Understanding Clause 5.7: The Importance of Operation and Maintenance Manuals

66 / 100 SEO Score

Views in the last 30 days: 45

Estimated read time: 11 minute(s)

Table of Contents

🧭 1️⃣ Purpose of Clause 5.7

📕 1999 Edition:

The purpose of Clause 5.7 in the 1999 Yellow Book is to ensure that, before the Works are taken over by the Employer, the Contractor provides documentation necessary for the Employer to operate, maintain, dismantle, reassemble, adjust, and repair the Plant. This provision is tied directly to the Taking-Over Certificate under Sub-Clause 10.1, meaning that without the delivery of these manuals, the Works cannot be considered complete for the purposes of Taking-Over.

This clause reflects the 1999 contract’s broader design philosophy: placing essential deliverables like manuals into the completion criteria, but with minimal procedural guidance or definition of scope or content.

📘 2017 Edition:

The 2017 edition significantly expands and formalizes the Contractor’s obligations. Now referred to with a defined term – “O&M Manuals” – the manuals must be:

  • Comprehensive,
  • Kept up-to-date,
  • Submitted in both provisional and final form,
  • Reviewed formally under Sub-Clause 5.2.2 [Review by Engineer].

Additionally, the 2017 edition clarifies what the manuals must contain, such as:

  • Detailed instructions for operation, maintenance, adjustment of the Works and Plant,
  • Instructions for dismantling and reassembly,
  • An inventory of spare parts for ongoing maintenance.

The clause emphasizes performance criteria compliance, linking the manuals with the Schedule of Performance Guarantees, making them not just operational tools but instruments of performance assurance.

🔁 Historical Context:

  • The 2017 changes were driven by practical difficulties observed under the 1999 contract where the lack of clarity and procedural rigour led to disputes or delays in Taking-Over.
  • The 2017 clause reflects increased attention to whole-life asset management and Employer risk mitigation.

🧱 2️⃣ Breakdown of Clause 5.7

Let’s deconstruct each key element and compare how it’s handled in each edition:

Element📘 FIDIC 2017📕 FIDIC 1999
Defined TermIntroduces “O&M Manuals” as a formal term used consistently in the contract.No defined term; simply refers to “operation and maintenance manuals”.
Content RequirementsManuals must include: (i) detailed procedures for operation, maintenance, adjustment; (ii) instructions for dismantling and repair; (iii) spare parts inventory.Only requires enough detail to operate, maintain, dismantle, reassemble, adjust, and repair the Plant. No mention of spare parts or performance compliance.
Level of DetailTied to Employer’s Requirements and performance standards. Must support the Employer in ensuring performance criteria are met.More general; depends on Employer’s Requirements, but less emphasis on performance metrics.
Provisional SubmissionMust submit provisional O&M Manuals before Tests on Completion. These are reviewed under Sub-Clause 5.2.2.Provisional manuals must be supplied before Tests on Completion, but there is no reference to formal review or approval.
Review and CorrectionIf defects are found during testing, Contractor must rectify at own cost. Engineer reviews both provisional and final versions.No explicit requirement to rectify errors in the manuals.
Final Submission and Taking-OverFinal O&M Manuals must be submitted before Taking-Over, and reviewed by the Engineer again.Final manuals must be submitted before Taking-Over; they are a precondition to issuing the Taking-Over Certificate.

🔍 3️⃣ Key Interpretations and Implications

📌 Key Obligations of the Contractor (2017):

  • Prepare O&M Manuals consistent with performance criteria.
  • Update them as needed during the course of the Works.
  • Submit both provisional (before Tests) and final (before Taking-Over) versions.
  • Rectify any errors in the manuals found during testing.

✅ Implications for the Employer:

  • Improved clarity on what is expected from the Contractor.
  • Enhanced ability to operate and maintain the facility post-handover.
  • Ability to withhold Taking-Over if final O&M Manuals are not delivered or are insufficient.

🚨 Risks in the 1999 Version:

  • Potential for ambiguity or inconsistency due to lack of definitions and review procedures.
  • Absence of a formal mechanism to correct or reject deficient manuals could delay project closeout or compromise long-term operability.
  • Dispute potential is higher due to general language.

🔄 4️⃣ Cross-Referencing with Other Clauses

To fully understand how Clause 5.7 fits into the broader contractual framework, it’s crucial to examine its interaction with several related clauses:

📘 FIDIC 2017 Cross-References:

🔗 Clause 5.2 [Contractor’s Documents]

  • Sub-Clause 5.2.2 [Review by Engineer] governs the review process for all Contractor-submitted documents, including the O&M Manuals.
  • The Engineer has the authority to review, comment on, or reject the provisional and final versions. This ensures that the manuals are subject to professional oversight.

🔗 Clause 9 [Tests on Completion]

  • The provisional O&M Manuals must be submitted before these tests begin.
  • If issues are found during testing that relate to the manuals (e.g., discrepancies or missing instructions), the Contractor must rectify them at its own cost.

