Views in the last 30 days: 52
Estimated read time: 18 minute(s)
1ď¸âŁ Purpose of Clause 5.8 [Design Error]
1999 Edition: The purpose of Clause 5.8 [Design Error] is to establish a clear and unambiguous responsibility on the Contractor for any errors, omissions, ambiguities, inconsistencies, inadequacies, or defects found in the Contractorâs Documents. These âDocumentsâ include the design-related deliverables prepared by the Contractor under the Contract, such as drawings, specifications, manuals, calculations, and other technical materials (as defined in Clause 1.1.6.1).
â This clause effectively safeguards the Employerâs interests by ensuring the Contractor cannot later shift the blame to the Engineer or claim that prior approval absolves them of responsibility.
đ Implications for the Parties:
- Contractor: Fully liable for quality and correctness of their design documentation, even post-approval.
- Engineer: Can approve or comment but does not assume liability through their actions.
- Employer: Gains protection from downstream issues caused by design defects.
2017 Edition: This clause maintains the same core objective of contractor accountability, but introduces a more structured, integrated approach by:
- Expanding coverage to include the Contractorâs actual design, not just documentation.
- Explicitly directing the resolution process through Sub-Clause 7.5 [Defects and Rejection].
- Clarifying the contractual effect of a prior Notice of No-objection given by the Engineer (under Sub-Clause 5.2.2).
â This evolution reflects FIDICâs increased focus on clarity and integrated defect resolution processes.
đ Practical Enhancements:
- Greater procedural guidance for how design errors are to be corrected.
- Emphasis on risk retention by the Contractor despite Engineerâs No-objection.
- Reduction of ambiguity around the Engineer’s review function.
đ°ď¸ Historical Context: The 2017 version arose in response to:
- Disputes around Engineer approvals being perceived as “certifications.”
- Increasing legal pressure for clarity in design-build contracts.
- The desire to link quality issues to structured processes (e.g., Clause 7.5).
2ď¸âŁ Breakdown of Clause 5.8 [Design Error]
đ 1999 Edition Full Text:
âIf errors, omissions, ambiguities, inconsistencies, inadequacies or other defects are found in the Contractorâs Documents, they and the Works shall be corrected at the Contractorâs cost, notwithstanding any consent or approval under this Clause.â
đ§ Key Terms Explained:
- Errors, omissions, ambiguities, inconsistencies, inadequacies, or other defects: Broad language captures a wide range of potential issues, from technical calculation errors to misalignments between documents.
- Contractorâs Documents: Defined in Clause 1.1.6.1, includes all technical deliverables.
- Shall be corrected: Mandatory language indicating non-negotiable obligation.
- At the Contractorâs cost: The burden is entirely on the Contractor, reinforcing risk allocation.
- Notwithstanding any consent or approval: Even if the Engineer reviewed and approved the documents, liability remains with the Contractor.
đ 2017 Edition Full Text:
âIf errors, omissions, ambiguities, inconsistencies, inadequacies or other defects are found in the Contractorâs design and/or the Contractorâs Documents, they and the Works shall be corrected in accordance with Sub-Clause 7.5 [Defects and Rejection]. If such Contractorâs Documents were previously the subject of a Notice of No-objection given (or deemed to be given) by the Engineer under Sub-Clause 5.2.2 [Review by Engineer], the provisions of Sub-Clause 5.2.2 shall apply as if the Engineer had given a Notice in respect of the Contractorâs Documents under sub-paragraph (b) of Sub-Clause 5.2.2.
All corrections and resubmissions under this Sub-Clause shall be at the Contractorâs risk and cost.â
đ§ Expanded and Clarified:
- Adds âContractorâs designâ to clarify liability includes original engineering decisions, not just documentation.
- Embeds compliance with Clause 7.5, thus connecting to a formal defect rejection and remedy procedure (e.g., timelines, inspection obligations).
- Introduces nuanced handling where the Engineer has previously issued a Notice of No-objection â doesn’t eliminate Contractor liability but adjusts procedural consequences.
- Final sentence reinforces that risk and cost remain with the Contractor, preserving the principle of self-responsibility.
