on good collaboration, transparency, and timely communication. The early warning process, regular forecasting (cl. 20.3), and open-book auditing mean the Client and PM will be deeply involved in the financial side throughout. This can be very positive (no surprises at final account) but requires trust. The obligation to act in a “spirit of mutual trust and co-operation” (cl. 10.2) is especially pertinent under target cost contracts.
In conclusion, Option C and Option D under NEC4 ECC are two sides of the same coin: they provide flexibility and incentives to manage projects where cost outcomes are uncertain. The choice between them hinges on the preferred method of price formation (activities vs quantities) and the project’s complexity. Both options, when used with diligent project management, can deliver excellent value for money, encourage innovation (through shared savings), and mitigate the adversarial nature of purely fixed-price agreements. Users should ensure they fully understand the mechanics – particularly how the target is adjusted and how the pain/gain is calculated – to reap the benefits these options offer in driving collaborative project delivery.