🔗 Clause 10.1 [Taking Over the Works and Sections]

  • Final O&M Manuals are an express precondition to issuing the Taking-Over Certificate.
  • If not submitted in compliance with Clause 5.7 and not accepted by the Engineer, Taking-Over is delayed, which may lead to potential liability for delay damages under Clause 8.8.

🔗 Schedule of Performance Guarantees

  • Clause 5.7 explicitly states that the manuals must allow the Employer to maintain operations in line with performance guarantees.
  • Failure to provide manuals that support such compliance may trigger performance-related disputes or non-conformities.

📕 FIDIC 1999 Cross-References:

🔗 Clause 5.1 [General Design Obligations]

  • Implies the Contractor’s responsibility for ensuring that all design documentation, including manuals, supports the proper functioning of the Works.

🔗 Clause 10.1 [Taking Over]

  • As with the 2017 edition, manual submission is a Taking-Over prerequisite.
  • However, there is no mention of a review or approval mechanism.

🔗 Clause 9 [Tests on Completion]

  • The 1999 edition is silent on the interplay between testing and the quality or completeness of manuals.

📌 Summary of Cross-Referencing Implications:

  • The 2017 edition integrates Clause 5.7 into a coherent documentation lifecycle, with clear procedural steps, rights of review, and performance alignment.
  • The 1999 version treats manuals more as a static handover deliverable, with fewer safeguards or defined review processes.

🤔 5️⃣ What If Scenarios?

What if the Contractor submits outdated or incomplete manuals?

  • 2017: The Engineer can reject under Sub-Clause 5.2.2. Contractor must update them at no cost. Employer may delay Taking-Over.
  • 1999: Engineer could delay Taking-Over, but lacks explicit authority or process for resubmission and review, leading to grey areas.

What if manuals are complete but fail to include spare parts inventory (2017 only)?

  • This would be a breach of Clause 5.7. Engineer may refuse to accept them as “final” and withhold Taking-Over Certificate.

What if manuals contain errors that affect operations post-Taking-Over?

  • 2017: If identified during Tests on Completion, the Contractor must rectify them. If identified post-Taking-Over, the issue may fall under Clause 11 [Defects].
  • 1999: No clear route for Employer recourse unless explicitly covered in the Employer’s Requirements.

💡 6️⃣ Suggestions for Clarity and Improvement

When assessing Clause 5.7, clarity and practical applicability are crucial. Below are enhanced recommendations to improve contract clarity and avoid ambiguity, with examples:

🛠️ For FIDIC 1999:

  1. Define “operation and maintenance manuals” as a formal term:
    • Add a definition in Clause 1.1 (Definitions) similar to the 2017 edition.
    • 🔄 Example: “O&M Manuals” means the documents that describe the operation, maintenance, adjustment, dismantling, and repair procedures of the Plant, in accordance with the Employer’s Requirements.
  2. Introduce a document review process:
    • Incorporate a clause similar to Sub-Clause 5.2.2 of 2017.
    • 🔄 Example Addition: “The Engineer shall review the submitted O&M Manuals and notify the Contractor of any required revisions within 14 days.”
  3. Clarify timing and approval procedures:
    • Specify submission deadlines relative to milestones (e.g., “Provisional manuals must be submitted 14 days before commencement of Tests on Completion.”)
  4. Add requirements for digital formatting:
    • Specify acceptable file formats (e.g., PDF, CAD, XML) and delivery media (USB, cloud portal).
    • 🔄 Example: “O&M Manuals shall be submitted in both hard copy and editable digital format.”
  5. Enumerate minimum content requirements:
    • List core sections expected in the manuals (e.g., system overview, troubleshooting guide, spare parts list).

🛠️ For FIDIC 2017:

  1. Add specific deadlines for final submissions:
    • 🔄 Example: “Final O&M Manuals shall be submitted no later than 7 days before the date for the Taking-Over Certificate.”
  2. Clarify the Engineer’s response window:
    • 🔄 Example: “The Engineer shall issue comments or approval within 14 days of receipt.”
  3. Detail consequences for late or defective submission:
    • 🔄 Example: “If the final O&M Manuals are not accepted within the time required, the Contractor shall be liable for delay damages as per Clause 8.8.”
  4. Require version control and update logs:
    • 🔄 Example: “Each manual shall include a version number, revision date, and a record of amendments.”
  5. Cross-reference with Employer’s operational needs:
    • 🔄 Example: “Manuals must support preventive maintenance schedules identified in the Employer’s Requirements.”

📌 Summary of Suggested Improvements:

  • ✅ Define key terms.
  • ✅ Introduce procedural clarity (reviews, timelines).
  • ✅ Expand on formatting and submission expectations.
  • ✅ Align documentation with long-term operational goals.
  • ✅ Reduce risk of disputes through clearer obligations.

These suggestions not only improve legal precision but also make the clause more practical and enforceable on real-world projects.

Let me know if you’d like sample clause rewrites or integration into Particular Conditions!


🧩 7️⃣ Final Takeaways

📌 Clause 5.7 is central to the smooth handover and successful long-term operation of the Works.

