Views in the last 30 days: 62
Estimated read time: 19 minute(s)
1ļøā£ Purpose of Clause 13.6 (1999) / Clause 13.5 (2017)
Letās start with the real-world angle: Not every part of a construction project is predictable. Some work just pops up on-siteāmaybe a hidden pipe, an unforeseen obstruction, or a last-minute change. Thatās where Daywork comes in.
Daywork allows the Engineer to instruct work on a time and materials basisāinstead of trying to negotiate a price on the fly. It only applies when a Daywork Schedule is part of the Contract.
FIDIC’s intent: This clause acts as a safety valve. It ensures that minor or reactive changes can be logged, tracked daily, and paid fairly without holding up progress or sparking disputes.
š„ Who Benefits?
- Contractor: Gets paid fairly for extra workāif it’s documented correctly.
- Engineer: Can issue instructions quickly and transparently.
- Employer: Pays only for verified, documented work.
š§ Why FIDIC Includes This
Because construction is unpredictable. Instead of pretending otherwise, FIDIC gives us a structured way to handle the surprisesāwithout breaking the contract flow.
š In Summary
- Deals with minor, incidental, or unpredictable work.
- Based on time, materials, and equipment usedādocumented daily.
- Requires a Daywork Schedule to apply.
- Relies on real-time Engineer oversight and agreement.
This clause is all about staying fair, flexible, and transparent when the job throws a curveball. And it almost always does. šÆ
š What does the Contractor need to do?
The Contractor canāt just start racking up hours and expect payment. Hereās the process, step-by-step:
- Daily Records: The Contractor must submit daily statements, and this is critical. These must include:
- š·āāļø Names and occupations of all workers involved.
- ā±ļø The exact time each one spent on the task.
- šļø Details of Contractorās Equipment used (what, when, how long).
- š¦ Quantities and types of Plant and Materials used or supplied.
- Engineerās Signature: These daily sheets need to be signed by the Engineer, ideally the same day. Why? Because this signature validates that the resources were actually used and the work was real. No signature = dispute risk. šāļø
- Supporting Evidence: If Goods (like fittings or spare parts) are purchased for the Daywork, the Contractor must provide:
- Quotations
- Supplier invoices
- Delivery notes
- Any other proof the Engineer reasonably asks for
- Final Valuation: The Contractor later submits a priced statement using the rates in the Daywork Schedule. This goes into the next Payment Certificate (Clause 14.6).
šļø Daily Records ā with a digital twist
Here’s where the 2017 edition tightens the bolts:
- The Contractor must submit daily statements showing the people, plant, and materials involved.
- These must be provided:
- In duplicate hard copy AND
- Electronically (e.g., spreadsheet, PDF log, or through a digital site tool).
- The data should be traceable to records maintained under Sub-Clause 6.10 [Contractorās Records] (personnel logs, equipment usage records, etc.).
š§ Pro Tip: FIDIC is trying to align with BIM and modern digital site tools here. Expect digital audits and QR code logs to be acceptable supporting documents.
šø Submitting the Claim
Once the Engineer verifies the records, the Contractor:
- Compiles a priced Daywork Statement based on the resources agreed or determined.
- Appends the invoices, delivery notes, receipts, etc.
- Submits this with the next Statement for payment (Clause 14.3).
- The Engineer adds the verified value to the next Interim Payment Certificate (Clause 14.6).
And one more neat touch: the clause states that unless otherwise noted, the Daywork rates include taxes, overhead, and profit. š§¾ No hidden mark-ups!
2ļøā£ Breakdown of Clause 13.6 (1999) and Clause 13.5 (2017)
Letās break this down as if we were preparing our site team to handle a Daywork instruction tomorrow morning. š ļø
š¹ š FIDIC 1999 ā Clause 13.6 [Daywork]
So, here’s the deal under the 1999 versionāDaywork is basically the go-to method when the variation is too uncertain or fiddly to measure and price ahead of time. You know those situations where the Engineer says, “Just do itāweāll sort the value laterā? Thatās when Clause 13.6 kicks in.