3ď¸âŁ Key Interpretations and Implications
đ¨ Absolute Liability for Design Quality:
Even with Engineer approval or No-objection, the Contractor cannot escape liability for design flaws.
â Risk Is Not Shifted by Engineerâs Review:
In both editions, whether the Engineer approved or gave No-objection has no bearing on the Contractor’s liability. This addresses a common misconception in disputes.
đ Introduction of Clause 7.5 in 2017:
- Brings in a formal mechanism for rejection, timelines for remedy, and the Contractorâs duty to respond.
- Creates a more controlled and auditable correction pathway.
đĄ Implications of the No-Objection Clause:
- 1999: Does not distinguish between approval and review types.
- 2017: Differentiates formal “No-objection” (non-binding) and explains its procedural role. See Sub-Clause 5.2.2(b), which allows the Engineer to re-invoke correction obligations without contractual conflict.
đ Summary of Impacts:
- đ ď¸ Contractor must design, review, and check rigorously â internal QA/QC is critical.
- đ§ž Employer is insulated from liability, even for approved documents.
- âď¸ Dispute boards and arbitral panels have clearer grounds to enforce Contractor liability.
4ď¸âŁ Cross-Referencing with Other Clauses
âHow does Clause 5.8 play with its clause-friends across the contract?â
Great question. Letâs unpack this step by step.
đŻ Core Idea Behind Cross-Referencing
Think of Clause 5.8 [Design Error] as a watchdog guarding the quality of design inputs. But this watchdog isnât barking in isolation â it interacts with several other clauses that shape what happens before, during, and after a design error shows up.
Weâll walk through the key supporting cast that give 5.8 its practical teeth.
đ§Š 1999 Edition â Cross-Linked Clauses
đ Clause 1.8 [Care and Supply of Documents]
Before anything is reviewed or constructed, this clause ensures the Contractor keeps the design documents on site and is responsible for their safekeeping.
đĄ Relevance to Clause 5.8:
- If something goes wrong in the Contractorâs Documents, they canât claim âoops, I lost the file!â Theyâre fully responsible for having and maintaining accurate, up-to-date designs.
đ Clause 5.2 [Contractorâs Documents]
This one sets the scene for how designs are prepared, submitted, and reviewed.
đ ď¸ The Engineer reviews the Contractorâs Documents and can either approve them or request changes. Butâand hereâs the kickerâeven if the Engineer gives a green light, Clause 5.8 still puts the risk squarely on the Contractor.
â ď¸ Contractor Trap to Avoid:
âBut the Engineer approved this!â
Nope! Clause 5.8 is crystal clear: approval doesn’t mean liability transfer.
đ Clause 3.5 [Engineerâs Determinations]
Hereâs the judge in our contract court. If a dispute arises about whether something really is a âdesign errorâ or not, the Engineer is empowered to make a determination.
đŹ Why it matters: If the Contractor resists a correction citing it’s ânot a true error,â the Engineer can decide under this clauseâand Clause 5.8 kicks in to say the Contractor must correct at their cost if the determination goes against them.
đ Clause 11.1 [Completion of Outstanding Work and Remedying Defects]
This one governs the Defects Notification Period. If a design error manifests after practical completion, Clause 11.1 works in tandem with Clause 5.8 to ensure the Contractor still fixes itâno escape!
â Itâs not âout of sight, out of mindâ once you hand over the keys.
âď¸ 2017 Edition â Cross-Linked Clauses
The 2017 edition tightens up the web of connections even more.
đ Clause 5.2.2 [Review by Engineer]
This is the upgraded, clearer version of the review process. It introduces the term “Notice of No-objection” â which replaces vague approvals.
đŻ Key takeaway: Even if the Engineer says âno objection,â the Contractor is still on the hook for any errors in the design. Clause 5.8 spells this out by looping back to 5.2.2 and clarifying that No-objection â Design Approval.
đŹ Think of this like a teacher saying, âYou may proceed with your project,â not âI promise this will work.â
đ Clause 7.5 [Defects and Rejection]
This is a BIG one.
