Views in the last 30 days: 79
Estimated read time: 26 minute(s)
🧩 1️⃣ Purpose of Clause 8.2 [Time for Completion]
(As per both FIDIC Yellow Book 1999 and 2017 editions)
Let’s set the scene 👷♂️🏗️—you’re the Contractor, and you’ve just been handed over the site. You’re eager to mobilize your team, pour concrete, and see those cranes swinging. But before you get too excited, FIDIC wants to make one thing very clear through Clause 8.2:
There is a specific deadline—called the Time for Completion—and it’s not just about finishing physical construction.
This clause serves as a contractual checkpoint: a formal finish line that the Contractor must cross. And crossing that line isn’t just about bricks and mortar. It’s about:
- 🧪 Passing all the contractual tests (Tests on Completion),
- 📑 Submitting key documents,
- 🛠️ Finishing everything necessary for the Employer to take over.
Let’s unpack it a bit more.
🧭 What is “Time for Completion” really?
Both editions define it (1999: Sub-Clause 1.1.1.3, 2017: Sub-Clause 1.1.81) as the duration from the Commencement Date to the date when the Works (or Sections) must be fully completed. But what does “fully completed” mean in FIDIC terms?
Here’s the fun part—it includes more than just finishing site work. According to Clause 8.2, you must:
- ✅ Achieve the passing of all Tests on Completion (See Clause 9),
- ✅ Complete all work defined in the Contract as necessary for Taking Over (Clause 10.1),
- ✅ Do all this within the duration stated in the Contract Data (2017) or Appendix to Tender (1999).
So even if the Contractor finishes building the plant or facility, but doesn’t complete the required documentation or fails a test—Guess what? You’ve not achieved “Completion” under Clause 8.2. And that has consequences. 💸

⚖️ What’s the big deal with this clause?
Clause 8.2 acts as the pivot point for many other contractual rights and obligations. It’s the trigger for:
- 💰 Delay damages (under Clause 8.7/8.8),
- 🏁 The Taking Over process (Clause 10.1),
- 🕓 And also defines when you might claim an Extension of Time (Clause 8.4/8.5) if something beyond your control delays you.
So, you could think of Clause 8.2 as the contractual deadline that all roads lead to. Miss it? You’re exposed to penalties and possible disputes.
🔄 Is there a difference between the 1999 and 2017 Editions?
The core intent is exactly the same—but the 2017 Edition tightens up the language to leave less room for ambiguity.
Let’s compare their wording briefly:
🏗️ 1999:
“…including (a) achieving the passing of the Tests on Completion and (b) completing all work… required for the purposes of taking over under Sub-Clause 10.1…”
🛠️ 2017:
“…including completion of all work which is stated in the Contract as being required for… taking over under Sub-Clause 10.1.”
🔍 See the difference?
The 1999 version splits out the two requirements (tests and other deliverables) more explicitly. The 2017 version is a little more streamlined, but assumes that the reader understands “completion” as a bundled package—everything necessary for Taking Over.
This subtle shift reflects a broader trend in the 2017 edition: moving toward a more integrated, obligation-linked structure, where clauses cross-reference one another in tighter loops.
👥 Why is this important for the parties?
Let’s consider each party’s perspective:
👷 Contractor:
- Knows exactly what’s expected to avoid delay damages.
- Has a strong reason to track completion milestones clearly.
- Can plan claims under Clause 8.5 with more precision.
🧑💼 Employer:
- Has a clear benchmark for when to expect delivery.
- Can enforce contractual remedies if the timeline is missed.
- Gains confidence in handover readiness, not just physical completion.
🧑⚖️ Engineer:
- Uses Clause 8.2 as a reference point for certifying completion.
- Aligns it with Clause 9 (Tests) and Clause 10 (Taking Over).
🏛️ Historical Context: Why the updates in 2017?
The 1999 version was already functional, but it left some gray areas—for example:
- Was a failure to pass a minor test enough to stop the clock?
- Could the Employer refuse Taking Over if just one deliverable was pending?
The 2017 edition aimed to streamline and clarify:
- That everything required for Taking Over must be done, and
- That “Completion” is not just physical—it’s contractual and procedural.
These changes align well with FIDIC’s Golden Principle 3:
“The Employer’s and the Contractor’s duties, rights, obligations and risks must be generally as required by the FIDIC Contract and must be clearly and unambiguously stated.”
By embedding clear expectations, the 2017 version reduces ambiguity and lowers the risk of disputes.