Butāit only applies if your Contract includes a Daywork Schedule. Thatās key. If that schedule isnāt in the contract, youāre out of luck using this clause. š« No backdoor entry here!
š When can Daywork be used?
- Only if instructed by the Engineer.
- Typically for minor or incidental workāso weāre not talking about major structural changes. Think repairs, small adjustments, or unexpected site clean-up.
š¹ š FIDIC 2017 ā Clause 13.5 [Daywork]
Now letās talk evolution. The 2017 version doesnāt throw out the old rulebookāit upgrades it with more clarity, fairness, and a touch of modern project management (yes, hello electronic reporting!).
š” When does it apply?
Same as before: only if thereās a Daywork Schedule in the Contract and the Engineer specifically instructs the Contractor to carry out work on a daywork basis.
But the š 2017 version goes further. It sets up a pre-check mechanism for materials and Goods not priced in the Daywork Schedule.
š Buying Unpriced Goods? Here’s the drill:
- Before buying, the Contractor must submit at least two quotations.
- The Engineer can either:
- Approve one,
- Instruct which to use, or
- Stay silent.
- If the Engineer says nothing for 7 days, the Contractor can go ahead and choose any of the submitted quotationsātheir discretion is now valid. ā
That 7-day silence rule is newāand it solves a common issue where the Engineer āghostsā the decision and delays procurement.
āļø Side-by-Side Summary
š 1999 Edition | š 2017 Edition |
---|---|
Requires Daywork Schedule ā | Same ā |
Only Engineer can instruct ā | Same ā |
Daily signed records required š | Requires paper + digital records šš» |
No procedure for unpriced Goods š§¾ | Includes quotation and approval flow for unpriced Goods š¬ |
Engineer’s silence = no action ā | After 7 days of silence, Contractor can proceed š¦ |
No reference to Sub-Clause 6.10 | Cross-refers to Sub-Clause 6.10 for accurate site records š |
No clarification on what rates include | Specifies that rates include tax, profit, and overhead šµ |
š Engineerās Daywork Sign-Off Sheet
In accordance with Clause 13.5 [Daywork] ā FIDIC Yellow Book 2017
š ļø Contractorās Daywork Checklist
Based on FIDIC Yellow Book š 2017 – Clause 13.5 [Daywork]
ā 3ļøā£ Key Interpretations and Implications ā Letās Get into the Nitty-Gritty
So, whatās the big deal with Daywork?
Well, Daywork is that special drawer in the FIDIC toolbox that you pull open when something pops up thatās small, urgent, or unquantifiable in advance. Think: minor cable reroutes, unexpected patch-ups, or fiddly tasks the Engineer didnāt see coming when pricing was done.
But hereās where it gets juicyāunderstanding what Clause 13.6 (1999) and Clause 13.5 (2017) actually mean in practice, and how they protect (or trip up) each party. Letās go clause by clause, book by book.
In both the š 1999 and š 2017 editions, the Engineer has to initiate the process.
ā Implication? If you’re the Contractor and you go ahead without written instructionāsorry, youāre probably not getting paid under this clause.
š Pro Tip: Always get that instruction in writing. Even better? Get it labeled as āDaywork.ā Saves everyone a headache later.
š ļø In the 1999 edition:
- Contractor must provide daily statements listing:
- Names and job titles of all personnel involved
- Hours worked
- Equipment used (with durations)
- Quantities of materials consumed
š§āš» In the 2017 edition:
- Same idea, but modernized: submit duplicates and an electronic copy
- Tightly linked to Sub-Clause 6.10 (Contractorās Records)
- Engineer must agree to the resources before they get priced
š If you skip them? You could lose entitlement to Daywork payments. Like doing the work without punching the clock!
šÆ If using materials not listed in the Daywork Schedule:
- Contractor must submit at least two supplier quotations
- Engineer has 7 days to pick one
- If silent? Contractor may choose any submitted quote
š Interpretive Twist: That 7-day “silence = consent” rule is a subtle but powerful way to keep site operations moving.