In the 2017 edition, if thereâs a design error, you donât just âfix it and move on.â Now it kicks off a formal process:
- Engineer rejects the defective Works or design.
- Contractor gets notified and must remedy the issue within a defined timeframe.
- The whole cycle becomes traceable, manageable, and enforceable.
đ Clause 5.8 in 2017 explicitly refers to 7.5 â giving design corrections structure, enforceability, and a timeline.
đ Clause 3.7 [Agreement or Determination]
In case there’s disagreement over whether the Contractorâs design is actually defective, this clause kicks in.
đ Think of it like a decision hub:
- First, the Parties try to agree.
- If that fails, the Engineer issues a determination.
- If someone still disagrees, they can escalate via the Dispute Avoidance/Adjudication Board (DAAB).
This gives Clause 5.8 backup in disputes: if the Contractor resists a correction, the contract has a defined route to resolve it.
đ Clause 11.1 [Completion of Outstanding Work and Remedying Defects]
As with 1999, any issues discovered after the Works are handed over â even during the Defects Notification Period â still require correction.
đ In practice: if a faulty design causes a problem 6 months post-handover, Clause 5.8 + 11.1 = “Contractor, fix it on your dime.”
đ Supporting Players
- Clause 4.1 [Contractorâs General Obligations]: Binds the Contractor to deliver a complete and functional design.
- Clause 4.9 [Quality Management]: The Contractor should have quality systems in place to catch design errors before submission.
Together, they give real-world strength to Clause 5.8 â itâs not just about what to do after something goes wrong, itâs also about how to prevent errors in the first place.
đ Summary Table: Clause 5.8 Interactions
Related Clause | Edition | Purpose | Why It Matters to 5.8 |
---|---|---|---|
1.8 | 1999 | Care of Documents | Contractor owns and manages design data |
5.2 | 1999 | Document Submission | Starts the Engineer review process |
3.5 | 1999 | Engineerâs Determination | Resolves disputes about what is an âerrorâ |
11.1 | Both | Defect Rectification | Design issues post-handover must still be fixed |
5.2.2 | 2017 | Review by Engineer | No-objection â No liability |
7.5 | 2017 | Defects & Rejection | Gives a procedural path to corrections |
3.7 | 2017 | Agreement/Determination | Dispute path if error is denied |
4.1 & 4.9 | 2017 | General Obligations & Quality | Contractor must prevent and fix design flaws |
5ď¸âŁ What-If Scenarios?
đ Scenario 1:
Contractorâs HVAC system design has an airflow miscalculation discovered during commissioning. The Engineer had previously issued a No-objection.
- 1999: Contractor must correct at their own cost; No-objection has no protective value.
- 2017: Same outcome. Correction must be made in accordance with Clause 7.5, and No-objection is acknowledged but doesn’t shield the Contractor.
đ Scenario 2:
The Engineer fails to spot a structural error during document review and gives full approval. Later, the error causes a construction delay.
- Contractor still bears cost and time impact.
- Possible recourse: Clause 20 (Claims) if delay was exacerbated by Engineer’s action â but design error correction cost is still non-recoverable.
6ď¸âŁ Suggestions for Clarity and Improvement
âWhat could we tweak in Clause 5.8 to make life easier for everyone?â
When a clause holds such significant liability and technical complexity, the smallest ambiguity can lead to big disputes. Letâs break down how Clause 5.8 can sometimes create confusionâand how we might clarify it using smart drafting, illustrative examples, and clear definitions.
đŻ 1. Clarify What Qualifies as a “Design Error”
Right now, both versions of Clause 5.8 refer broadly to:
âerrors, omissions, ambiguities, inconsistencies, inadequacies or other defects…â
đ What’s unclear?
These terms are not defined anywhere in the General Conditions.
đ§Š Why it matters:
Contractors and Employers may interpret these differently. For instance:
- Is a design that meets performance specs but uses unconventional methods an error?
- Is a lack of detailing in the drawing an âomissionâ or just incomplete scope?