📚 2️⃣ Breakdown of Clause 8.2 [Time for Completion]
📖 Let’s Start With the Verbatim Clause Texts:
📘 FIDIC Yellow Book 1999 – Clause 8.2
“The Contractor shall complete the whole of the Works, and each Section (if any), within the Time for Completion for the Works or Section (as the case may be), including:
(a) achieving the passing of the Tests on Completion,
(b) completing all work which is stated in the Contract as being required for the Works or Section to be considered to be completed for the purposes of taking-over under Sub-Clause 10.1 [Taking Over of the Works and Sections].”1. FIDIC Yellow Book 19…
📙 FIDIC Yellow Book 2017 – Clause 8.2
“The Contractor shall complete the whole of the Works, and each Section (if any), within the Time for Completion for the Works or Section (as the case may be), including completion of all work which is stated in the Contract as being required for the Works or Section to be considered to be completed for the purposes of taking over under Sub-Clause 10.1 [Taking Over the Works and Sections].”1. FIDIC Yellow Book 20…
🗣️ Let’s Decode That in Plain English
At first glance, this might seem like a simple clause: “Finish your work on time.” But FIDIC adds layers of legal meaning behind those words. Here’s what it actually means:
🔍 Step-by-Step Interpretation:
🧱 “Complete the whole of the Works…”
➡ This means all construction, design, and procurement obligations must be fulfilled. No half-baked handovers.
Whether it’s a power plant or a toll plaza—you’ve got to fully deliver what’s in the Contract.
🧩 “… and each Section (if any)…”
➡ Many large projects break the works into Sections (e.g., Phase 1, Phase 2). Each Section has its own Time for Completion. This allows the Employer to take over in stages, making it easier to manage.
✅ Tip: In both editions, it’s crucial to define Sections and their timelines clearly in the Contract Data (2017) or Appendix to Tender (1999). Otherwise, this can become a dispute magnet.
🎯 “…within the Time for Completion…”
➡ This phrase doesn’t just mean “finish quickly.” It means:
- Within the exact duration stated in the Contract,
- As measured from the Commencement Date, and
- Subject to extensions (see Clause 8.4 in 1999, Clause 8.5 in 2017).
📌 In 1999, this definition is clearly given in Sub-Clause 1.1.3.3, while in 2017, it appears in Sub-Clause 1.1.81:
“‘Time for Completion’ means the time for completing the Works or a Section (as the case may be) under Sub-Clause 8.2… calculated from the Commencement Date.”1. FIDIC Yellow Book 19…
🧪 “…including achieving the passing of the Tests on Completion…”
➡ A game-changer. Completion isn’t just physical. The Works or Section must pass specified Tests to prove it performs safely and as intended.
These Tests are outlined in Clause 9 and include:
- Pre-commissioning tests (e.g., dry tests),
- Commissioning tests (systems run under real conditions),
- Trial operations (full-blown functionality testing under real-world stress).
🚨 Without passing these? Even if you’ve built everything, you haven’t completed the job1. FIDIC Yellow Book 19…1. FIDIC Yellow Book 20….
📄 “…completing all work which is stated in the Contract as being required… for the purposes of taking-over under Sub-Clause 10.1”
➡ This is often misunderstood. Many assume that once the work is built and tested, it’s done. Not true.
Completion also includes:
- Submission and approval of As-Built Records (Sub-Clause 5.6),
- Delivery of O&M Manuals (Sub-Clause 5.7),
- Completion of training, if applicable (Sub-Clause 5.5),
- Any other obligations listed in the Employer’s Requirements or Contract Data.
Only when all of these are complete can the Contractor apply for the Taking-Over Certificate (Clause 10.1)1. FIDIC Yellow Book 20…1. FIDIC Yellow Book 19….
✅ Key Differences in Language
Element | 1999 Edition | 2017 Edition |
---|---|---|
Tests on Completion mentioned separately | ✅ Yes (explicit in point a) | 🚫 No (bundled into broader definition) |
Structure | Bulleted format (a, b) | Continuous sentence |
Focus | Slightly more checklist-based | Slightly more narrative and condensed |
Clarity for readers | Easier to parse for newcomers | Needs stronger cross-referencing with Clause 10.1 & Clause 9 |
The substance is the same, but 2017 refines the language to encourage users to read in context rather than rely on individual clauses.
🔎 What Should the Contractor Watch For?
🧠 Just saying “we’re done” isn’t enough. You need to:
- Prove the Tests were passed,
- Get the Engineer’s No-Objection Notices for docs,
- Confirm all contractually required components are delivered.
🚧 What Happens If You Miss the Mark?
If you fail to meet Clause 8.2, the Employer may:
- Enforce Delay Damages under Clause 8.7 (1999) / 8.8 (2017),
- Refuse to issue the Taking-Over Certificate (Clause 10.1),
- Trigger possible termination events under Clause 15 in extreme cases.
