Site icon Navigating Knowledge Across Domains

Unlocking the Power of FIDIC Clause 5.5 Training

image 57

🧠 1️⃣ Purpose of Clause 5.5 [Training]

Okay, so let’s start with the big question: why is training even in the contract?

Well, in design-build projects, especially those involving complex plants or systems, the Employer is going to inherit a shiny new facility. But here’s the kicker: if the Employer’s team doesn’t know how to use it or maintain it properly, it can lead to all sorts of problems—breakdowns, safety issues, poor performance—you name it.

That’s where Clause 5.5 steps in. It’s all about making sure the Contractor doesn’t just deliver the physical asset, but also the know-how to keep it running smoothly. The clause requires the Contractor to train the Employer’s personnel—those who’ll be responsible for day-to-day operations and maintenance.

👥 Who benefits?


📖 2️⃣ Breakdown of Clause 5.5 [Training]

Let’s look at how the clause reads in both editions and unpack the layers.


📘 1999 Edition (Original Flavor)

Here’s the core wording:

“The Contractor shall carry out the training of Employer’s Personnel in the operation and maintenance of the Works to the extent specified in the Employer’s Requirements. If the Contract specifies training which is to be carried out before taking-over, the Works shall not be considered to be completed […] until this training has been completed.”​

So, what’s it saying?

🔍 But notice what’s missing?


📙 2017 Edition (New and Improved)

Here’s how FIDIC upgraded the language:

“The Contractor shall carry out training of employees of the Employer (and/or other personnel identified in the Employer’s Requirements) […] If the Employer’s Requirements specify training which is to be carried out before taking over, the Works shall not be considered to be completed […] until this training has been completed […] The Contractor shall provide qualified and experienced training staff, training facilities and all training materials as necessary.”​

Let’s break that down:

🔧 What’s new?

📌 In short, the 2017 edition puts more flesh on the bones. It anticipates practical needs and gives both sides a clearer map of what’s expected.


⚖️ 3️⃣ Key Interpretations and Implications

Here’s where things get juicy. Let’s interpret what the clause means in the real world:

✅ Training is not a “nice to have”—it can be a gatekeeper.

If training is specified as a precondition to Taking Over, then no training = no certificate. This delays revenue generation, warranty periods, and final payments.

📌 Scope must be clear—or it’s a minefield.

The Employer’s Requirements need to say who gets trained, on what, when, and how long. If it’s vague, the parties could argue about what “sufficient” training means. (Trust me—it happens!)

🚨 Risk to the Contractor:

If training isn’t done properly or on time:


🔗 4️⃣ Cross-References You Should Know

Clause 10.1 [Taking Over the Works and Sections]

📂 Clause 5.2 [Contractor’s Documents]

📣 Clause 20.1 [Contractor’s Claims]

Clause 8.5 [Extension of Time for Completion]

This is a critical clause when training delays affect Taking Over or completion dates​​.

Delays related to Employer-caused impediments (such as not nominating trainees or giving site access for training) are valid grounds for EOT, but again must be claimed via Clause 20.


🤔 5️⃣ What If Scenarios

Let’s explore some realistic situations you might face.

What if training is delayed because the Employer didn’t nominate staff?

➡️ The Contractor could raise a claim under Clause 20, and potentially get an extension of time (EOT) under Clause 8.5.

What if the training is completed, but the Employer says it was “unsatisfactory”?

➡️ If the Employer’s Requirements don’t set quality metrics, this becomes subjective and a potential source of dispute. A lesson in specifying outcomes clearly in the ERs!

Can training be subcontracted?

➡️ Yes, but it should still meet the contractual standards and ideally be flagged to the Engineer. And the Contractor retains the liability.


✍️ 6️⃣ Suggestions for Clarity and Improvement

To reduce ambiguity and keep things smooth:

🧩 Clarify the training scope:

📅 Fix the timing:

✅ Add confirmation mechanism:


🔚 7️⃣ Final Takeaways

Let’s wrap it all up:

Clause 5.5 is deceptively short but super impactful—especially for operational handovers.

📌 The 1999 edition left a lot open to interpretation. The 2017 version tightens the screws and raises the bar on training delivery.

🚨 Contractors: Don’t treat this as an afterthought. Training can be a make-or-break milestone for Taking Over.

💡 Practical tip: Draft a “Training Plan” early on and get it reviewed as part of your Submittals. That way, everyone’s expectations are aligned.