- Overheads
- Contractorās profit
- Taxes
ā 1999 left this open to interpretationāwhich meant more room for disputes. The 2017 update smartly shuts this door.
š Drafting tip: Always double-check whatās ābaked intoā the Daywork Scheduleāand spell out exclusions in Particular Conditions if needed.
š 1999 ā Go to Clause 3.5 (Determination)
š 2017 ā Youāre off to Clause 3.7 (Agreement or Determination), which has:
- Defined consultation steps
- Clear timelines
- Engineerās final say, unless disputed again
You canāt just make up the rulesāno Schedule means no fallback.
In that case, you’d revert to pricing the Variation under Clause 13.3 using:
- Market rates
- Cost Plus Profit (if justified)
4ļøā£ Cross-Referencing with Other Clauses ā Letās Connect the Dots š§©
Hereās where the magic of FIDIC really shinesāDaywork doesnāt operate in a vacuum. It actually weaves into several other clauses to ensure the variation is properly instructed, recorded, measured, valued, and finally paid. Letās walk through the most important companion clauses and what roles they play in the Daywork process.
Sub-Clause 6.10: Contractorās Records ā forms the basis for the daily statements.
Sub-Clause 3.7 (2017) / 3.5 (1999): Used if there’s disagreement on daily records or valuations.
Clause 13.3: If Daywork isn’t applicable or too complex, the normal Variation procedure kicks in.
Clause 14.3: Final priced Daywork gets added to interim payment certificates.
In the 2017 edition, Sub-Clause 3.7 formalizes the process:
ā Consultation first (try to reach an agreement).
ā If no agreement in 42 days, the Engineer issues a determination.
ā If either party is unhappy, they can issue a Notice of Dissatisfaction (NOD).
So, if there’s a fight over whatās billable under Daywork, Clause 13.5 points directly to Clause 3.7. Itās like calling in a senior manager to settle a dispute.
This clause requires the Contractor to maintain:
ā Names, occupations, and time worked by personnel.
ā Equipment used (type, time on site).
ā Materials and quantities consumed.
FIDIC 2017 goes a step furtherānow, youāre expected to deliver not just hard copies but also electronic versions of these daily records. These form the basis for the daily Daywork sheets under Clause 13.5.
No records = No payment. Simple.
So, think of Clause 13.3 as the gateway. The Engineer instructs a Variation under 13.3, then directs Daywork under 13.5 (2017) or 13.6 (1999) if appropriate.
Clause 13.5 doesnāt stand aloneāitās a child of the broader variation procedure.
ā Interim Payment Certificates via Clause 14.3.
ā Corrected/adjusted if necessary under Clause 14.6.3 (2017).
So once Daywork records are verified and priced, they flow directly into the payment pipeline through Clause 14. Itās the final stop before the money hits the Contractorās account.
The Schedule defines the agreed rates for:
ā Labor
ā Equipment
ā Materials
FIDIC 2017 even clarifies that unless stated otherwise, these rates include taxes, overheads, and profit. If thereās no Daywork Schedule? Then you fall back to Clause 13.3, and everything must be negotiated.
Under FIDIC 2017:
ā Issue a Notice of Claim within 28 days.
ā Follow up with a Detailed Claim within 84 days.
Your daily records (thanks, Clause 6.10!) become your key evidence. Clause 20 gives you the structured pathway to claim time and/or money if something goes wrong in the Daywork chain.
š§© FIDIC Daywork Clause Interactive Flowchart
Click on any node to explore how Clause 13.5 / 13.6 links to related provisions.
5ļøā£ What-If Scenarios? ā How Daywork Plays Out on the Ground šļø
Because no clause is complete until we see it in action, right? Here’s how Clause 13.5 / 13.6 unfolds in real-world construction settingsāwith some juicy āwhat ifā twists. These examples are grounded in both FIDIC books, the Golden Principles š”, and industry practice.