🧠 3️⃣ Key Interpretations and Implications of Clause 8.2 [Time for Completion]
🎯 So… what’s the real punch of Clause 8.2?
On paper, Clause 8.2 seems pretty straightforward: “Finish the Works within the Time for Completion.” But under the hood, it’s a power clause that:
- Connects to the heart of project delivery,
- Has serious financial consequences if missed,
- And sets off a domino effect across Clauses 8.4/8.5 (Extension of Time), 8.7/8.8 (Delay Damages), 9 (Tests on Completion), and 10.1 (Taking Over).
Let’s walk through what this really means for each party—and what they must never overlook 👇
🧑🔧 For the Contractor: It’s All About the Clock ⏰
✅ Your Main Obligation?
Finish the Works (or each Section) not just physically, but also:
- ✅ Pass all required Tests on Completion (Clause 9.1),
- ✅ Deliver all documents needed for Taking Over (Clause 10.1),
- ✅ Do all this before the Time for Completion expires.
📌 Miss it—even slightly—and you risk:
- 💸 Delay Damages every single day (see 1999 Clause 8.7 and 2017 Clause 8.8)1. FIDIC Yellow Book 19…1. FIDIC Yellow Book 20…,
- ❌ Rejection of your Taking Over application (Clause 10.1),
- ❗ Forced acceleration measures by the Engineer (Clause 8.6).
⚖️ Example Consequences:
“But I passed the structural inspections!”
Still not enough. If you haven’t passed the trial operation test or submitted your O&M Manuals—you’re still in breach of Clause 8.21. FIDIC Yellow Book 20….
🧑💼 For the Employer: It’s Your Shield 🛡️
🏗️ Why Clause 8.2 Works for the Employer:
- Sets a clear deadline to expect handover.
- Creates a financial remedy (delay damages) if the Contractor underperforms.
- Provides legal grounds to reject incomplete work until all obligations are met (Clause 10.1).
✅ Delay Damages (1999 & 2017):
“…a sum stated in the Appendix to Tender / Contract Data, payable for every day of delay…”
But there’s a cap—a maximum limit to these damages to keep things fair1. FIDIC Yellow Book 19…1. FIDIC Yellow Book 20….
📌 Even with Delay Damages, you’re still entitled to full completion. The damages are compensation—not a trade-off.
🧑⚖️ For the Engineer: Your Anchor for Administration ⚖️
Clause 8.2 becomes the Engineer’s reference point for:
- Monitoring progress (Clause 8.3 – Programme),
- Assessing delay claims (Clause 8.4/8.5 – EOT),
- Approving Taking Over Certificates (Clause 10.1),
- Enforcing acceleration (Clause 8.6 – Rate of Progress).
✅ The Engineer also gets to reject Taking Over requests if Tests or deliverables are not complete—even if the Contractor insists the work is “done”1. FIDIC Yellow Book 20….
🚨 Risks Hidden in Plain Sight
Let’s spotlight some common traps Contractors fall into (and how Clause 8.2 makes them painful):
🚧 Trap 1: “Work is built, but tests are pending”
❌ You haven’t fulfilled Clause 8.2.
Clause 9.4 allows the Engineer to:
- Demand retesting,
- Reject the Works, or
- Accept the works with a value reduction1. FIDIC Yellow Book 20….
🚧 Trap 2: “We submitted the documents, they’re just not approved yet”
That’s not good enough.
Clause 10.1 requires No-Objection Notices for:
- As-Built Records (Clause 5.6),
- O&M Manuals (Clause 5.7),
- Training (Clause 5.5) where applicable1. FIDIC Yellow Book 20….
So even if the physical site is shiny and ready, documents can delay completion.
🚧 Trap 3: “We’re delayed, but the Employer was also at fault”
Enter the world of concurrent delays.
Clause 8.5 (2017) says EOT entitlement will be assessed using rules in the Special Provisions, or if silent, then based on all relevant circumstances1. FIDIC Yellow Book 20….
📌 If concurrency rules aren’t clear, the Contractor may struggle to prove EOT.
💡 Pro Tip: Use Clause 8.2 as a Strategic Tool
If you’re a Contractor:
- Build a reverse timeline from the Time for Completion.
- Schedule in: Testing time, document reviews, training delivery, buffer for non-critical defects.
- Link it all to your Clause 8.3 Programme submission.
If you’re the Employer:
- Make sure Sectional Completion Dates are realistic, not aspirational.
- List every deliverable needed for Taking Over.
- Confirm the Delay Damages formula is enforceable in your jurisdiction.