🚀 2017 Edition Advances:

  • Transforms manuals from an “afterthought” to a technical and legal deliverable.
  • Enhances Employer protection and contract enforceability.
  • Reflects modern best practices in O&M documentation.

🧱 1999 Edition Risks:

  • Lacks precision and enforceability.
  • Relies heavily on good drafting in the Employer’s Requirements.
  • More susceptible to disputes and non-conformance during handover.

Would you like this in a formatted report or table format for inclusion in a project manual or tender documentation?

✅ 📋 Practical Checklist for Clause 5.7 Compliance (FIDIC 2017)

RequirementReferenceCompleted
Prepare comprehensive O&M ManualsClause 5.7, para 1[ ]
Include details for operation, maintenance, adjustmentClause 5.7, para 2(a)[ ]
Include procedures for dismantling, reassembly, repairClause 5.7, para 2(b)[ ]
Add inventory of spare parts for long-term maintenanceClause 5.7, para 2(c)[ ]
Submit provisional manuals before Tests on CompletionClause 5.7, para 3[ ]
Rectify any defects found during testing at own costClause 5.7, para 4[ ]
Submit final manuals before Taking-Over CertificateClause 5.7, para 5[ ]
Engineer reviews provisional and final versionsClause 5.2.2[ ]

✅ 📋 Practical Checklist for Clause 5.7 Compliance (FIDIC 1999)

RequirementReferenceCompleted
Submit provisional manuals before Tests on CompletionClause 5.7, sentence 1[ ]
Ensure manuals allow operation, maintenance, repair, etc.Clause 5.7, sentence 1[ ]
Submit final manuals prior to Taking-OverClause 5.7, sentence 2[ ]
Include any additional manuals required by Employer’s RequirementsClause 5.7, sentence 2[ ]

📄 Sample Letter 1: Submission of Provisional O&M Manuals (FIDIC 2017)

To: The Engineer
Subject: Submission of Provisional Operation and Maintenance Manuals
Date: [Insert Date]
Contract Reference: [Insert Contract Name & Number]

Dear [Engineer’s Name],

In accordance with Sub-Clause 5.7 [Operation and Maintenance Manuals] and Sub-Clause 5.2.2 [Review by Engineer] of the Conditions of Contract, we hereby submit the provisional Operation and Maintenance Manuals for the [Works / Section].

The submitted documents include:

  • Detailed procedures for operation and maintenance,
  • Dismantling and reassembly guidance,
  • Spare parts inventory,
  • Supporting diagrams and instructions.

We kindly request your review and comments, if any, within the contractual timeframe.

Yours sincerely,
[Contractor’s Representative]


📄 Sample Letter 2: Rectification of Errors Found During Tests

To: The Engineer
Subject: Rectification of Errors in O&M Manuals Identified During Tests on Completion
Date: [Insert Date]
Contract Reference: [Insert Contract Name & Number]

Dear [Engineer’s Name],

Further to the testing activities carried out on [date], and as per your comments dated [reference], we acknowledge the deficiencies found in the provisional Operation and Maintenance Manuals.

In compliance with Clause 5.7, we have rectified the errors and updated the documents accordingly. The revised manuals are enclosed herewith for your further review and confirmation.

Please advise if any further clarification or modifications are needed.

Sincerely,
[Contractor’s Representative]


📄 Sample Letter 3: Submission of Final O&M Manuals for Taking-Over

To: The Engineer
Subject: Submission of Final Operation and Maintenance Manuals for Taking-Over
Date: [Insert Date]
Contract Reference: [Insert Contract Name & Number]

Dear [Engineer’s Name],

Pursuant to Clause 5.7 [Operation and Maintenance Manuals] and as a condition precedent to issuance of the Taking-Over Certificate under Clause 10.1, we hereby submit the final version of the Operation and Maintenance Manuals.

These manuals incorporate:

  • Corrections based on your review of the provisional version,
  • All updates identified during Tests on Completion,
  • Full compliance with Employer’s Requirements and Performance Guarantees.

Please confirm acceptance or notify us of any outstanding issues requiring attention.

Sincerely,
[Contractor’s Representative]


📄 Sample Letter 4: Engineer’s Request for Correction or Resubmission

To: The Contractor
Subject: Request for Revision of Submitted O&M Manuals
Date: [Insert Date]
Contract Reference: [Insert Contract Name & Number]

Dear [Contractor’s Name],

Following our review of the provisional Operation and Maintenance Manuals submitted on [insert date], we have identified certain deficiencies, as detailed below:

  1. Missing procedures for [specific system],
  2. Incomplete spare parts list,
  3. Lack of alignment with the Employer’s Requirements under the Schedule of Performance Guarantees.

In accordance with Sub-Clause 5.7 and Sub-Clause 5.2.2, you are hereby requested to revise and resubmit the documents within [e.g., 7 days] of receipt of this letter.

Should you require clarification, please liaise with our office.

Yours faithfully,
[Engineer’s Name]

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top