â Suggested Improvement:
đ Include a definition or Annex defining âDesign Errorâ with categories like:
- Calculation mistake (e.g., miscalculated beam load)
- Code non-compliance (e.g., not meeting Eurocode 2 for concrete design)
- Functional failure (e.g., HVAC not delivering airflow required)
- Ambiguity in instructions (e.g., conflicting dimensions between sections)
đ§ Example:
If the Contractorâs drawings show a beam size of â300mm x 400mmâ in one section and â450mm x 600mmâ in another, is this an âambiguityâ or just a mistake?
Clause 5.8 should explicitly handle these inconsistencies by example or definition.
đŻ 2. Make the Engineerâs âNo-objectionâ Meaning Crystal Clear
In 2017, the clause does a better job by referencing Sub-Clause 5.2.2, but thereâs still room to clarify what a âNo-objectionâ meansâand more importantly, what it doesnât mean.
đ Common Misunderstanding:
âThe Engineer gave me a No-objection, so if thereâs a problem, itâs their fault.â
Wrong! But the wording could do more to close the door on that line of argument.
â Suggested Improvement:
Add a statement in Clause 5.8 like:
âFor the avoidance of doubt, the Engineerâs Notice of No-objection under Sub-Clause 5.2.2 shall not relieve the Contractor of any obligation or liability under this Sub-Clause.â
đ§ Example:
Letâs say the Contractor designs a retaining wall using soil anchors. The Engineer issues a No-objection. Months later, it collapses due to under-designed anchorage lengths.
đ The Contractor might argue: âBut I got a No-objection!â
A stronger Clause 5.8 would squash this by stating the No-objection doesn’t shift liability.
đŻ 3. Introduce Timeframes for Corrections
Currently, Clause 5.8 says errors âshall be corrected,â but doesnât specify how quickly.
đ Thatâs risky. Why?
Without deadlines, a Contractor might delay action, claiming theyâre âassessingâ or âwaiting for redesign.â
â Suggested Improvement:
Add a phrase like:
âThe Contractor shall propose corrective measures within 7 days of being notified of the error and complete corrections within a reasonable period, as instructed by the Engineer.â
đ§ Example:
A pump station design has the wrong pipe gradients. The Engineer finds this issue during review. Without a deadline, the Contractor could stall. With a timeline built in, it triggers immediate action.
đŻ 4. Specify Consequences for Non-Compliance
While the clause says the Contractor must correct at their âown cost and risk,â it doesnât explicitly link failure to correct with the Employerâs right to step in or claim damages.
đ Thatâs a gap you donât want during a live project!
â Suggested Improvement:
Add language such as:
âIf the Contractor fails to correct any design error within the timeframe stated by the Engineer, the Employer shall be entitled to engage third parties to perform such corrections, and recover the associated costs from the Contractor.â
đ§ Example:
Letâs say the electrical design fails to consider voltage drop over long cable runs. The Contractor refuses to acknowledge the issue. Under this enhanced clause, the Employer can fix it and backcharge.
đŻ 5. Reference Technical Standards for Evaluation
When does an error really count as an error? Without a benchmark, itâs subjective.
đ Smart move: tie design obligations to specific codes or industry standards, where possible.
â Suggested Improvement:
âThe Contractorâs design shall comply with the Employerâs Requirements and with applicable codes such as [e.g., ISO, EN, ASME, NFPA] unless otherwise specified. Design errors shall be evaluated with reference to these standards.â
đ§ Example:
An MEP subcontractor designs HVAC ducting using outdated ASHRAE guidelines. This leads to insufficient air changes. Clause 5.8 would benefit from referencing ASHRAE or relevant standards as the benchmark for âerror.â
đŻ 6. Encourage Internal QA and Peer Review
Right now, Clause 5.8 assumes design will be correctâbut doesnât encourage the Contractor to adopt preventive measures.
đ If we want fewer design errors, letâs build quality into the contract, not just react to mistakes.
â Suggested Improvement:
Require that the Contractor include a peer-review process or design verification checks as part of their Quality Assurance Plan under Clause 4.9.
đ§ Example:
Require something like:
âEach critical design element shall be reviewed and signed off internally by a qualified engineer who did not prepare the original design.â
đŻ This not only prevents design errorsâit gives the Employer a clearer picture of the Contractorâs competence and accountability.