🔍 Final Thoughts on the Implications
Clause 8.2 is deceptively short but contractually powerful. It binds everyone:
- The Contractor to a clear finish line with no shortcuts,
- The Employer to a defined right of redress, and
- The Engineer to a gatekeeper role who ensures no one crosses that finish line prematurely.
🔗 4️⃣ Cross-Referencing Clause 8.2 with Other Clauses
🔍 So, why cross-referencing matters?
Because Clause 8.2 is not a standalone clause. It’s the anchor that interlocks with:
- Clause 8.3 – Programme 📆
- Clause 8.4/8.5 – Extension of Time ⏳
- Clause 9 – Tests on Completion 🧪
- Clause 10.1 – Taking Over 🏁
- Clause 8.6 – Rate of Progress 🚧
Let’s break down each one and see how the web is woven 👇
📅 Clause 8.3 – Programme: The Roadmap to Clause 8.2
🧩 In both editions, Clause 8.3 requires the Contractor to submit a detailed programme within 28 days of the Commencement Notice.
But here’s the twist—this programme must include:
- The Time for Completion of the Works and Sections,
- The entire sequence of tasks: design, procurement, manufacturing, testing, commissioning,
- The timing of Tests on Completion and submission of critical documents1. FIDIC Yellow Book 20…1. FIDIC Yellow Book 19….
📌 The Programme is not optional fluff—it forms the basis for:
- Determining whether the Contractor is on track to meet Clause 8.2,
- Triggering acceleration orders (Clause 8.6),
- Supporting or denying EOT claims (Clause 8.5).
✅ If your Clause 8.3 programme doesn’t reflect the real milestones in Clause 8.2—you’re already setting yourself up for disputes.
⏳ Clause 8.4 (1999) / 8.5 (2017) – Extension of Time: The Lifeline for Delays
📌 Clause 8.2 sets the finish line. Clause 8.4/8.5 says:
“If that finish line needs to move for reasons beyond your control—we’ll allow it, but only if you follow the process.”
What triggers an Extension of Time (EOT)?
- Variations (Clause 13),
- Exceptionally adverse weather,
- Shortages due to epidemics or government restrictions,
- Delays caused by the Employer or their other contractors1. FIDIC Yellow Book 19…1. FIDIC Yellow Book 20….
But here’s the kicker:
Completion for the purpose of Clause 8.2 must be delayed, not just site activity.
That means if document approvals, O&M manuals, or Tests on Completion are delayed—you can still claim EOT if you notify properly (Clause 20).
🧪 Clause 9 – Tests on Completion: The Final Gate Before Taking Over
Remember in Clause 8.2, the Contractor must pass Tests on Completion before the Works are considered “complete”? That comes from Clause 9.
Here’s how it links:
- Clause 9.1: Contractor must submit a detailed testing programme,
- Must give 42 days’ advance notice before starting tests,
- Must get a Notice of No-objection from the Engineer,
- Cannot start tests until the Engineer agrees or is deemed to agree1. FIDIC Yellow Book 20….
📌 If these tests fail, Clause 9.4 kicks in. The Engineer can:
- Order a retest,
- Reject the Works,
- Or accept it with value deduction (a risky shortcut).
So, without successful Clause 9 tests, you’re dead in the water under Clause 8.2.
🏁 Clause 10.1 – Taking Over: The Outcome of Clause 8.2
Clause 8.2 is the gate you must unlock to enter Clause 10.1.
🧩 Clause 10.1 says:
The Engineer shall issue the Taking Over Certificate only when:
- All Works required under Clause 8.2 are completed,
- Tests are passed,
- O&M manuals and As-Built Records are submitted,
- Training (if required) is completed1. FIDIC Yellow Book 20….
🧠 Here’s the logic chain:
- Clause 9 (Tests) ✅
- Clause 5.6 (As-Built Records) ✅
- Clause 5.7 (O&M Manuals) ✅
- Clause 5.5 (Training) ✅
➡ Then—and only then—do you cross the Clause 8.2 finish line.
📌 If any of those aren’t done, Clause 10.1 allows the Engineer to reject your request for Taking Over.
➡ So Clause 8.2 is like your final exam, and Clause 10.1 is the degree certificate.
🚧 Clause 8.6 / 8.7 – Rate of Progress & Delay Damages: The Stick Behind the Schedule
If Clause 8.2 is the finish line, Clause 8.6 is the warning bell:
“Hey Contractor, your progress is slipping—we don’t think you’ll make it to 8.2 on time.”
The Engineer can:
- Demand a revised programme under Clause 8.3,
- Ask for acceleration measures,
- And require the Contractor to bear the cost if the problem is not due to Employer reasons1. FIDIC Yellow Book 20….