📋 Clause 5.5 [Training] Compliance & Coordination Checklist

Checklist ItemRelevant ClauseDetails / Notes
Has the scope of training (who, what, how) been clearly defined in the Employer’s Requirements?Clause 5.5Should include list of trainees, subjects, format (theory/hands-on), and duration.
Has the timing of the training been explicitly stated?Clause 5.5If not specified, 2017 edition defaults to “as acceptable to the Employer.”
Has the Contractor developed and submitted a Training Plan?Clause 5.5 & 5.2Include methodology, materials, schedule, trainers, and assessment.
Has the Engineer reviewed and approved the training materials (manuals, guides, presentations)?Clause 5.2These fall under Contractor’s Documents and may require review.
Are training staff, facilities, and materials provided by the Contractor as required?Clause 5.5 (2017 only)Ensure staff are qualified and facilities are adequate.
Is the training documented with attendance sheets, feedback forms, and completion records?Clause 5.5Critical for demonstrating compliance.
Has the Employer confirmed satisfactory completion of the training?Clause 10.1Required for issuance of Taking-Over Certificate (if training is a precondition).
If delayed, has the Contractor submitted a claim for EOT due to Employer-caused training delays?Clause 8.5 + 20.1Must follow notification and substantiation timelines.
If delayed, has a cost claim been submitted under Clause 20.1 (with records)?Clause 20.1Applies if delay is due to Employer (e.g., late nomination of trainees).
Is the training completion date aligned with the Taking Over schedule?Clause 10.1Misalignment may delay Taking Over.

📩 Letter 1: Submission of Training Plan and Schedule

From: Contractor
To: The Engineer
Subject: Submission of Training Plan in Accordance with Clause 5.5


Dear [Engineer’s Name],

Pursuant to Clause 5.5 [Training] of the Conditions of Contract, we hereby submit our proposed Training Plan for the Employer’s Personnel as specified in the Employer’s Requirements.

The attached plan includes:

We kindly request your review and feedback. If acceptable, we propose commencing training on [proposed date], subject to confirmation of the Employer’s nominated personnel.

Please confirm if the attached plan meets the requirements or advise of any further modifications.

Yours faithfully,
[Contractor’s Representative]
[Contractor’s Name]


📩 Letter 2: Notice of Employer’s Delay in Nominating Personnel for Training

From: Contractor
To: The Engineer
Subject: Notice of Delay – Training Pending Nomination of Employer’s Personnel (Clause 20.1 and 5.5)


Dear [Engineer’s Name],

We refer to our previous correspondence dated [date] regarding training of Employer’s Personnel under Clause 5.5 [Training].

To date, we have not received the list of personnel to be trained, which is required to finalize the training schedule and commence sessions. We believe this delay may affect the timeline for completion and Taking Over of the Works as outlined in Clause 10.1.

Accordingly, and pursuant to Clause 20.1 [Contractor’s Claims], we hereby notify the Employer of a potential claim for extension of time and/or associated Costs, pending resolution of this matter.

We respectfully request the Engineer’s assistance in facilitating prompt nomination by the Employer.

Yours sincerely,
[Contractor’s Representative]
[Contractor’s Name]


📩 Letter 3: Confirmation of Training Completion

From: Contractor
To: The Engineer
Subject: Confirmation of Completion of Training Under Clause 5.5


Dear [Engineer’s Name],

We confirm that the training of Employer’s Personnel, as required under Clause 5.5 [Training] and detailed in the Employer’s Requirements, was successfully completed on [date].

Attached are:

We respectfully request confirmation that the training requirement has been fulfilled, to allow progression toward the Taking-Over Certificate as per Clause 10.1.

Should any further documentation or clarification be required, please advise.

Best regards,
[Contractor’s Representative]
[Contractor’s Name]


📩 Letter 4: Engineer’s Confirmation of Training Completion (from Engineer to Employer)

From: Engineer
To: Employer
Subject: Confirmation of Contractor’s Completion of Training Obligation


Dear [Employer’s Name],

Following the Contractor’s submission and execution of the training program required under Clause 5.5 [Training], and based on our review of submitted records and feedback, we confirm that this obligation has been satisfactorily completed.

This satisfies the condition precedent to Taking Over (where applicable), and we consider the training requirement closed unless advised otherwise.

Please confirm your agreement or advise of any outstanding matters requiring resolution.

Sincerely,
[Engineer’s Name]
[Engineer’s Company]

Exit mobile version