Scenario | Click to View Explanation |
---|---|
Daywork Schedule is Missing |
š Clause 13.6 / š Clause 13.5 only applies if a Daywork Schedule is included in the Contract. If itās missing, you canāt claim payment on a time-and-materials basis. Instead, you’d revert to Clause 13.3 for traditional valuationāeither agreed rates or fair valuation. Pro tip: Check during tendering whether the Daywork Schedule is included. If not, consider raising it as a risk or requesting it be added. |
Engineer Doesn’t Respond to Quotations |
š Under the 2017 Book, if the Engineer doesnāt respond to your three submitted quotations for unpriced Goods within 7 days, you can proceed with any of them. This avoids project delays, but be cautiousāchoose the most reasonable quote to avoid disputes under Clause 3.7. This protects you from inaction, but puts the burden on your judgment and documentation. |
Engineer Disputes Daily Records |
Daily statements (incl. labour, plant, materials) must be signed by the Engineer or agreed upon. If they disagree, it becomes a “matter” under Clause 3.7 (2017) or 3.5 (1999). Always aim for daily sign-off. If not possible, include photos, timestamps, and logs to protect your entitlement. š§ Without Engineer sign-off, the burden of proof falls heavily on the Contractor. |
Starting Daywork Without Instruction |
No go. Both editions make it clear: Daywork must be instructed by the Engineer. If you proceed without instructionāeven if the work seems minorāyou risk non-payment. Golden Principle 1 reminds us: risk and responsibility must be clearly allocated. Here, the Engineer leads the Daywork process. |
Missed a Daily Statement Submission |
š 1999 expects daily hard-copy reports. š 2017 modernizes it: requires a duplicate paper + electronic version. If you miss the daily submission, your entitlement could be at riskāespecially if work canāt be verified later. Daily reporting is a protective tool. Don’t skip itāmake it routine! |
Engineer Tries to Cut Daywork Value Later |
Once signed and verified daily records are submitted, the Engineer cannot arbitrarily reduce payments unless there’s a genuine error or dispute. Disagreements must follow the fair determination path under Clause 3.7 (or 3.5 in 1999). š”ļø Signed statements act like a shieldāEngineers can’t override them without due process. |
6ļøā£ Suggestions for Clarity and Improvement (Expanded & GP-Aligned) āļøš ļø
Issue: The term āminor or incidentalā is vague and can lead to disputes over Daywork applicability.
Solution: Define this clearly in the Particular Conditions. E.g.: āMinor or incidentalā means any work valued under $5,000 or taking less than two working days.
- GP2: Defines scope clearly
- GP3: Prevents unfair interpretation
Issue: Disagreements arise when records lack consistency.
Solution: Provide a structured Daywork template with fields for labour, plant hours, materials, and photos if needed.
- GP1: Clear communication
- GP2: Structured documentation
Issue: Delayed signatures stall payments.
Solution: Add a clause stating daily records must be reviewed within 48 hours, or they’re deemed accepted.
- GP4: Timely resolution
- GP5: Dispute avoidance
Issue: Misunderstanding about what rates include.
Solution: State: āUnless otherwise noted, Daywork rates include all applicable taxes, overheads, and profit.ā
- GP2: Avoid ambiguity
- GP3: Fair compensation
Issue: Clause 13.5 becomes ineffective without a Daywork Schedule.
Solution: Include fallback language: use actual cost + agreed markup if no schedule is included.
- GP1: Keeps contract operational
- GP3: Equitable risk allocation
Issue: Lack of traceability between daywork and instructions.
Solution: Require reference to the Variation number or instruction (e.g., Clause 13.3) in each daywork report.