And if the Contractor still fails to hit the Clause 8.2 target? ➡ Clause 8.8 (2017) / Clause 8.7 (1999) hits them with Delay Damages—daily, cumulative penalties until the Time for Completion is achieved1. FIDIC Yellow Book 20…1. FIDIC Yellow Book 19….
🧠 Key Takeaway:
Clause 8.2 is not the destination—it’s the gateway that only opens when everything behind it is in order:
- Programme,
- Tests,
- Documents,
- And coordination with the Engineer.
One slip in this chain? You’re locked out of Taking Over—and may be bleeding Delay Damages daily.
🎭 5️⃣ What-If Scenarios? Let’s Test Clause 8.2 in Action!
🤔 Scenario 1: The Works Are Physically Complete—but the Tests Haven’t Happened Yet
“We’ve finished the installation. Can we get Taking Over?”
📌 Not so fast. Clause 8.2 explicitly requires that the Tests on Completion are passed before the Works or Section can be considered complete. Just finishing construction isn’t enough.
Let’s go deeper:
- Under Clause 9.1, the Contractor must notify the Engineer that the Works are ready for testing and submit a programme for the Tests.
- If the Engineer or Employer delays these tests unreasonably, Clause 9.2 allows the Contractor to request the Engineer to proceed with them—or even have the Employer conduct them at the Contractor’s risk1. FIDIC Yellow Book 20….
✅ Lesson: You can’t cross the Clause 8.2 finish line without crossing the testing checkpoint first.
🔍 Scenario 2: The Tests Were Done… But Failed 😬
“The tests didn’t go well, but the Employer still wants to take over the plant.”
Clause 9.4 comes into play here, and it’s wild:
- The Engineer may reject the Works if the failure deprives the Employer of the “substantial benefit.”
- Or… the Engineer may issue the Taking-Over Certificate anyway—but with a Contract Price reduction reflecting the performance shortfall1. FIDIC Yellow Book 20….
🚨 Risk Alert: This scenario opens the door for:
- 🌩️ Contract Price disputes,
- 📉 Employer claiming a reduction under Clause 11.4 (Failure to Remedy Defects).
✅ Lesson: Clause 8.2 doesn’t demand perfection—but it expects full compliance with test requirements unless the Employer waives it (and that comes at a price).
🤯 Scenario 3: Contractor Submits Everything—But Engineer Says “Not Yet”
“The Engineer says I didn’t submit O&M manuals, but I already emailed them.”
Here’s what matters: Clause 10.1 says the Engineer must issue the Taking-Over Certificate only if:
- Tests are passed,
- As-Built Records get a Notice of No-Objection (Clause 5.6),
- O&M Manuals get a Notice of No-Objection (Clause 5.7),
- Training (Clause 5.5) is done, if required1. FIDIC Yellow Book 20….
So even if you submitted documents, you need formal no-objection notices (or deemed acceptance). Otherwise, you’re not done under Clause 8.2.
✅ Lesson: Submission ≠ Approval. Always track Notice dates to prove compliance.
⚖️ Scenario 4: The Delay is Partly the Contractor’s Fault, and Partly the Employer’s
“Sure, I was late, but the Employer didn’t give approvals on time either.”
Welcome to the murky waters of concurrent delay.
- Under Clause 8.5 (2017), if the delay is due to both parties, the Engineer must assess EOT fairly based on rules in the Special Provisions. If none exist, he assesses using “all relevant circumstances”1. FIDIC Yellow Book 20….
- The 1999 edition is similar—but less explicit about concurrency protocols.
🚧 If you don’t have concurrency rules in your contract? Expect long arguments and maybe a trip to Dispute Avoidance/Adjudication Board (DAAB).
✅ Lesson: Always define concurrency treatment in your Particular Conditions—ideally aligned with industry standards like the SCL Delay Protocol.
🛑 Scenario 5: Contractor Misses the Time for Completion—Now What?
“We didn’t make it in time. What happens next?”
Clause 8.2 has been breached. That automatically activates Clause:
- 8.7 in 1999 or 8.8 in 2017 = Delay Damages per day of delay,
- But capped at a maximum amount stated in the Appendix to Tender or Contract Data1. FIDIC Yellow Book 20…1. FIDIC Yellow Book 19….
⚖️ Delay Damages:
- Must be a reasonable estimate of the Employer’s loss.
- Cannot be punitive.
- Do not relieve the Contractor of the obligation to finish the Works.
✅ Lesson: Delay Damages are financial pain, not a shortcut to completion. You still have to finish the job.