đ Final Summary of Section 6 Suggestions
Area | Issue | Proposed Fix | Example |
---|---|---|---|
Definition | Broad terms like âerrorsâ undefined | Add glossary or examples | Misaligned column sizes |
No-objection | Misinterpreted as approval | Explicit disclaimer | Retaining wall failure |
Timeframes | No urgency for fixes | Add deadlines for response and correction | Pipe gradient error |
Consequences | No stated remedy for inaction | Employer can step in and charge | Electrical voltage issue |
Standards | No objective criteria | Reference codes like EN, ISO | HVAC air flow misdesign |
Prevention | No QA process required | Mandate design peer-review | Structural design check |
7ď¸âŁ Final Takeaways
đ Key Insights:
- Both editions maintain strong accountability for design quality on the Contractor.
- 2017 improves procedural clarity and links design error resolution into defect control workflows.
- No-objection â approval â a critical distinction to educate project teams on.
đŻ Practical Applications:
- Contractors should implement rigorous design verification, peer review, and internal sign-off.
- Employers can rely on this clause as a risk shield â especially helpful in multi-disciplinary, design-heavy projects.
â Clause 5.8 Compliance & Quality Control Checklist
(FIDIC Yellow Book 1999 & 2017 Editions)
đ For Contractors: Pre-Submission Design Review
Item | Description | â Check |
---|---|---|
1 | Have all design calculations been verified independently? | â |
2 | Are all drawings and specifications internally peer-reviewed? | â |
3 | Do the design documents comply with the Employerâs Requirements? | â |
4 | Are applicable technical standards (e.g., EN, ISO, ASME) clearly followed and cited? | â |
5 | Are all design assumptions documented and traceable? | â |
6 | Are all drawing revisions recorded and change logs maintained? | â |
7 | Have ambiguities and inconsistencies between drawings and specifications been resolved? | â |
8 | Has a design QA/QC checklist been completed and signed off internally? | â |
9 | Has Clause 5.8 been reviewed with the design team for liability awareness? | â |
đ§° For Engineers: Design Review & No-Objection Checks
Item | Description | â Check |
---|---|---|
1 | Was the review completed within the stipulated review period (see Clause 5.2.2)? | â |
2 | Has the Engineer refrained from issuing âapprovalsâ and instead used âNo-objectionâ where applicable? | â |
3 | Were any comments or rejections properly documented and communicated? | â |
4 | Has the Engineer verified that the Contractor understands that a No-objection does not transfer liability? | â |
5 | Have previous issues or known design risks been addressed in the current submission? | â |
6 | Has the Engineer maintained a record of all No-objection notices issued? | â |
đ ď¸ For Contractors: Responding to Identified Design Errors (Post-Submission)
Item | Description | â Check |
---|---|---|
1 | Has the Contractor acknowledged the design error in writing? | â |
2 | Has a correction plan been submitted within the required period (suggested: 7 days)? | â |
3 | Has the Engineer approved or rejected the proposed correction method? | â |
4 | Are all associated Works affected by the design error being revised simultaneously? | â |
5 | Have costs and delays been evaluated internally for possible claims under Clause 20 (if applicable)? | â |
6 | Has the Contractor ensured that similar errors are not repeated in other areas of the design? | â |
âď¸ For Employers: Oversight & Risk Mitigation
Item | Description | â Check |
---|---|---|
1 | Is the Contractorâs QA system compliant with Clause 4.9? | â |
2 | Are there protocols to ensure timely Engineer reviews of Contractorâs Documents? | â |
3 | Have disputes arising from design error been tracked and escalated properly (via Clause 3.7 or Clause 21)? | â |
4 | Is the Employerâs team aware that even with Engineer No-objection, liability remains with the Contractor? | â |
5 | Have provisions for backcharging corrections (if Contractor fails to act) been clearly understood? | â |
đ Sample Letter
đ Sample Letter #1: Engineer Notifies Contractor of a Design Error
Scenario: The Engineer has discovered a design inconsistency in the Contractorâs Documents.