- GP2: Improves traceability
- GP5: Simplifies resolution of disputes
Checklist
š Clause 13.5 ā Daywork Checklist (Click to Expand)
# | Checklist Point | Reference (2017/1999) | ā |
---|---|---|---|
1 | Is a Daywork Schedule included in the Contract? | 13.5 / 13.6 | |
2 | Was the Daywork explicitly instructed by the Engineer? | 13.5 / 13.6 | |
3 | Was the work minor or incidental in nature? | 13.5 / 13.6 | |
4 | Were quotations for unpriced Goods submitted? | 13.5 (2017) | |
5 | Did the Engineer respond within 7 days to quotations? | 13.5 (2017) | |
6 | If no response, did Contractor proceed with one quotation? | 13.5 (2017) | |
7 | Were daily statements submitted and signed? | 13.5 / 13.6 | |
8 | Did statements include names, hours, plant, materials? | 13.5 / 13.6 | |
9 | Was an electronic copy submitted? (2017 only) | 13.5 (2017) | |
10 | Were invoices/receipts for materials attached? | 13.5 / 13.6 | |
11 | Was the priced statement submitted for payment? | 14 / 13.5 / 13.6 | |
12 | Were rates applied as per Daywork Schedule (incl. markup)? | 13.5 (2017) | |
13 | Were disputes referred via Clause 3.7 / 3.5 as needed? | 3.7 / 3.5 |
š Sample Letter
Subject: Request for Daywork Instruction ā Minor Variation (Clause 13.5) To: The Engineer From: Contractor Date: [Insert Date] Contract No.: [Insert Contract Number] Project: [Insert Project Name] Dear [Engineerās Name], Pursuant to Clause 13.5 [Daywork] of the Conditions of Contract, we respectfully request your instruction to proceed with the following works on a Daywork basis: - Description of Work: [e.g., Minor pipe rerouting near Column C3] - Location: [Insert Site Location] - Estimated Duration: [e.g., 2 Days] - Reason: [e.g., Unforeseen obstruction requiring immediate resolution] We will submit daily statements accordingly. Please confirm. Yours faithfully, [Authorized Contractor's Rep] [Company Name]
Subject: Daily Statement Submission ā Daywork Activities (Clause 13.5) To: The Engineer From: Contractor Date: [Insert Date] Daywork Reference No.: DW-[001] Dear [Engineerās Name], Please find attached the daily statement for Daywork performed on [Date] under Clause 13.5: - Labor: 2 Pipefitters, 8 hrs each - Plant: 1 Excavator, 5 hrs - Materials: 10m HDPE Pipe DN150 Kindly acknowledge by countersignature. PDF copy also submitted. Sincerely, [Site Engineer] [Company Name] Attachment: DW-001 Daily Statement
Subject: Submission of Quotations for Unpriced Materials under Clause 13.5 To: The Engineer From: Contractor Date: [Insert Date] Dear [Engineerās Name], In line with Clause 13.5 [Daywork], we submit the following quotations for [Insert Item]: 1. Vendor A ā QAR 4,250 2. Vendor B ā QAR 4,700 3. Vendor C ā QAR 4,100 Please advise which to proceed with. Failing response within 7 days, we will act per Clause 13.5. Yours sincerely, [Authorized Representative] [Company Name] Attachments: Vendor Quotations
Subject: Submission of Priced Daywork Statement for Engineerās Certification To: The Engineer From: Contractor Date: [Insert Date] Dear [Engineerās Name], Please find attached our priced Daywork statement for work carried out between [Start Date] and [End Date]. This includes: - Verified resources - Daywork Schedule rates - Supporting invoices We request certification and inclusion in the upcoming IPC. Best regards, [Commercial Manager] [Company Name] Attachments: Priced Daywork Summary
Subject: Notice of Disagreement with Daywork Valuation ā Clause 3.7 Reference To: The Engineer From: Contractor Date: [Insert Date] Dear [Engineerās Name], We note your determination dated [Date] concerning Daywork valuation. Certain labor and plant items were disallowed. We disagree with this and request formal determination under Clause 3.7. Disputed items and justification are attached for your review. Yours faithfully, [Authorized Signatory] [Contractorās Company] Attachments: Comparison Table of Disputed Items