🧮 Bonus Scenario: What if the Employer Wants to Take Over Early?
“We want to start using the facility before completion. Can we?”
Yes—under Clause 10.2, the Employer can take over Parts of the Works. But:
- This does not count as Time for Completion being achieved,
- The Contractor still has to meet Clause 8.2 for the rest of the Works,
- Risks of damages, disruption, and insurance liabilities need to be considered.
✅ Lesson: Early use ≠ completion. Make sure your clause interactions (insurance, risk transfer, defect notification) are tightly coordinated.
💡 Final Thoughts on “What Ifs” for Clause 8.2
Scenario | Clause Involved | FIDIC’s Stance |
---|---|---|
Tests not done | 8.2 + 9.1 | ❌ Not complete |
Tests failed | 9.4 + 11.4 | Possible rejection or price cut |
Docs submitted but not approved | 10.1 | ❌ Not complete |
Concurrency | 8.5 (2017) | EOT depends on Special Provisions |
Missed deadline | 8.7 / 8.8 | 💸 Delay damages apply |
Employer takes over early | 10.2 | 🚧 Partially valid, but 8.2 still governs completion |
🧾 6️⃣ Suggestions for Clarity and Improvement of Clause 8.2 [Time for Completion]
📌 First: What’s Already Strong About Clause 8.2?
- ✅ Clearly states that completion = testing + documentation + readiness for Taking Over.
- ✅ Links time-bound delivery to performance testing (Clause 9) and handover readiness (Clause 10.1).
- ✅ Aligns across both editions with few contradictions.
But even a well-built clause can leave a few windows open during a storm. So let’s look at:
⚠️ Where Could Ambiguity Arise?
1. 🔍 Ambiguity in the phrase “completion… for the purposes of taking over”
Both editions of Clause 8.2 say the Works are to be completed “for the purposes of taking over under Clause 10.1.” But this phrase could mean different things unless explicitly linked to the documents and approvals required under Clause 10.1:
- 🗂️ As-Built Records (Clause 5.6),
- 📘 O&M Manuals (Clause 5.7),
- 👨🏫 Training (Clause 5.5),
- 🧪 Tests on Completion (Clause 9).
✅ Suggestion: In the Particular Conditions (PCs), list these items as a checklist of conditions precedent to deeming the Works “complete.”
🔧 Particular Condition Example:
“For the purposes of Sub-Clause 8.2, ‘completion’ shall include:
(i) Successful completion and approval (or deemed approval) of all Tests on Completion as per Sub-Clause 9.1;
(ii) Notice of No-Objection issued (or deemed issued) for As-Built Records under Sub-Clause 5.6 and O&M Manuals under Sub-Clause 5.7;
(iii) Completion of training under Sub-Clause 5.5, where specified.”
2. ⏳ Lack of Guidance on Delays from Document Approvals
Let’s say the Contractor submits the O&M Manuals on time—but the Engineer takes 40 days to respond. Is that delay counted against the Contractor?
Clause 10.1 and Clause 5.7 are silent on approval timelines, which could cause disputes.
✅ Suggestion: Add specific durations for review and approval of documentation, e.g.:
“The Engineer shall provide a Notice of No-Objection (or justified rejection with reasons) within 14 days of receipt. Failure to respond shall be deemed as No-Objection.”
This also aligns with GP4, which requires reasonable timeframes for all actions1. FIDIC Yellow Book 20….
3. 🧪 No Threshold for Acceptable Test Failure
Clause 9.4 allows the Engineer to reject the Works or accept with a price reduction if the Works fail Tests on Completion. But it’s subjective what counts as “substantially depriving the Employer” of the Works.
✅ Suggestion: Define acceptable performance bands in the Employer’s Requirements or in a PC:
“For the purposes of Sub-Clause 9.4 and 8.2, failure of a Section to achieve [>95% capacity], [≤2% leakage], or [<3 sec. response time] shall not be deemed substantial, unless otherwise stated.”
This gives the Engineer a benchmark and the Contractor a fair expectation.
4. 🗺️ Inconsistent Section Handover Logic
Clause 8.2 refers to “each Section (if any),” but there’s no default logic for how Sections interact—for example:
- Can a failed Section delay the Taking Over of others?
- Can Sectional Delay Damages be imposed separately?
✅ Suggestion: In the Contract Data or PCs, clarify the logic:
“Each Section shall be assessed independently for the purposes of Clause 8.2, Clause 8.8 (Delay Damages), and Clause 10.1. Delay in one Section shall not impact the Taking Over or delay assessments of another unless expressly stated.”
This supports GP2—which demands clarity, structure, and avoids unintentional overlaps1. FIDIC Yellow Book 20….