Title: Notice of Design Error â Request for Correction
[Engineerâs Letterhead]
[Date]
To: [Contractorâs Name]
[Contractorâs Address]
Subject: Notice of Design Error â Clause 5.8 [Design Error]
Dear [Contractorâs Representative],
We refer to your submission dated [Submission Date] concerning [Description of Document â e.g., Structural Design Drawings for Pump Station].
Upon review, we have identified the following issue:
[Briefly describe the issue â e.g., The beam sizing shown in Section A-A (300mm x 400mm) conflicts with Section B-B (450mm x 600mm)].
In accordance with **Clause 5.8 [Design Error]**, you are hereby notified that the above constitutes a design inconsistency. You are requested to:
- Provide corrected documents, and
- Propose corresponding corrective measures for the Works already executed (if applicable),
within **[insert reasonable period, e.g., 7 days]** from the date of this Notice.
Please note, as per Clause 5.8, all such corrections shall be at your own risk and cost, notwithstanding any prior Notice of No-objection provided.
Yours faithfully,
[Engineerâs Name]
[Title]
cc: Employer
đ Sample Letter #2: Contractor Responds Acknowledging the Design Error
Scenario: Contractor agrees there is a design error and outlines the corrective action.
Title: Acknowledgement and Corrective Action for Design Error
[Contractorâs Letterhead]
[Date]
To: [Engineerâs Name]
[Engineerâs Address]
Subject: Response to Notice of Design Error â Clause 5.8
Dear [Engineerâs Name],
We acknowledge receipt of your Notice dated [Engineerâs Letter Date] regarding the design inconsistency in [Description of Documents].
Upon internal review, we confirm that an error exists in the submitted design documents. In accordance with **Clause 5.8 [Design Error]**, we propose the following corrective actions:
1. Revision of the affected drawing [Drawing No. XYZ], with corrected dimensions.
2. Removal and reconstruction of the Works already affected, namely [describe works], to align with the updated design.
The revised documents are enclosed herewith for your review. We confirm that the above actions will be undertaken at our own cost and risk.
Kindly confirm if the proposed measures meet your requirements so we may proceed without delay.
Yours sincerely,
[Contractorâs Representative]
[Title]
cc: Employer
đ Sample Letter #3: Contractor Disputes the Alleged Design Error
Scenario: Contractor believes the design is correct and disputes the Engineerâs Notice.
Title: Response to Alleged Design Error â Request for Determination
[Contractorâs Letterhead]
[Date]
To: [Engineerâs Name]
[Engineerâs Address]
Subject: Dispute of Design Error Allegation â Clause 5.8
Dear [Engineerâs Name],
We refer to your Notice dated [Date] alleging a design error in [Document Name or Section].
Following a detailed review, we respectfully disagree with the assertion that the subject matter constitutes a design error. Our submission complies with the applicable standards [specify standard/code], and was developed in accordance with the Employerâs Requirements.
Given the differing views, we hereby request that the matter be addressed under **Clause 3.7 [Agreement or Determination]**. We remain committed to resolving this issue promptly and professionally.
Please advise on the next steps for consultation.
Yours faithfully,
[Contractorâs Representative]
[Title]
cc: Employer
đ Sample Letter #4: Employer Backcharges Contractor for Failure to Correct Error
Scenario: Contractor failed to correct the design error, so the Employer engaged a third party to do so.
Title: Recovery of Costs for Unrectified Design Error â Clause 5.8
Employerâs Letterhead]
[Date]
To: [Contractorâs Name]
[Contractorâs Address]
Subject: Cost Recovery for Third-Party Correction â Clause 5.8
Dear [Contractorâs Representative],
We refer to the unresolved design error concerning [Design Topic] notified by the Engineer on [Date], and your failure to provide or implement a timely correction.
In accordance with **Clause 5.8 [Design Error]**, and due to your non-compliance, we engaged an independent third party to implement corrective works. The total cost incurred was [insert amount], supported by the attached invoices.
This amount will be deducted from your next interim payment, or otherwise recovered per the terms of the Contract.
Yours sincerely,
[Employerâs Representative]
[Title]
cc: Engineer