✨ Bonus Enhancements Aligned with FIDIC Golden Principles
🔧 Area | Suggested Enhancement | GP Aligned |
---|---|---|
Document Review Timelines | Add fixed review durations (e.g. 14 days) | GP4 |
Risk Allocation in Test Failures | Define thresholds or tolerances | GP3 |
Clear Link to Clause 10.1 Requirements | Insert explicit checklist | GP2 |
Concurrent Delay Resolution | Reference SCL Protocol or national law | GP3 |
Section Completion Logic | Define interdependence of Sections | GP2 |
✍️ Practical Template – PCs Text (Based on GP2)
Here’s a suggested Particular Condition (PC) format:
Sub-Clause 8.2 [Time for Completion] – Amended
The Contractor shall complete the Works and each Section (if any) within the respective Time for Completion, including:
(i) Passing all Tests on Completion as per Clause 9.1;
(ii) Submission and Engineer’s Notice of No-Objection (or deemed approval) of all As-Built Records under Sub-Clause 5.6 and O&M Manuals under Sub-Clause 5.7, within 14 days of submission;
(iii) Completion of any required training as per Clause 5.5.
For avoidance of doubt, delay by the Engineer in providing such No-Objection shall be deemed to justify an Extension of Time.
This format:
- ✅ Respects the original GCs (GP1),
- ✅ Clarifies roles and timelines (GP2, GP4),
- ✅ Maintains balanced risk (GP3).
🧾 7️⃣ Final Takeaways on Clause 8.2 [Time for Completion]
📌 The Big Picture
Clause 8.2 might look deceptively short—but it’s one of the most powerful clauses in the entire FIDIC Yellow Book. It defines what it really means to finish the job. And spoiler alert: it’s not just about bricks and concrete. It’s about:
- 🔄 Completing all contractual obligations,
- 🧪 Passing Tests on Completion,
- 🗂️ Submitting all documents,
- 🏁 Becoming eligible for Taking Over.
In short: Clause 8.2 = your golden key to “job done.”
🧠 Top Lessons You Can’t Ignore
✅ Completion isn’t just construction.
You need:
- Passed tests (Clause 9),
- All handover documents approved (Clause 10.1),
- Any required training finished (Clause 5.5).
📆 Programme is your survival tool.
Under Clause 8.3, your submitted programme must clearly lead to 8.2. If not? You’ve already broken the path to completion.
⏳ Delay? You’d better have followed the EOT procedure.
Whether it’s Clause 8.4 (1999) or 8.5 (2017)—if delays hit, notify early, justify clearly, and tie them to how they impact actual completion under Clause 8.2.
💸 Delay = Damages.
If you miss the Time for Completion, Clause 8.7/8.8 means:
- You’ll owe Delay Damages,
- And they’ll keep accumulating until you cross the Clause 8.2 finish line.
🔄 Why This Clause Connects So Deeply
Connected Clause | Why It Matters |
---|---|
Clause 8.3 – Programme | Tracks your path to Clause 8.2 compliance |
Clause 8.4/8.5 – EOT | Adjusts the Time for Completion if justified |
Clause 9 – Tests | Must be passed for 8.2 to be satisfied |
Clause 10.1 – Taking Over | Can’t happen unless 8.2 is fulfilled |
Clause 5.6/5.7 – Docs | Documents required before completion |
Clause 8.6/8.7 – Progress & Damages | Monitor delays, apply financial pressure |
🛠 Suggestions You Should Seriously Consider
📌 Use Particular Conditions to:
- List all items required for Taking Over clearly,
- Define timelines for Engineer’s approvals,
- Set test performance tolerances,
- Clarify Section-wise Time for Completion logic.
📌 Align with FIDIC Golden Principles:
- GP2 – Make obligations crystal clear,
- GP3 – Maintain a fair risk balance between Contractor and Employer,
- GP4 – Ensure timeframes are realistic and enforceable.
🔚 Final Thought:
If you treat Clause 8.2 as just a date on a calendar—you’ll miss its power. But if you treat it as the culmination of smart planning, precise testing, and proactive coordination—you’ll be in full control of handover, commercial closure, and client satisfaction.
✅ Clause 8.2 [Time for Completion] – Compliance Checklist
🆔 | ✅ Requirement | 🔍 Description | ☑️ Check |
---|---|---|---|
1 | Physical Completion | Has the entire scope of the Works (or Section) been physically completed as per the Contract? | ☐ |
2 | Tests on Completion | Have all Tests on Completion been successfully passed as per Clause 9? | ☐ |
3 | As-Built Records | Have As-Built Records been submitted and received a Notice of No-Objection (Clause 5.6)? | ☐ |
4 | O&M Manuals | Have Operation and Maintenance (O&M) Manuals been submitted and approved (Clause 5.7)? | ☐ |
5 | Training | Has the required training (if applicable) been completed and documented (Clause 5.5)? | ☐ |
6 | Testing Notices | Has the Contractor issued the required notices for testing and submission timelines (Clause 9.1)? | ☐ |
7 | Sectional Requirements | Have all Section-specific requirements (if any) been completed and verified? | ☐ |
8 | Engineer Acknowledgment | Has the Engineer acknowledged or deemed to have acknowledged the readiness for Taking Over? | ☐ |
9 | Timely Completion | Was the Time for Completion achieved within the contractual deadline (including any approved EOT)? | ☐ |
10 | Evidence Readiness | Is there documentation to support each requirement above in case of dispute? | ☐ |
📨 Sample Letters for Clause 8.2 Scenarios
📩 Letter 1: Notification of Completion of Works (Triggering Clause 10.1 via Clause 8.2)
Subject: Notification of Completion of the Works and Readiness for Taking Over
Contract: [Project Name], Contract No. [XXX]
To: The Engineer
Date: [Insert Date]
Dear [Engineer’s Name],
In accordance with Sub-Clause 8.2 [Time for Completion] and Sub-Clause 10.1 [Taking Over of the Works], we hereby notify you that the Works (or Section [specify]) have been completed in full, including:
- Successful passing of all Tests on Completion (as per Clause 9),
- Submission of As-Built Records and O&M Manuals,
- Completion of training requirements (where applicable).
We request that a joint inspection be scheduled to verify readiness and that the Taking-Over Certificate be issued accordingly.
Yours sincerely,
[Authorized Contractor’s Representative]
📩 Letter 2: Request for Time Extension due to Delays Affecting Clause 8.2
Subject: Notice of Delay Affecting Time for Completion – Request for EOT
To: The Engineer
Date: [Insert Date]
Dear [Engineer’s Name],
Pursuant to Sub-Clause 8.5 [Extension of Time], we hereby give notice that completion of the Works under Clause 8.2 is likely to be delayed due to the following reasons beyond our control:
- [Describe cause: e.g., late approvals, adverse weather, variations, Employer-caused delays]
This delay affects our ability to complete the Works by the current Time for Completion. We respectfully request the Engineer’s assessment and an Extension of Time under Clause 20.2 (2017) / 20.1 (1999), supported by records and updated programmes.
Yours faithfully,
[Authorized Contractor’s Representative]
📩 Letter 3: Notification of Readiness for Tests on Completion (Related to Clause 8.2)
Subject: Notification of Readiness for Tests on Completion under Clause 9
To: The Engineer
Date: [Insert Date]
Dear [Engineer’s Name],
As required under Sub-Clause 9.1 [Tests on Completion] and referenced in Clause 8.2, we hereby notify that the Works (or Section) are now ready for testing. Kindly find attached our proposed Testing Schedule and procedures.
Please confirm the date and time for the joint testing activities and ensure your representatives are present. These tests are essential to fulfill our obligations under Clause 8.2, enabling the Taking-Over process.
Yours sincerely,
[Authorized Contractor’s Representative]
📩 Letter 4: Request for Confirmation of Engineer’s Acceptance of Deliverables
Subject: Request for Confirmation of Acceptance – Clause 8.2 Deliverables
To: The Engineer
Date: [Insert Date]
Dear [Engineer’s Name],
We wish to confirm that all contractual deliverables under Clause 8.2 required for Taking Over have been submitted, including:
- As-Built Records (Clause 5.6),
- O&M Manuals (Clause 5.7),
- Training records (Clause 5.5),
- Testing results under Clause 9.
We kindly request your formal Notice of No-Objection or feedback on any pending items. Your timely response is necessary to proceed with the request for Taking Over under Clause 10.1.
Yours faithfully,
[Authorized Contractor’s Representative]
📩 Letter 5: Employer’s Early Taking Over Request (Clause 10.2, Linked with Clause 8.2)
Subject: Request for Early Taking Over of Part of the Works
To: The Engineer
Date: [Insert Date]
Dear [Engineer’s Name],
In accordance with Clause 10.2 [Taking Over of Parts of the Works], we, the Employer, request to take over [specific part or Section] of the Works before full completion under Clause 8.2.
We understand that this early use may affect the Contractor’s remaining obligations and will coordinate with the Contractor to agree on the implications regarding access, risk transfer, and insurance.
Kindly confirm your agreement and proceed with appropriate documentation.
Yours sincerely,
[Employer’s Authorized Representative]